Overall Case Outcomes
In the competitive landscape of real estate, selecting a reliable builder is crucial for ensuring a satisfactory purchase experience. Ansal Housing, a prominent name in the industry, has had its share of successes and challenges, evident from the numerous legal cases brought against it. This blog post delves into the complexities of Ansal Housing's legal landscape, analyzing the patterns in the cases it has faced and won, and providing valuable insights for potential buyers.
Ansal Housing operates across several states, which reflects its expansive portfolio. However, with a significantly higher number of vocal complaints and legal challenges, there is much to analyze regarding its performance in the legal domain.
Ansal Housing has lost a staggering 200 cases, revealing substantial difficulties in legal compliance and project delivery. The predominant reasons for losses can be categorized as follows:
Despite the overwhelming number of lost cases, Ansal Housing has successfully won 28 cases. The common threads in these victories include:
Ansal Housing represents a complex case in the realm of real estate development. With two hundred lost cases, potential clients should approach with caution while also considering the builder's notable successes in navigating certain challenges. Here are some tips for potential buyers:
In summary, while Ansal Housing has strengths in certain areas, the evidence presents a cautionary tale for potential buyers to engage thoroughly and strategically.
Yearly Trend for these Cases
Analysis of the cases filed against Ansal Housing, where the builder lost, revealed significant insights into the common themes and disputes surrounding their projects. The cases can be broadly categorized into several types, including delayed possession claims, refund and compensation disputes, force majeure and unforeseen circumstances, non-compliance with regulatory requirements, and penalties for project delays.
The majority of the cases revolved around delayed possession claims, where buyers sought relief for the builder's failure to deliver units within the stipulated timelines. These claims often cited reasons like force majeure circumstances, orders from various courts, and the National Green Tribunal, which the builder claimed were beyond their control. However, the authorities consistently ruled in favor of the buyers, indicating a pattern where the builder's defenses based on unforeseen circumstances were not accepted.
Refund and compensation disputes were another frequent theme. Buyers who had made substantial payments towards their units sought refunds due to the builder’s inability to provide possession as promised. The builder's claims of having fulfilled their obligations or facing financial difficulties did not stand, leading to multiple rulings mandating refunds along with interest compensation.
Additionally, several cases highlighted issues related to non-compliance with regulatory requirements. Buyers questioned the builder's adherence to the Real Estate (Regulation and Development) Act, 2016, and other municipal regulations, which led to further legal consequences for the builder, including penalties for non-compliance and project delays.
A striking pattern in these cases is the common triggers for litigation, which primarily revolve around the builder's inability to meet project timelines and fulfill their commitments to buyers. The authorities' decisions suggest that the builder's repeated reliance on force majeure claims was not convincing, indicating a systemic issue in project management and compliance rather than isolated incidents of bad luck.
The builder lost these cases predominantly due to insufficient evidence to support their claims of force majeure and unforeseen circumstances. Furthermore, there were instances of non-compliance with legal requirements, resulting in penalties and rulings against the builder. The lack of transparency and fulfilling obligations in accordance with the buyer agreements also contributed to the builder's losses in these cases.
This table provides details of individual cases contributing to the summary above. Click rows to expand content. Use "Show More/Less" buttons below.
Case No. | State | Summary | Topic | Detailed Summary | Appellant | Respondent | Source |
---|---|---|---|---|---|---|---|
Appeal No.49 of 2021Appeal No.49 of 2021 | HaryanaHaryana | The appellant-allottee withdrew from the project,…The appellant-allottee withdrew from the project, and the appeal was dismissed as withdrawn. The appellant-allottee was given liberty to file a fresh complaint for refund before the Ld. Authority. | ["Withdrawal of app…["Withdrawal of appeal", "Fresh complaint for refund"] | {"appellant_claim": "The appellant-allottee wante…{"appellant_claim": "The appellant-allottee wanted to withdraw from the project due to the long delay.", "respondent_claim": "Not applicable", "final_verdict": "The appeal was dismissed as withdrawn, and the appellant-allottee was given liberty to file a fresh complaint for refund.", "in_favor_of_respondent": "no"} | Pawan GuptaPawan Gupta | Ansal Housing Const…Ansal Housing Construction Limited | Link |
51 of 202151 of 2021 | HaryanaHaryana | The appellant-allottee withdrew from the project …The appellant-allottee withdrew from the project and the appeal was dismissed. The appellant-allottee is free to file a fresh complaint for refund within a month, which will be decided expeditiously. | ["Withdrawal of app…["Withdrawal of appeal", "Fresh complaint for refund"] | {"appellant_claim": "The appellant-allottee wants…{"appellant_claim": "The appellant-allottee wants to withdraw from the project and dismiss the appeal.", "respondent_claim": "None", "final_verdict": "The appeal is dismissed as withdrawn. The appellant-allottee is free to file a fresh complaint for refund within a month.", "in_favor_of_respondent": "no"} | Amitabh SandujaAmitabh Sanduja | Ansal Housing Const…Ansal Housing Construction Limited | Link |
RAJ/RERA/C-2018-2303RAJ/RERA/C-2018-2303 | RajasthanRajasthan | The complainant, Anil Chelani, filed a complaint …The complainant, Anil Chelani, filed a complaint against Ansal Housing for delayed possession of a flat in the Ansal Majestic Floor project in Alwar. The RERA authority directed the respondent to register the project, pay penalty, and offer possession to the complainant. | ["Delayed possessio…["Delayed possession", "Project registration"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat and sought relief.", "respondent_claim": "The respondent claimed that the project was completed and that the complainant was not entitled to relief.", "final_verdict": "The RERA authority directed the respondent to register the project, pay penalty, and offer possession to the complainant.", "in_favor_of_respondent": "no"} | Anil ChelaniAnil Chelani | Ansal HousingAnsal Housing | Link |
F.1६ (७2)RAJIRERA/C…F.1६ (७2)RAJIRERA/CI20२1 | RajasthanRajasthan | The case is about non-registration of a real esta…The case is about non-registration of a real estate project by the promoter, Ansal Housing, despite directions from the Rajasthan Real Estate Regulatory Authority. The Authority has decided to prosecute the promoter for non-compliance. | ["Non-registration …["Non-registration of real estate project", "Prosecution of promoter"] | {"appellant_claim": "", "respondent_claim": "", "…{"appellant_claim": "", "respondent_claim": "", "final_verdict": "The Authority has decided to prosecute the promoter for non-compliance with directions to register the real estate project.", "in_favor_of_respondent": "no"} | Ansal HousingAnsal Housing | Link | |
4547 of 20204547 of 2020 | HaryanaHaryana | The complainant sought possession of a flat and c…The complainant sought possession of a flat and compensation for delay. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Compensation"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent had delayed possession of the flat and sought compensation for the same.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had not breached any agreement.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Rakesh SareenRakesh Sareen | Ansal HousingAnsal Housing | Link |
GC No.0504/2021GC No.0504/2021 | PunjabPunjab | Complainants Tarsem Singh Uppal and Jodhbir Singh…Complainants Tarsem Singh Uppal and Jodhbir Singh filed a complaint against Ansal Housing Limited for refund of Rs.1,00,000/- with interest. The authority ordered a refund of Rs.1,00,000/- with interest as per the provisions of Section 18 of the Act. | ["Refund", "Real Es…["Refund", "Real Estate"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that they had paid Rs.1,00,000/- to the respondent for two plots, but the respondent had not provided them with an allotment letter or agreement to sell. The complainants sought a refund of Rs.1,40,000/- with interest.", "respondent_claim": "The respondent claimed that there was no allottee-promoter relationship between the parties, and therefore, the complainants were not entitled to a refund.", "final_verdict": "The authority ordered a refund of Rs.1,00,000/- with interest as per the provisions of Section 18 of the Act.", "in_favor_of_respondent": "no"} | Jodhbir SinghJodhbir Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
85 of 201985 of 2019 | HaryanaHaryana | Complainant Sudhir Singh Yadav filed a complaint …Complainant Sudhir Singh Yadav filed a complaint against M/s Ansal Housing Limited for not handing over possession of a flat within the agreed-upon time. The Haryana Real Estate Regulatory Authority directed the respondent to pay delay possession charges at a prescribed rate. | ["Delay in possessi…["Delay in possession", "Real Estate"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the flat within the agreed-upon time and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had made efforts to complete the project as soon as possible.", "final_verdict": "The authority directed the respondent to pay delay possession charges at a prescribed rate of 10.75% per annum from 30.08.2016 until the offer of possession.", "in_favor_of_respondent": "no"} | Sudhir Singh YadavSudhir Singh Yadav | Ansal Housing Limit…Ansal Housing Limited | Link |
193 of 2021193 of 2021 | HaryanaHaryana | The complainant filed a complaint against Ansal H…The complainant filed a complaint against Ansal Housing Limited for not handing over the possession of a flat despite the due date being 07.03.2016. The authority found the respondent in contravention of section 11(4)(a) of the Act and directed the payment of interest at the rate of 9.30% per annum. | ["Non-handover of p…["Non-handover of possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over the possession of the flat despite the due date being 07.03.2016.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances beyond their control.", "final_verdict": "The authority found the respondent in contravention of section 11(4)(a) of the Act and directed the payment of interest at the rate of 9.30% per annum.", "in_favor_of_respondent": "no"} | Rahul AroraRahul Arora | Ansal Housing Limit…Ansal Housing Limited | Link |
179 of 2020179 of 2020 | HaryanaHaryana | The complainants filed a complaint against the re…The complainants filed a complaint against the respondent for not handing over the possession of the apartment within the stipulated time. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over the possession of the apartment within the stipulated time and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had taken all necessary steps to complete the project.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Richa KanwarRicha Kanwar | Ansal Housing Limit…Ansal Housing Limited | Link |
4884 of 20204884 of 2020 | HaryanaHaryana | The complainants, Mrs. Sushma Bajaj and Mr. Satis…The complainants, Mrs. Sushma Bajaj and Mr. Satish Bajaj, filed a complaint against M/s Ansal Housing Ltd. for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession. | Delay in handing ov…Delay in handing over possession | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the subject apartment within the stipulated time period of 26.02.2017.", "respondent_claim": "The respondent claimed that the delay in handing over possession was due to various circumstances beyond their control, including orders passed by the Punjab and Haryana High Court and the National Green Tribunal.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession.", "in_favor_of_respondent": "no"} | Mr. Satish BajajMr. Satish Bajaj | Ansal Housing Limit…Ansal Housing Limited | Link |
1162 of 20201162 of 2020 | HaryanaHaryana | The complainant filed a complaint against the res…The complainant filed a complaint against the respondent for not handing over the possession of the unit by the due date. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over the possession of the unit by the due date and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and sought an extension of time to complete the project.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Shaila KohliShaila Kohli | Ansal Housing Limit…Ansal Housing Limited | Link |
1761 of 20211761 of 2021 | HaryanaHaryana | The complainants, Mrs. Brij Bala Sood and Mr. Arj…The complainants, Mrs. Brij Bala Sood and Mr. Arjun Sood, filed a complaint against M/s Ansal Housing Ltd. for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the actual handing over of the possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the flat within the stipulated period of 42 months from the date of execution of the agreement.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances beyond their control, including orders from the Hon'ble Punjab & Haryana High Court and the National Green Tribunal.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the actual handing over of the possession.", "in_favor_of_respondent": "no"} | Mr. Arjun SoodMr. Arjun Sood | Ansal Housing Limit…Ansal Housing Limited | Link |
110 of 2021110 of 2021 | HaryanaHaryana | The complainants, Vandana Chauhan and Vijay Singh…The complainants, Vandana Chauhan and Vijay Singh Chauhan, filed a complaint against Ansal Housing Limited for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession. | ["Delay in possessi…["Delay in possession", "Non-compliance of obligations"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the subject apartment within the stipulated period and sought delay possession charges at the prescribed rate.", "respondent_claim": "The respondent claimed that the delay was due to unforeseeable events beyond their control and sought to invoke the force majeure clause.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Vijay Singh ChauhanVijay Singh Chauhan | Ansal Housing Limit…Ansal Housing Limited | Link |
1410 of 20211410 of 2021 | HaryanaHaryana | The complainants filed a complaint against the re…The complainants filed a complaint against the respondent for not handing over the possession of the flat within the stipulated period. The authority directed the respondent to pay the interest at the rate of 9.30% per annum from 14.02.2016 till the date of the order. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over the possession of the flat within the stipulated period of 42 months.", "respondent_claim": "The respondent claimed that the delay in possession was due to various reasons including force majeure.", "final_verdict": "The authority directed the respondent to pay the interest at the rate of 9.30% per annum from 14.02.2016 till the date of the order.", "in_favor_of_respondent": "no"} | Mr. Manoj SehrawatMr. Manoj Sehrawat | Ansal Housing Limit…Ansal Housing Limited | Link |
16 of 202116 of 2021 | HaryanaHaryana | The complainants, Tarun Jain and Kanupriya Jain, …The complainants, Tarun Jain and Kanupriya Jain, filed a complaint against Ansal Housing Limited and Samyak Projects Pvt. Ltd. for delay in possession of a residential unit. The Haryana Real Estate Regulatory Authority directed the respondents to pay interest at the prescribed rate of 9.30% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondents delayed possession of the residential unit beyond the stipulated date.", "respondent_claim": "The respondents claimed that the delay was due to force majeure circumstances such as difficulty in water extraction, NGT orders, and COVID-19.", "final_verdict": "The Haryana Real Estate Regulatory Authority directed the respondents to pay interest at the prescribed rate of 9.30% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Kanupriya JainKanupriya Jain | Ansal Housing Limit…Ansal Housing Limited | Link |
79 of 202179 of 2021 | HaryanaHaryana | The complainants sought delay possession charges …The complainants sought delay possession charges and compensation for not receiving possession of their flat within the stipulated time. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that they did not receive possession of their flat within the stipulated time and sought delay possession charges and compensation.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen events beyond their control and sought to avoid paying interest.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Jayant SinghJayant Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
527 of 2021527 of 2021 | HaryanaHaryana | The complainants, Siddhant Shandilya and Rashmi S…The complainants, Siddhant Shandilya and Rashmi Sinha, filed a complaint against Ansal Housing Limited for delay in possession of their flat in the Estella project. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent delayed the possession of their flat beyond the stipulated period of 36 months.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances beyond their control.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Rashmi SinhaRashmi Sinha | Ansal Housing Limit…Ansal Housing Limited | Link |
4867 of 20204867 of 2020 | HaryanaHaryana | The complainant sought earliest possession of the…The complainant sought earliest possession of the flat along with delay penalty at applicable rate as per HRERA till date of physical possession of the unit with occupancy certificate. The authority directed the respondents to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents failed to hand over possession of the flat within the stipulated period and sought delay penalty at applicable rate as per HRERA.", "respondent_claim": "The respondents claimed that the delay in possession was due to force majeure conditions such as ban on water extraction, NGT orders, and COVID-19.", "final_verdict": "The authority directed the respondents to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession.", "in_favor_of_respondent": "no"} | Vikas LalVikas Lal | Ansal Housing Limit…Ansal Housing Limited | Link |
4835 of 20204835 of 2020 | HaryanaHaryana | The complainants, Mrs. Sushma Arora, Mr. Rakesh K…The complainants, Mrs. Sushma Arora, Mr. Rakesh Kumar, and Mr. Rishi Arora, filed a complaint against Ansal Housing Limited for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% per annum for every month of delay on the amount paid by the complainants. | Delay in possession…Delay in possession of flat | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the flat within the stipulated period of 36 months from the date of execution of the agreement.", "respondent_claim": "The respondent claimed that the delay in possession was due to various reasons, including obtaining occupation certificate and completion of super structure.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% per annum for every month of delay on the amount paid by the complainants.", "in_favor_of_respondent": "no"} | Mr. Rishi AroraMr. Rishi Arora | Ansal Housing Limit…Ansal Housing Limited | Link |
1294 of 20211294 of 2021 | HaryanaHaryana | The complainant, Deepti Singh, filed a complaint …The complainant, Deepti Singh, filed a complaint against Ansal Housing Limited for not handing over the possession of a flat in the Estella project despite paying the full amount. The Haryana Real Estate Regulatory Authority (HRERA) directed the respondent to pay interest at the rate of 9.30% per annum for the delay in possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that she paid the full amount for the flat but the respondent did not hand over the possession despite the due date being 25.08.2015.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances including demonetization and NGT orders.", "final_verdict": "The HRERA directed the respondent to pay interest at the rate of 9.30% per annum for the delay in possession.", "in_favor_of_respondent": "no"} | Deepti SinghDeepti Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
417 of 2020417 of 2020 | HaryanaHaryana | The complainant sought delay possession charges a…The complainant sought delay possession charges and delivery of possession of the shop/office space. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession. | ["Delay in possessi…["Delay in possession", "Non-compliance of agreement"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the shop/office space within the stipulated time and sought delay possession charges.", "respondent_claim": "The respondent claimed that the delay was due to unforeseeable events beyond their control and sought to invoke the force majeure clause.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession till the date of handing over possession.", "in_favor_of_respondent": "no"} | Ramawtar MeenaRamawtar Meena | Ansal Housing Limit…Ansal Housing Limited | Link |
696 of 2021696 of 2021 | HaryanaHaryana | The complainant, Ram Gopal Yadav, filed a complai…The complainant, Ram Gopal Yadav, filed a complaint against Ansal Housing Limited for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession. | ["Violation of sect…["Violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent violated section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016 by not handing over the possession of the flat within the prescribed time period.", "respondent_claim": "The respondent claimed that the complainant was not entitled to the relief sought as the agreement signed between the parties was in 2013, and the RERA Act, 2016 was not applicable at that time.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Ram Gopal YadavRam Gopal Yadav | Ansal Housing Limit…Ansal Housing Limited | Link |
2430 of 20212430 of 2021 | HaryanaHaryana | The complainants, Rajiv Yadav and Kanta Yadav, fi…The complainants, Rajiv Yadav and Kanta Yadav, filed a complaint against Ansal Housing Limited for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay. | ["Non-compliance of…["Non-compliance of possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the flat within the stipulated period and sought interest payment for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and sought to avoid payment of interest.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Kanta YadavKanta Yadav | Ansal Housing Limit…Ansal Housing Limited | Link |
750 of 2021750 of 2021 | HaryanaHaryana | Complainant Sonika Garg filed a complaint against…Complainant Sonika Garg filed a complaint against Ansal Housing Ltd. for delayed possession of a flat. The Haryana Real Estate Regulatory Authority allowed the complaint and directed the respondent to refund the entire amount paid by the complainant. | ["Delayed possessio…["Delayed possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that she had made timely payments towards the allotted unit, but the respondent had delayed the possession of the flat.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including force majeure circumstances and ongoing projects.", "final_verdict": "The Haryana Real Estate Regulatory Authority allowed the complaint and directed the respondent to refund the entire amount paid by the complainant.", "in_favor_of_respondent": "no"} | Sonika GargSonika Garg | Ansal Housing Limit…Ansal Housing Limited | Link |
5230f20215230f2021 | HaryanaHaryana | The complainants sought delay possession charges …The complainants sought delay possession charges from the respondent for not handing over the possession of the apartment within the stipulated period. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over the possession of the apartment within the stipulated period of 36 months from the date of execution of the agreement.", "respondent_claim": "The respondent claimed that the complainants were not in default under any provisions of the agreement and that the possession clause was vague and uncertain.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Anita BishtAnita Bisht | Ansal Housing Limit…Ansal Housing Limited | Link |
2359 of 20212359 of 2021 | HaryanaHaryana | Complainant sought delay interest and possession …Complainant sought delay interest and possession for a flat in Ansal Heights project. Authority directed the respondent to pay interest at 9.30% p.a. for delay in possession. | ["Delay in possessi…["Delay in possession", "Interest for delay"] | {"appellant_claim": "Complainant sought delay int…{"appellant_claim": "Complainant sought delay interest and possession for a flat in Ansal Heights project.", "respondent_claim": "Respondent claimed that the complainant had not approached the Adjudicating Officer with clean hands and had not disclosed true and material facts.", "final_verdict": "Authority directed the respondent to pay interest at 9.30% p.a. for delay in possession.", "in_favor_of_respondent": "no"} | Ms. Urmila RaniMs. Urmila Rani | Ansal Housing Limit…Ansal Housing Limited | Link |
1411 of 20211411 of 2021 | HaryanaHaryana | Complainants sought possession of flat and delay …Complainants sought possession of flat and delay possession charges from respondent. Authority directed respondent to pay interest at prescribed rate for delay in possession. | ["Delay in possessi…["Delay in possession", "Interest for delay"] | {"appellant_claim": "Complainants claimed that re…{"appellant_claim": "Complainants claimed that respondent delayed possession of flat and sought interest and compensation for the delay.", "respondent_claim": "Respondent claimed that complainants were not ready to pay as per schedule and that delay was due to various reasons including force majeure.", "final_verdict": "Authority directed respondent to pay interest at prescribed rate for delay in possession.", "in_favor_of_respondent": "no"} | Pinki GoyalPinki Goyal | Ansal Housing Limit…Ansal Housing Limited | Link |
1258 of 20211258 of 2021 | HaryanaHaryana | The complainant, Binoo Sehgal, filed a complaint …The complainant, Binoo Sehgal, filed a complaint against M/s Ansal Housing Ltd. for not handing over possession of a residential apartment despite payment of full amount. The Haryana Real Estate Regulatory Authority (HARERA) directed the respondent to pay interest at the prescribed rate for every month of delay and refund labour charges unjustifiably levied. | ["Delay in possessi…["Delay in possession", "Labour charges"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the apartment despite payment of full amount and unjustifiably levied labour charges.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen circumstances and the labour charges were levied as per law.", "final_verdict": "The HARERA directed the respondent to pay interest at the prescribed rate for every month of delay and refund labour charges unjustifiably levied.", "in_favor_of_respondent": "no"} | Binoo SehgalBinoo Sehgal | Ansal Housing Limit…Ansal Housing Limited | Link |
1412 of 20211412 of 2021 | HaryanaHaryana | The complainant, Mrs. Pinki Goyal, filed a compla…The complainant, Mrs. Pinki Goyal, filed a complaint against Ansal Housing Limited for delay in handing over possession of a flat. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed handing over possession of the flat beyond the agreed-upon date.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including force majeure.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Mrs. Pinki GoyalMrs. Pinki Goyal | Ansal Housing Limit…Ansal Housing Limited | Link |
4530 of 20214530 of 2021 | HaryanaHaryana | The complainants, Amrit Lal Saxena and Neha Saxen…The complainants, Amrit Lal Saxena and Neha Saxena, filed a complaint against M/s Ansal Housing Ltd. for not handing over possession of a shop in the project 'Ansal Hub' in Sector 83, Gurugram, within the stipulated period of 36 months. | ["Delay in possessi…["Delay in possession", "Non-compliance with agreement"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over possession of the shop within the stipulated period of 36 months and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and sought to justify the delay.", "final_verdict": "The authority held that the respondent was in contravention of section 11(4)(a) of the Act by not handing over possession within the stipulated period and directed the respondent to pay interest at the prescribed rate of 9.50% per annum for every month of delay from 11.09.2016 till the actual handing over of possession.", "in_favor_of_respondent": "no"} | Neha SaxenaNeha Saxena | Ansal Housing Limit…Ansal Housing Limited | Link |
3992 of 20213992 of 2021 | HaryanaHaryana | The complainant, Somesh Aggarwal, filed a complai…The complainant, Somesh Aggarwal, filed a complaint against Ansal Housing Limited for delay in possession of a flat in the Estella project. The Haryana Real Estate Regulatory Authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat by 6 years and 2 months and sought compensation for the same.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including unforeseen circumstances and sought to avoid paying compensation.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Somesh AggarwalSomesh Aggarwal | Ansal Housing Limit…Ansal Housing Limited | Link |
4408 of 20214408 of 2021 | HaryanaHaryana | The complainants, Anil Sachdeva and Rita Sachdeva…The complainants, Anil Sachdeva and Rita Sachdeva, filed a complaint against M/s Ansal Housing Ltd. for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay from the due date of possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over possession of the unit within the stipulated period of 36 months and sought compensation in the form of interest payment.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen circumstances and that they were not liable for the compensation.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Rita SachdevaRita Sachdeva | Ansal Housing Limit…Ansal Housing Limited | Link |
2308 of 20192308 of 2019 | HaryanaHaryana | The complainants, Deepa Hemrajani and Kamal Hemra…The complainants, Deepa Hemrajani and Kamal Hemrajani, filed a complaint against M/s Ansal Housing Ltd. for delayed possession of a commercial unit. The Haryana Real Estate Regulatory Authority found the respondent in contravention of section 11(4)(a) of the Act and directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay. | ["Delayed possessio…["Delayed possession", "Non-compliance of agreement"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to deliver possession of the commercial unit within the stipulated period of 36 months and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances beyond their control, including force majeure events and lack of cooperation from the complainants.", "final_verdict": "The Haryana Real Estate Regulatory Authority found the respondent in contravention of section 11(4)(a) of the Act and directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Kamal HemrajaniKamal Hemrajani | Ansal Housing Limit…Ansal Housing Limited | Link |
4071 of 20214071 of 2021 | HaryanaHaryana | The complainants, Sarabjeet Singh Sethi and Ravne…The complainants, Sarabjeet Singh Sethi and Ravneet Kaur, filed a complaint against M/s Ansal Housing Ltd. for delay in handing over possession of a commercial unit. The Haryana Real Estate Regulatory Authority (HARERA) directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent delayed handing over possession of the commercial unit beyond the stipulated period of 36 months.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and force majeure events.", "final_verdict": "The HARERA directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Ravneet KaurRavneet Kaur | Ansal Housing Limit…Ansal Housing Limited | Link |
4207 of 20214207 of 2021 | HaryanaHaryana | The complainant, K.R. Nair, filed a complaint aga…The complainant, K.R. Nair, filed a complaint against Ansal Housing Limited for delay in possession of a flat in the Estella project. The Haryana Real Estate Regulatory Authority (HRERA) directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat beyond the agreed-upon date and sought compensation for the same.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had taken steps to rectify the situation.", "final_verdict": "The HRERA directed the respondent to pay interest at the prescribed rate for every month of delay from the due date of possession till the actual handing over of possession.", "in_favor_of_respondent": "no"} | K.R. NairK.R. Nair | Ansal Housing Limit…Ansal Housing Limited | Link |
4409 of 20214409 of 2021 | HaryanaHaryana | The complainant, Manoj Gupta, filed a complaint a…The complainant, Manoj Gupta, filed a complaint against M/s Ansal Housing Ltd. for not handing over possession of a shop in their project, 'Ansal Hub', within the stipulated period. The Haryana Real Estate Regulatory Authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the shop within the stipulated period of 36 months and sought compensation in the form of interest payment.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen circumstances and that they were not liable for the compensation.", "final_verdict": "The Haryana Real Estate Regulatory Authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Manoj GuptaManoj Gupta | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/4953/2021CR/4953/2021 | HaryanaHaryana | The complainant, Jagdish Chauhan, filed a complai…The complainant, Jagdish Chauhan, filed a complaint against Ansal Housing Limited for delay in possession of a shop in their project, HUB 83. The authority directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the shop by 5 years and 9 months and sought compensation and interest payment.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including force majeure circumstances.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.50% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Jagdish ChauhanJagdish Chauhan | Ansal Housing Limit…Ansal Housing Limited | Link |
753 of 2021753 of 2021 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest for delay in possession of the flat. The authority directed the promoter to refund the amount with interest at the prescribed rate. | ["Delay in possessi…["Delay in possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the promoter failed to deliver the possession of the flat within the stipulated period and sought refund of the amount paid with interest.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen events and sought to justify the same.", "final_verdict": "The authority directed the promoter to refund the amount paid by the complainant with interest at the prescribed rate.", "in_favor_of_respondent": "no"} | Ashok KumarAshok Kumar | Ansal Housing Limit…Ansal Housing Limited | Link |
4271 of 20214271 of 2021 | HaryanaHaryana | The complainant, Aishwarya Tiwari, filed a compla…The complainant, Aishwarya Tiwari, filed a complaint against Ansal Housing Limited for not handing over the possession of a flat within the stipulated period. The Haryana Real Estate Regulatory Authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over the possession of the flat within the stipulated period of 42 months.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including obtaining necessary approvals and sanctions.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Aishwarya TiwariAishwarya Tiwari | Ansal Housing Limit…Ansal Housing Limited | Link |
3904 of 20213904 of 2021 | HaryanaHaryana | The complainant, Somesh Aggarwal, filed a complai…The complainant, Somesh Aggarwal, filed a complaint against Ansal Housing Limited for delay in possession of a flat in the Estella project. The authority directed the respondent to pay interest at the rate of 9.50% per annum for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat by more than 5 years and 6 months and sought compensation for the same.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including obtaining sanctions and approvals.", "final_verdict": "The authority directed the respondent to pay interest at the rate of 9.50% per annum for every month of delay.", "in_favor_of_respondent": "no"} | Somesh AggarwalSomesh Aggarwal | Ansal Housing Limit…Ansal Housing Limited | Link |
112 of 2021112 of 2021 | HaryanaHaryana | Complainants sought delay possession charges and …Complainants sought delay possession charges and interest on paid amount for every month of delay. Authority directed respondent to pay interest at prescribed rate of 9.50% per annum for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest on delay"] | {"appellant_claim": "Complainants claimed that re…{"appellant_claim": "Complainants claimed that respondent failed to deliver possession within the prescribed time limit and sought delay possession charges and interest on paid amount for every month of delay.", "respondent_claim": "Respondent claimed that the possession was delayed due to various reasons and that the complainants were not entitled to any compensation.", "final_verdict": "Authority directed respondent to pay interest at prescribed rate of 9.50% per annum for every month of delay.", "in_favor_of_respondent": "no"} | Sarita Rani GambhirSarita Rani Gambhir | Ansal Housing Limit…Ansal Housing Limited | Link |
4954 of 20214954 of 2021 | HaryanaHaryana | The complainant sought relief for delayed possess…The complainant sought relief for delayed possession of a commercial unit in the 'Ansal Hub' project. The Haryana Real Estate Regulatory Authority (HARERA) directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delayed possessio…["Delayed possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent had failed to deliver possession of the commercial unit within the stipulated period of 36 months.", "respondent_claim": "The respondent did not file a reply within the stipulated time period, and their defense was struck off.", "final_verdict": "The HARERA directed the respondent to pay interest at the prescribed rate of 9.50% per annum for every month of delay from the due date of possession (11.09.2016) till the actual handing over of possession.", "in_favor_of_respondent": "no"} | Jagdish ChauhanJagdish Chauhan | Ansal Housing Limit…Ansal Housing Limited | Link |
1252 of 20181252 of 2018 | HaryanaHaryana | The complainants sought refund of the amount paid…The complainants sought refund of the amount paid by them along with interest for delay in possession of the shop/office. The authority directed the respondent to refund the amount with interest. | ["Delay in possessi…["Delay in possession", "Refund of amount"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent delayed the possession of the shop/office and sought refund of the amount paid by them along with interest.", "respondent_claim": "The respondent claimed that the delay was due to various reasons including force majeure circumstances and sought to avoid liability.", "final_verdict": "The authority directed the respondent to refund the amount with interest.", "in_favor_of_respondent": "no"} | Raj AroraRaj Arora | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/751/2020CR/751/2020 | HaryanaHaryana | The complainant sought refund of the entire amoun…The complainant sought refund of the entire amount paid with interest and compensation for delay in possession of a commercial shop in the Ansal Hub 83 project. The authority directed the respondent to refund the amount with interest at the rate of 9.80% p.a. | ["Delay in possessi…["Delay in possession", "Refund"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the commercial shop within the stipulated period and sought refund of the entire amount paid with interest and compensation.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had made efforts to complete the project.", "final_verdict": "The authority directed the respondent to refund the amount with interest at the rate of 9.80% p.a.", "in_favor_of_respondent": "no"} | Dax AbrahamDax Abraham | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/2007/2018CR/2007/2018 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest and compensation for not handing over possession of the flat within the stipulated period. The authority directed the respondent to refund the amount with interest at the rate of 9.80% p.a. | ["Refund of amount"…["Refund of amount", "Interest", "Compensation"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to hand over possession of the flat within the stipulated period and sought refund of the amount paid with interest and compensation.", "respondent_claim": "The respondent claimed that the delay in handing over possession was due to unforeseen circumstances and sought to avoid refunding the amount.", "final_verdict": "The authority directed the respondent to refund the amount with interest at the rate of 9.80% p.a.", "in_favor_of_respondent": "no"} | Sangeeta JainSangeeta Jain | Ansal Housing Limit…Ansal Housing Limited | Link |
5951 of 20195951 of 2019 | HaryanaHaryana | The complainants sought refund of the amount paid…The complainants sought refund of the amount paid with interest for delay in possession of the flat. The authority directed the respondent to refund the amount with interest at the prescribed rate. | ["Delay in possessi…["Delay in possession", "Refund of amount"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to deliver possession of the flat within the stipulated time and sought refund of the amount paid with interest.", "respondent_claim": "The respondent claimed that the delay in possession was due to unforeseen circumstances and that the complainants were not entitled to refund.", "final_verdict": "The authority directed the respondent to refund the amount paid by the complainants with interest at the prescribed rate.", "in_favor_of_respondent": "no"} | Susan DaxSusan Dax | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/816/2020CR/816/2020 | HaryanaHaryana | The complainant sought refund of the entire amoun…The complainant sought refund of the entire amount paid with interest for delay in possession of a flat by the respondent. The authority directed the respondent to refund the amount with interest at the rate of 10% p.a. | ["Delay in possessi…["Delay in possession", "Refund with interest"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the flat within the agreed-upon time frame and sought refund of the entire amount paid with interest.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they were not liable for the same.", "final_verdict": "The authority directed the respondent to refund the amount with interest at the rate of 10% p.a.", "in_favor_of_respondent": "no"} | Vinay NagrathVinay Nagrath | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/762/2021/5770/20…CR/762/2021/5770/2019 | HaryanaHaryana | The complainant, Kewal Krishan Chopra Sudershan, …The complainant, Kewal Krishan Chopra Sudershan, withdrew the complaint against Ansal Housing Limited after an amicable settlement. A settlement deed dated 01.11.2022 was signed by both parties. | ["Real Estate Dispu…["Real Estate Dispute"] | {"appellant_claim": "Not provided", "respondent_c…{"appellant_claim": "Not provided", "respondent_claim": "Not provided", "final_verdict": "The matter stands disposed off due to an amicable settlement between the parties.", "in_favor_of_respondent": "no"} | Kewal Krishan Chopr…Kewal Krishan Chopra Sudershan | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/174/2020CR/174/2020 | HaryanaHaryana | The complainant sought refund of the entire amoun…The complainant sought refund of the entire amount paid with interest and compensation due to delay in possession of the flat. The authority directed the respondent to refund the amount with interest at the rate of 10.35% p.a. | ["Delay in possessi…["Delay in possession", "Refund"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat and sought refund of the entire amount paid with interest and compensation.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant was not entitled to refund.", "final_verdict": "The authority directed the respondent to refund the amount with interest at the rate of 10.35% p.a.", "in_favor_of_respondent": "no"} | Chavi SuriChavi Suri | Ansal Housing Limit…Ansal Housing Limited | Link |
1862 of 20211862 of 2021 | HaryanaHaryana | Complainant sought refund for delayed possession …Complainant sought refund for delayed possession of flat. Authority directed refund with interest. | ["Refund for delaye…["Refund for delayed possession"] | {"appellant_claim": "Complainant sought refund fo…{"appellant_claim": "Complainant sought refund for delayed possession of flat.", "respondent_claim": "Respondent claimed delay due to various reasons, including court orders and demonetization.", "final_verdict": "Authority directed refund with interest.", "in_favor_of_respondent": "no"} | Sunita MalhotraSunita Malhotra | Ansal Housing Limit…Ansal Housing Limited | Link |
1493 of 20211493 of 2021 | HaryanaHaryana | Complainants sought refund for delayed possession…Complainants sought refund for delayed possession of a flat. HARERA directed the promoter to refund the amount with interest. | ["Delayed possessio…["Delayed possession", "Refund"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to deliver possession of the flat within the agreed-upon time frame and sought refund of the amount paid.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had taken steps to complete the project.", "final_verdict": "HARERA directed the respondent to refund the amount paid by the complainants with interest at the rate of 10.70% per annum.", "in_favor_of_respondent": "no"} | Babita GoelBabita Goel | Ansal Housing Limit…Ansal Housing Limited | Link |
5390 of 20225390 of 2022 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest for delay in possession of the unit. The authority directed the respondent to refund the amount with prescribed rate of interest. | ["Delay in possessi…["Delay in possession", "Refund with interest"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the unit within the agreed-upon time frame and sought refund of the amount paid with interest.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant was not entitled to refund.", "final_verdict": "The authority directed the respondent to refund the amount paid by the complainant with prescribed rate of interest.", "in_favor_of_respondent": "no"} | Sima OjhaSima Ojha | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/1804/2021CR/1804/2021 | HaryanaHaryana | The complainant, Neepa Vashisht, filed a complain…The complainant, Neepa Vashisht, filed a complaint against Ansal Housing Ltd. for not handing over possession of a shop in the ANSAL HUB 83 project despite paying the full amount. The HARERA found that the respondent was liable to refund the amount with interest. | ["Non-handover of p…["Non-handover of possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that she paid the full amount for a shop in the ANSAL HUB 83 project but the respondent did not hand over possession despite several requests.", "respondent_claim": "The respondent claimed that the complainant was not entitled to refund as she had not completed the payment schedule.", "final_verdict": "The HARERA found that the respondent was liable to refund the amount with interest.", "in_favor_of_respondent": "no"} | Neepa VashishtNeepa Vashisht | Ansal Housing Limit…Ansal Housing Limited | Link |
2143 of 20222143 of 2022 | HaryanaHaryana | The complainants, Parag Kashyap and Sunita Kashya…The complainants, Parag Kashyap and Sunita Kashyap, filed a complaint against M/s Ansal Housing Ltd. for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to handover the physical possession of the unit along with interest at the prescribed rate of 10.70% p.a. for every month of delay. | ["Non-compliance of…["Non-compliance of possession date", "Delay in handover of possession"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to handover the possession of the unit within the stipulated period of 36 months from the date of execution of the agreement.", "respondent_claim": "The respondent claimed that the delay in handover of possession was due to various reasons including force majeure circumstances.", "final_verdict": "The authority directed the respondent to handover the physical possession of the unit along with interest at the prescribed rate of 10.70% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Sunita KashyapSunita Kashyap | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/11/2022CR/11/2022 | HaryanaHaryana | The complainant, Vinita Yadav, filed a complaint …The complainant, Vinita Yadav, filed a complaint against Ansal Housing Ltd. for not handing over possession of her shop within the stipulated period. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | Delay in possession…Delay in possession of shop | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of her shop within the stipulated period and sought delay possession charges at the prescribed rate of interest.", "respondent_claim": "The respondent claimed that the delay was due to force majeure circumstances beyond their control.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Vinita YadavVinita Yadav | Ansal Housing Limit…Ansal Housing Limited | Link |
48534853 | HaryanaHaryana | The complainant sought relief for delayed possess…The complainant sought relief for delayed possession of a commercial unit in the 'Ansal Hub 83 Boulevard' project. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delayed possessio…["Delayed possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent had failed to deliver possession of the commercial unit within the agreed-upon timeframe and sought relief for the delay.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances beyond their control, including court orders and COVID-19-related issues.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay from the due date of possession until the expiry of 2 months from the date of issuance of occupation certificate or actual handing over of possession.", "in_favor_of_respondent": "no"} | Ankush GuptaAnkush Gupta | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/4680/2022CR/4680/2022 | HaryanaHaryana | The complainants, Uma Vijay and Tanuj Vijay, file…The complainants, Uma Vijay and Tanuj Vijay, filed a complaint against Ansal Housing Ltd. for not handing over the possession of their flat within the stipulated period and for not paying delay possession charges. | ["Delay in possessi…["Delay in possession", "Non-payment of delay possession charges"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over the possession of their flat within the stipulated period of 42 months and did not pay delay possession charges.", "respondent_claim": "The respondent claimed that the delay in possession was due to various reasons, including force majeure circumstances, and that they had paid delay possession charges at the rate of Rs. 5/- per sq. ft. per month.", "final_verdict": "The authority directed the respondent to hand over the physical possession of the unit to the complainants within 2 months from the date of the order and pay interest at the prescribed rate of 10.70% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Tanuj VijayTanuj Vijay | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/6038/2022CR/6038/2022 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest for not receiving possession of the shop by the due date. The authority directed the respondent to refund the amount with interest. | ["Refund for delaye…["Refund for delayed possession"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the shop by the due date and sought refund of the amount paid with interest.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant was not entitled to refund.", "final_verdict": "The authority directed the respondent to refund the amount paid by the complainant with interest at the rate of 10.75% per annum.", "in_favor_of_respondent": "no"} | Ankur JainAnkur Jain | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/6035/2022CR/6035/2022 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest and compensation for delayed possession of a flat in the 'Ansal Highland Park' project. The authority directed the respondent to refund the amount with interest at the rate of 10.75% per annum. | ["Delayed possessio…["Delayed possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the flat within the stipulated time and sought refund of the amount paid with interest and compensation.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant was not entitled to refund.", "final_verdict": "The authority directed the respondent to refund the amount paid by the complainant with interest at the rate of 10.75% per annum.", "in_favor_of_respondent": "no"} | Ankur JainAnkur Jain | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/962/2022CR/962/2022 | HaryanaHaryana | The complainants sought delay possession charges …The complainants sought delay possession charges and handover of physical possession of the unit. The authority directed the respondent to pay interest at the rate of 10.75% p.a. and hand over the physical possession of the unit within 2 months. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent failed to hand over the physical possession of the unit within the stipulated period and sought delay possession charges.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen events and sought to avoid payment of delay possession charges.", "final_verdict": "The authority directed the respondent to pay interest at the rate of 10.75% p.a. and hand over the physical possession of the unit within 2 months.", "in_favor_of_respondent": "no"} | Dinesh KumarDinesh Kumar | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/2904/2022CR/2904/2022 | HaryanaHaryana | The complainant sought delay possession charges a…The complainant sought delay possession charges at prescribed rate of interest. The authority directed the respondent to pay interest at the prescribed rate for every month of delay on the amount paid by the complainant. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession by the due date and sought delay possession charges at prescribed rate of interest.", "respondent_claim": "The respondent claimed that the delay in possession was due to force majeure circumstances and that the complainant was not entitled to compensation.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay on the amount paid by the complainant.", "in_favor_of_respondent": "no"} | Anil Mohan ChughAnil Mohan Chugh | Ansal Housing Limit…Ansal Housing Limited | Link |
2234 of 20222234 of 2022 | HaryanaHaryana | The complainant sought relief for delay in posses…The complainant sought relief for delay in possession of a flat in the Ansal Heights project. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed possession of the flat and sought relief for the same.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant had not paid the full amount due.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Kuldeep GrewalKuldeep Grewal | Ansal Housing Limit…Ansal Housing Limited | Link |
6843 of 20226843 of 2022 | HaryanaHaryana | The complainant sought delay possession charges a…The complainant sought delay possession charges and refund of arbitrary charges. The authority directed the respondent to pay interest at the prescribed rate for every month of delay and refund the arbitrary charges. | ["Delay possession …["Delay possession charges", "Arbitrary charges"] | {"appellant_claim": "The complainant sought delay…{"appellant_claim": "The complainant sought delay possession charges and refund of arbitrary charges.", "respondent_claim": "The respondent claimed that the complainant was not entitled to delay possession charges and that the arbitrary charges were legitimate.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay and refund the arbitrary charges.", "in_favor_of_respondent": "no"} | Abha YadavAbha Yadav | Ansal Housing Limit…Ansal Housing Limited | Link |
580 of 2022580 of 2022 | HaryanaHaryana | The complainant filed a complaint against the res…The complainant filed a complaint against the respondent for delay in possession of a commercial unit/shop. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed the possession of the commercial unit/shop and sought relief for the same.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including force majeure, demonetization, and orders of the Hon'ble NGT prohibiting construction in and around Delhi.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | GautamGautam | Ansal Housing Limit…Ansal Housing Limited | Link |
1622 of 20221622 of 2022 | HaryanaHaryana | The complainants, Ajay Chawla and Neetu Ghulani, …The complainants, Ajay Chawla and Neetu Ghulani, filed a complaint against Ansal Housing Limited for not handing over possession of their flat within the stipulated period. The authority directed the respondent to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over possession of their flat within the stipulated period of 36 months from the date of agreement.", "respondent_claim": "The respondent claimed that the delay was due to various reasons, including force majeure circumstances and orders passed by the Hon'ble High Court and National Green Tribunal.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for every month of delay from the due date of possession till the expiry of 2 months from the date of offer of possession after issuance of occupation certificate.", "in_favor_of_respondent": "no"} | Neetu GhulaniNeetu Ghulani | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/5441/2022 and CR…CR/5441/2022 and CR/6087/2022 | HaryanaHaryana | The complainants, Col. Sanjeev Kumar and Nita, an…The complainants, Col. Sanjeev Kumar and Nita, and Devender Kaur and Vijender Singh, filed complaints against Ansal Housing Limited for not handing over possession of their flats within the agreed-upon time frame. The Haryana Real Estate Regulatory Authority (HARERA) directed Ansal Housing Limited to pay interest to the complainants at the prescribed rate of 10.75% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that Ansal Housing Limited failed to hand over possession of their flats within the agreed-upon time frame of 42 months from the date of execution of the agreement.", "respondent_claim": "Ansal Housing Limited claimed that the delay was due to various reasons, including force majeure, demonetization, and orders from the National Green Tribunal prohibiting construction in and around Delhi.", "final_verdict": "The HARERA directed Ansal Housing Limited to pay interest to the complainants at the prescribed rate of 10.75% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Vijender SinghVijender Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
7360 of 20227360 of 2022 | HaryanaHaryana | Complainants sought delay possession charges, phy…Complainants sought delay possession charges, physical and legal possession of apartment, and conveyance deed. Authority directed payment of interest at 10.75% per annum for delay and handover of possession. | ["Delay in possessi…["Delay in possession", "Non-compliance with agreement"] | {"appellant_claim": "Complainants claimed delay i…{"appellant_claim": "Complainants claimed delay in possession of apartment, non-handover of physical and legal possession, and non-execution of conveyance deed.", "respondent_claim": "Respondent claimed that delay was due to force majeure circumstances, and that complainants had not paid full dues.", "final_verdict": "Authority directed payment of interest at 10.75% per annum for delay and handover of possession within 30 days.", "in_favor_of_respondent": "no"} | Harpreet KaurHarpreet Kaur | Ansal Housing Limit…Ansal Housing Limited | Link |
5504 of 20225504 of 2022 | HaryanaHaryana | The complainants sought refund of the amount paid…The complainants sought refund of the amount paid by them along with interest prescribed rate of interest. The authority is satisfied that the respondent is in contravention of the section 11(4)(a) of the Act by not handing over possession by the due date as per the agreement. | ["Non-handover of p…["Non-handover of possession", "Refund of amount"] | {"appellant_claim": "The complainants sought refu…{"appellant_claim": "The complainants sought refund of the amount paid by them along with interest prescribed rate of interest.", "respondent_claim": "The respondent claimed that the complainants were not in default under any provisions of the agreement.", "final_verdict": "The authority is satisfied that the respondent is in contravention of the section 11(4)(a) of the Act by not handing over possession by the due date as per the agreement. The respondents/promoters are directed to refund the amount i.e, Rs.14,62,511/- received by it from the complainants along with interest at the rate of 10.75% p.a.", "in_favor_of_respondent": "no"} | Mr. Suresh BhattMr. Suresh Bhatt | Ansal Housing Limit…Ansal Housing Limited | Link |
1767 of 20221767 of 2022 | HaryanaHaryana | The complainants, Mr. Alex Kurian, Mr. Salcy, Mr.…The complainants, Mr. Alex Kurian, Mr. Salcy, Mr. Jubin Kurian, and Mr. Ravinder Pal Singh, filed a complaint against Ansal Housing Limited and Samyak Projects Private Limited for violation of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondents to refund the amount paid by the complainants with interest. | ["Non-delivery of p…["Non-delivery of possession", "Refund of amount"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondents failed to deliver possession of the unit and sought refund of the amount paid.", "respondent_claim": "The respondents claimed that the delay was due to force majeure conditions and sought to avoid refund.", "final_verdict": "The authority directed the respondents to refund the amount paid by the complainants with interest.", "in_favor_of_respondent": "no"} | Mr. Ravinder Pal Si…Mr. Ravinder Pal Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/6173/2022CR/6173/2022 | HaryanaHaryana | The complainants, Mr. Rajesh Babbar and Mrs. Bhaw…The complainants, Mr. Rajesh Babbar and Mrs. Bhawana Babbar, filed a complaint against Ansal Housing Limited for not handing over the possession of their apartment and seeking delay possession charges. | ["Delayed Possessio…["Delayed Possession", "Possession Charges"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondent did not hand over the possession of their apartment within the stipulated period and sought delay possession charges.", "respondent_claim": "The respondent claimed that the complainants did not pay the amount in time and therefore, the delay in possession.", "final_verdict": "The authority directed the respondent to pay the interest at the prescribed rate of 10.75% per annum for every month of delay on the amount paid by the complainants.", "in_favor_of_respondent": "no"} | Mrs. Bhawana BabbarMrs. Bhawana Babbar | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/7374/2022CR/7374/2022 | HaryanaHaryana | The complainant sought delay possession charges a…The complainant sought delay possession charges and interest for not handing over possession of the apartment by the due date. The authority directed the respondent to pay interest at the prescribed rate of 10.75% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest rates"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the apartment by the due date and sought delay possession charges and interest.", "respondent_claim": "The respondent claimed that the delay was due to various reasons including force majeure conditions and sought to avoid liability.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 10.75% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Rattan Singh SainiRattan Singh Saini | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/585/2023CR/585/2023 | HaryanaHaryana | The complainant, Rajesh Vashista, filed a complai…The complainant, Rajesh Vashista, filed a complaint against Ansal Housing Ltd. and Samyak Projects Pvt. Ltd. for not handing over possession of a flat in the Ansal Heights 86 project within the stipulated period. | ["Delay in possessi…["Delay in possession", "Non-compliance with agreement"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the flat within the stipulated period of 42 months and sought delay possession charges along with interest.", "respondent_claim": "The respondent claimed that the delay in possession was due to various circumstances beyond their control, including orders from the High Court and the National Green Tribunal.", "final_verdict": "The authority held that the respondent was in contravention of section 11(4)(a) of the Act by not handing over possession by the due date as per the agreement. The authority directed the respondent to hand over the actual physical possession of the unit to the complainant within 2 months after obtaining occupation certificate and to pay interest at the prescribed rate of 10.85% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Rajesh VashistaRajesh Vashista | Ansal Housing Limit…Ansal Housing Limited | Link |
5587 of 20225587 of 2022 | HaryanaHaryana | Complainant sought possession of flat and delay p…Complainant sought possession of flat and delay possession charges from respondent. Authority directed respondent to pay interest at prescribed rate for delay in possession. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "Complainant sought possessio…{"appellant_claim": "Complainant sought possession of flat and delay possession charges from respondent.", "respondent_claim": "Respondent claimed that delay in possession was due to various reasons including force majeure circumstances.", "final_verdict": "Authority directed respondent to pay interest at prescribed rate for delay in possession.", "in_favor_of_respondent": "no"} | Mrs Rashmi SalujaMrs Rashmi Saluja | Ansal Housing Limit…Ansal Housing Limited | Link |
182 of 2023182 of 2023 | HaryanaHaryana | The complainant, Mrs. Sunita Godara and Mr. Pawan…The complainant, Mrs. Sunita Godara and Mr. Pawan Veer, filed a complaint against Ansal Housing Ltd. and Samyak Projects Private Limited for not handing over possession of their flat despite paying the full amount. The Haryana Real Estate Regulatory Authority (HARERA) directed the respondents to refund the amount with interest. | ["Non-handover of p…["Non-handover of possession", "Refund with interest"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that they had paid the full amount for their flat, but the respondents had not handed over possession despite several requests.", "respondent_claim": "The respondents claimed that the delay was due to various reasons, including force majeure conditions.", "final_verdict": "The HARERA directed the respondents to refund the amount with interest at the rate of 10.85% per annum.", "in_favor_of_respondent": "no"} | Mr. Pawan VeerMr. Pawan Veer | Ansal Housing Limit…Ansal Housing Limited | Link |
1799 of 20231799 of 2023 | HaryanaHaryana | The complainant, Mr. Sharad Kumar Agrawal, filed …The complainant, Mr. Sharad Kumar Agrawal, filed a complaint against Ansal Housing Ltd. for not handing over possession of a flat in the Ansal Heights project despite payment of the full amount. The Haryana Real Estate Regulatory Authority (HRERA) directed the respondent to refund the amount with interest. | ["Delay in possessi…["Delay in possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that he had paid the full amount for the flat but the respondent had not handed over possession despite the due date having expired.", "respondent_claim": "The respondent claimed that the delay was due to various reasons including force majeure conditions.", "final_verdict": "The HRERA directed the respondent to refund the amount with interest.", "in_favor_of_respondent": "no"} | Mr. Sharad Kumar Ag…Mr. Sharad Kumar Agrawal | Ansal Housing Limit…Ansal Housing Limited | Link |
3026 of 20233026 of 2023 | HaryanaHaryana | The complainant filed a complaint against the res…The complainant filed a complaint against the respondent for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to handover possession of the unit and pay interest at the prescribed rate. | ["Delay in possessi…["Delay in possession", "Non-compliance of agreement"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not handover possession of the unit on time and did not comply with the agreement.", "respondent_claim": "The respondent claimed that the delay was due to force majeure circumstances and that they had complied with the agreement.", "final_verdict": "The authority directed the respondent to handover possession of the unit and pay interest at the prescribed rate.", "in_favor_of_respondent": "no"} | Jaspreet SinghJaspreet Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
3197 of 20233197 of 2023 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid for a villa in the Ansal Heights project due to non-completion of the project and non-handover of possession. The authority directed the respondent to refund the amount with interest. | ["Non-completion of…["Non-completion of project", "Non-handover of possession"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to complete the project and handover possession of the villa despite receiving the full payment.", "respondent_claim": "The respondent claimed that the delay was due to various reasons including force majeure circumstances such as orders passed by the National Green Tribunal and demonetization.", "final_verdict": "The authority directed the respondent to refund the amount paid by the complainant with interest.", "in_favor_of_respondent": "no"} | Kulwant SinghKulwant Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
3396 of 20233396 of 2023 | HaryanaHaryana | Complainant sought possession of flat and compens…Complainant sought possession of flat and compensation for delay. Authority directed respondent to pay interest for delay and hand over possession upon obtaining occupation certificate. | ["Delay in possessi…["Delay in possession", "Unjustified charges"] | {"appellant_claim": "Complainant sought possessio…{"appellant_claim": "Complainant sought possession of flat and compensation for delay.", "respondent_claim": "Respondent claimed that complainant had not paid outstanding amounts.", "final_verdict": "Authority directed respondent to pay interest for delay and hand over possession upon obtaining occupation certificate.", "in_favor_of_respondent": "no"} | Mr. Ashok BaliMr. Ashok Bali | Ansal Housing Limit…Ansal Housing Limited | Link |
3027 of 20233027 of 2023 | HaryanaHaryana | The complainant filed a complaint against the res…The complainant filed a complaint against the respondent for not handing over possession of the flat within the stipulated period. The authority directed the respondent to hand over possession and pay interest at the rate of 10.85% per annum. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent did not hand over possession of the flat within the stipulated period of 42 months.", "respondent_claim": "The respondent claimed that the delay was due to various reasons including force majeure circumstances.", "final_verdict": "The authority directed the respondent to hand over possession of the flat and pay interest at the rate of 10.85% per annum.", "in_favor_of_respondent": "no"} | Mr. Alok UpadhyayMr. Alok Upadhyay | Ansal Housing Limit…Ansal Housing Limited | Link |
Appeal No.310/2019Appeal No.310/2019 | HaryanaHaryana | The appellant sought refund of amount deposited b…The appellant sought refund of amount deposited by him along with interest including damages. The appeal was allowed, and the impugned order dated 13.11.2018 was set-aside. The complaint filed by the appellant/allottee stands transferred to the adjudicating officer, Gurugram, for adjudication in accordance with law. | ["Refund of amount …["Refund of amount deposited", "Interest including damages"] | {"appellant_claim(in detail)": "The appellant sou…{"appellant_claim(in detail)": "The appellant sought refund of amount deposited by him along with interest including damages.", "respondent_claim(in detail)": "The respondent claimed that the appellant was not entitled to refund of amount deposited by him along with interest including damages.", "final_verdict(in detail)": "The appeal was allowed, and the impugned order dated 13.11.2018 was set-aside. The complaint filed by the appellant/allottee stands transferred to the adjudicating officer, Gurugram, for adjudication in accordance with law.", "in_favor_of_respondent": "no"} | Sanjay KhannaSanjay Khanna | Ansal Housing Limit…Ansal Housing Limited | Link |
3897 of 20203897 of 2020 | HaryanaHaryana | The complainants, Ankit Rana and Anita Rana, file…The complainants, Ankit Rana and Anita Rana, filed a complaint against Ansal Housing Limited and Ish Kripa Properties Private Limited for delay in handing over possession of a flat in the Estella project. The authority directed the respondents to pay interest at the prescribed rate for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondents delayed handing over possession of the flat beyond the stipulated period and sought payment of interest for the delay.", "respondent_claim": "The respondents claimed that the delay was due to unforeseen circumstances and that they had not failed to fulfill their obligations.", "final_verdict": "The authority directed the respondents to pay interest at the prescribed rate for every month of delay.", "in_favor_of_respondent": "no"} | Anita RanaAnita Rana | Ansal Housing Limit…Ansal Housing Limited | Link |
441 of 2021441 of 2021 | HaryanaHaryana | The complainant, Bal Kishan Jain, filed a complai…The complainant, Bal Kishan Jain, filed a complaint against Ansal Housing Limited for violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016. The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession. | ["Violation of sect…["Violation of section 11(4)(a) of the Real Estate (Regulation and Development) Act, 2016"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to hand over possession of the apartment within the stipulated period and sought interest for the delayed period.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and sought to invoke the force majeure clause.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession.", "in_favor_of_respondent": "no"} | Bal Kishan JainBal Kishan Jain | Ansal Housing Limit…Ansal Housing Limited | Link |
651 of 2020651 of 2020 | HaryanaHaryana | Complainant sought refund for flat not completed …Complainant sought refund for flat not completed by developer. Developer ordered to refund with interest. | ["Refund for undeli…["Refund for undelivered flat"] | {"appellant_claim(in detail)": "The complainant b…{"appellant_claim(in detail)": "The complainant booked a flat in the respondent's project Ansal Highland Park in 2012 and paid Rs 6,00,000 as booking amount. The respondent allotted a unit, bearing unit No. STRLG - 1303, admeasuring 1762 sq. ft. for a total consideration of Rs 93,71,121/- including BSP, PLC, EDC etc. An apartment buyer\u2019s agreement (ABA) was executed on 21.03.2013 between parties. The complainant made timely payment of Rs 50,02,774/- i.e. 50 % of entire agreed consideration along with miscellaneous and additional charges etc, but to her utter dismay, respondents have not given any information regarding completion of construction work. Possession of the unit has not been offered till date.", "respondent_claim(in detail)": "The respondent contested the complaint by filing a written reply. It is averred that complainant has no locus standi and cause: of action to file the complaint. The complaint has been filed on an erroneous interpretation of the provisions of Act of 2016 as well as terms and conditions of ABA. Respondent no. 1 claimed that despite there being defaulters in the project, it (respondent no. 1) infused funds into project and developed the same.", "final_verdict(in detail)": "The complaint in hands is, thus, allowed. ABA is shown to have been executed between complainant and respondent no. 1 only. It is told that the latter has received payments from the complainant. Same (respondent no. 1) is liable to refund the amount. Respondent no. 1 is directed to refund amounts received from complainant till now i.e. Rs 50,02,774/-within 90 days from today, along with interest @ 9.3% p.a. from the date of each receipts, till realization of amount. The respondent no. 1 is also burdened with litigation cost of Rs.1,00,000/- to be paid to the complainant.", "in_favor_of_respondent": "no"} | Kamlesh NarangKamlesh Narang | Ansal Housing Limit…Ansal Housing Limited | Link |
752 of 2021752 of 2021 | HaryanaHaryana | The complainant sought refund of the amount paid …The complainant sought refund of the amount paid with interest for delay in possession of the flat. The authority directed the promoter to return the amount with interest at the rate of 9.50%. | ["Delay in possessi…["Delay in possession", "Refund of amount"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the promoter failed to deliver possession of the flat within the stipulated period and sought refund of the amount paid with interest.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that the complainant was not entitled to refund.", "final_verdict": "The authority directed the promoter to return the amount paid by the complainant with interest at the rate of 9.50%.", "in_favor_of_respondent": "no"} | Ashok KumarAshok Kumar | Ansal Housing Limit…Ansal Housing Limited | Link |
4738 of 20214738 of 2021 | HaryanaHaryana | The complainant booked a residential unit in the …The complainant booked a residential unit in the 'Ansal Highland Park' project, developed by Ansal Housing Limited and Identity Buildtech Private Limited. The complainant alleged that the respondents failed to hand over possession of the unit within the stipulated period and sought delay possession charges. | ["Delay in possessi…["Delay in possession", "Interest on delayed possession"] | {"appellant_claim": "The complainant alleged that…{"appellant_claim": "The complainant alleged that the respondents failed to hand over possession of the unit within the stipulated period and sought delay possession charges.", "respondent_claim": "The respondents claimed that the delay in possession was due to various reasons, including force majeure circumstances.", "final_verdict": "The authority directed the respondents to pay interest to the complainants against the paid-up amount at the prescribed rate of 10.75% p.a. for every month of delay from the due date of possession till actual handing over of possession or offer of possession plus two months.", "in_favor_of_respondent": "no"} | Mrs. Usha AgarwalMrs. Usha Agarwal | Ansal Housing Limit…Ansal Housing Limited | Link |
341 of 2021341 of 2021 | HaryanaHaryana | The complainant, Pankaj Dhawan, filed a complaint…The complainant, Pankaj Dhawan, filed a complaint against Ansal Housing Limited for delay in handing over possession of a flat in the Estella project. The Haryana Real Estate Regulatory Authority (HARERA) directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest payment"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent delayed handing over possession of the flat beyond the stipulated period of 36 months.", "respondent_claim": "The respondent claimed that the delay was due to various circumstances beyond their control, including financial crunch, orders from the Hon'ble Punjab & Haryana High Court, and restrictions on water extraction.", "final_verdict": "The HARERA directed the respondent to pay interest at the prescribed rate of 9.30% p.a. for every month of delay from the due date of possession ie., 08.05.2015 till the date of handing over possession.", "in_favor_of_respondent": "no"} | Pankaj DhawanPankaj Dhawan | Ansal Housing Limit…Ansal Housing Limited | Link |
997 of 2021997 of 2021 | HaryanaHaryana | The complainant sought possession of a flat and c…The complainant sought possession of a flat and compensation for delay. The authority directed the respondent to pay interest at the prescribed rate for the delay. | ["Delay in possessi…["Delay in possession", "Interest for delay"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondent failed to deliver possession of the flat within the agreed-upon time and sought compensation for the delay.", "respondent_claim": "The respondent claimed that the delay was due to unforeseen circumstances and that they had taken steps to complete the project as soon as possible.", "final_verdict": "The authority directed the respondent to pay interest at the prescribed rate for the delay.", "in_favor_of_respondent": "no"} | Ranvir Singh GargRanvir Singh Garg | Ansal Housing Limit…Ansal Housing Limited | Link |
270 of 2022270 of 2022 | HaryanaHaryana | The complainant, Rahul Rekhi, filed a complaint a…The complainant, Rahul Rekhi, filed a complaint against M/s Ansal Housing Ltd. and M/s Samyak Projects Pvt. Ltd. for delay in possession of a flat in the project 'Ansal Heights, Sector 92, Gurugram'. The authority directed the respondents to hand over the possession of the flat along with interest at the prescribed rate of 10.75% p.a. for every month of delay. | ["Delay in possessi…["Delay in possession", "Interest at prescribed rate"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents delayed the possession of the flat beyond the agreed-upon date and sought compensation for the same.", "respondent_claim": "The respondents claimed that the delay was due to unforeseen circumstances and that they were not liable for the same.", "final_verdict": "The authority directed the respondents to hand over the possession of the flat along with interest at the prescribed rate of 10.75% p.a. for every month of delay.", "in_favor_of_respondent": "no"} | Rahul RekhiRahul Rekhi | Ansal Housing Limit…Ansal Housing Limited | Link |
Yearly Trend for these Cases
The analysis of the cases filed by the builder Ansal Housing, which it lost, reveals a pattern of recurring themes that center primarily around regulatory compliance, financial commitments, and procedural observances.
In terms of non-compliance with regulatory provisions, it is evident that many cases stemmed from the builder's failure to adhere to the mandatory provisions of pre-deposit outlined in the Real Estate (Regulation and Development) Act, 2016. The builder often claimed that they had complied with the Act, yet the respondents consistently asserted otherwise, leading to dismissals based on the lack of necessary financial securities. This theme highlights a critical area where the builder's assertions did not align with legal expectations, resulting in unfavorable outcomes.
Another theme revolves around disputes over pre-deposit requirements, with case after case demonstrating the importance of this provision in the appeal process. The consistent dismissal of appeals on these grounds indicates a systematic issue in how the builder managed its financial obligations related to litigation.
Additionally, a notable number of cases demonstrated issues related to failure to follow court orders. For instance, appeals were dismissed when the builder did not comply with previous orders or when deadlines set by the court were not adhered to. This pattern of procedural non-compliance showcases a troubling trend where the builder may have underestimated the importance of timely and thorough responses in legal proceedings.
The withdrawal of appeals signifies instances where the builder may have recognized the futility of their claims or the solid stance of the respondents. It reflects a strategic decision but highlights the underlying issues that necessitated such withdrawals.
Lastly, the presence of pending cases and compliance issues illustrates a broad struggle the builder faces with stringent regulatory frameworks. In several instances, complaints were dismissed due to the builder's failure to deposit amounts deemed necessary by authorities, pointing to systematic deficiencies in management and adherence to legal protocols.
Overall, the cases reflect a deeper operational challenge within Ansal Housing, focusing particularly on the realms of financial compliance, regulatory adherence, and judicial processes. The common triggers leading to litigation appear to stem from disputes over compliance with financial obligations, which often overlapped with a general failure to understand or manage the expectations set forth by regulatory bodies and court systems. The builder's repeated non-compliance with these provisions has not only led to legal defeats but also raises significant concerns for potential buyers regarding trustworthiness and reliability in future dealings.
This table provides details of individual cases contributing to the summary above. Click rows to expand content. Use "Show More/Less" buttons below.
Case No. | State | Summary | Topic | Detailed Summary | Appellant | Respondent | Source |
---|---|---|---|---|---|---|---|
59/202359/2023 | RajasthanRajasthan | Ansal Housing's appeal was dismissed for not comp…Ansal Housing's appeal was dismissed for not complying with a previous order to cure defects within the granted time. | ["Non-compliance wi…["Non-compliance with previous order"] | {"appellant_claim": "Not provided", "respondent_c…{"appellant_claim": "Not provided", "respondent_claim": "Not provided", "final_verdict": "The appeal was dismissed for not complying with the previous order to cure defects within the granted time.", "in_favor_of_respondent": "yes"} | Ansal HousingAnsal Housing | RERARERA | Link |
Appeal No.288 of 20…Appeal No.288 of 2019 | HaryanaHaryana | The appellant, M/s Ansal Housing Limited, failed …The appellant, M/s Ansal Housing Limited, failed to comply with the provisions of proviso to section 43(5) of the Real Estate (Regulation and Development) Act, 2016, and therefore, the appeal was dismissed. | ["Non-compliance of…["Non-compliance of provisions"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that they had preferred a civil writ petition against the order dated 25.09.2019 passed by this Tribunal.", "respondent_claim": "None", "final_verdict": "The appeal was dismissed due to non-compliance of the mandatory provisions of proviso to section 43(5) of the Act.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Link | |
Appeal No. 205 of 2…Appeal No. 205 of 2021 | HaryanaHaryana | The appeal was rendered infructuous as the compla…The appeal was rendered infructuous as the complaint filed by the respondent had already been disposed by the authority. The appeal was dismissed as withdrawn. | ["Infructuous appea…["Infructuous appeal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the appeal was not infructuous.", "respondent_claim": "The respondent claimed that the complaint filed by them had already been disposed by the authority.", "final_verdict": "The appeal was dismissed as withdrawn.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Aditya TripathiAditya Tripathi | Link |
Appeal No.62 of 2019Appeal No.62 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appellant-promoter has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that they have complied with all the provisions of the Real Estate (Regulation and Development) Act, 2016.", "respondent_claim": "The respondent claimed that the appellant has not complied with the mandatory provisions of pre-deposit.", "final_verdict": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Shri Kapil ChaudharyShri Kapil Chaudhary | Link |
61 of 201961 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appellant has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that they have complied with the provisions of the Act.", "respondent_claim": "The respondent claimed that the appellant has not complied with the mandatory provisions of pre-deposit.", "final_verdict": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Narender KumarNarender Kumar | Link |
Appeal No.534 of 20…Appeal No.534 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appeal is restored and dismissed. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim(in detail)": "The appellant cla…{"appellant_claim(in detail)": "The appellant claims that they have not complied with the mandatory provisions of pre-deposit.", "respondent_claim(in detail)": "The respondent claims that the appellant has not complied with the mandatory provisions of pre-deposit.", "final_verdict(in detail)": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Sudhir Singh YadavSudhir Singh Yadav | Link |
Appeal No.457 of 20…Appeal No.457 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appeal is restored and dismissed. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim": "The appellant claims that th…{"appellant_claim": "The appellant claims that they have not complied with the mandatory provisions of pre-deposit.", "respondent_claim": "The respondent claims that the appellant has not complied with the mandatory provisions of pre-deposit.", "final_verdict": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Mrs. Nandani ModiMrs. Nandani Modi | Link |
358 of 2019358 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the provisions of pre-deposit. The appellant has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim(in detail)": "The appellant cla…{"appellant_claim(in detail)": "The appellant claimed that they have not complied with the provisions of pre-deposit due to certain reasons.", "respondent_claim(in detail)": "The respondent claimed that the appellant has not complied with the provisions of pre-deposit and therefore the appeal should be dismissed.", "final_verdict(in detail)": "The appeal is dismissed as the appellant has not complied with the provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Sudhish GuptaSudhish Gupta | Link |
Appeal No.456 of 20…Appeal No.456 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appellant has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim(in detail)": "The appellant cla…{"appellant_claim(in detail)": "The appellant claimed that they have complied with all the provisions of the Real Estate (Regulation and Development) Act, 2016.", "respondent_claim(in detail)": "The respondent claimed that the appellant has not complied with the mandatory provisions of pre-deposit.", "final_verdict(in detail)": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Dharampal SinghDharampal Singh | Link |
Appeal No.289 of 20…Appeal No.289 of 2019 | HaryanaHaryana | The appeal is dismissed as the appellant has not …The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appellant has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. | ["Non-compliance of…["Non-compliance of pre-deposit"] | {"appellant_claim(in detail)": "The appellant cla…{"appellant_claim(in detail)": "The appellant claimed that they have complied with all the provisions of the Real Estate (Regulation and Development) Act, 2016 and therefore, the appeal should be entertained.", "respondent_claim(in detail)": "The respondent claimed that the appellant has not complied with the mandatory provisions of pre-deposit and therefore, the appeal cannot be entertained.", "final_verdict(in detail)": "The appeal is dismissed as the appellant has not complied with the mandatory provisions of pre-deposit. The appellant has not deposited any amount to comply with the provisions of proviso to Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | NavneetNavneet | Link |
Yearly Trend for these Cases
An analysis of the cases filed by the builder, Ansal Housing, which it won, revealed the following information.
The cases brought forth by Ansal Housing have revolved around several key themes, primarily focusing on the legality of orders that struck off the builder's defence, disputes related to compliance with legal directions, and issues regarding the withdrawal of appeals and settlement of disputes related to charges. These recurring topics indicate a complex interplay between the builder's operational compliance and the legal environment within which it operates.
Looking more closely, many of the disputes involve the striking off of the builder's defence due to claims of non-compliance with directions issued in previous orders. This suggests a contentious dynamic wherein procedural requirements play a critical role in litigation outcomes. Common themes such as 'Non-compliance with Directions' and 'Striking Off Defence Claims' highlight a litigation trend where the builder consistently contests the legality of actions taken by adjudicating authorities. The analysis shows that Ansal Housing often contends that such decisions were unwarranted, leading to a successful strike down of those orders.
One notable reason behind the builder's legal engagements appears to center on defending against claims that typically fall into penalty disputes, claims surrounding additional charges, and improper procedural actions from the opposing party. The data suggests that the builder frequently establishes its grounds for appeal successfully by demonstrating either that the procedural rules were improperly enforced against them or that opposing parties failed to provide adequate evidence justifying the initial judgments received against Ansal Housing.
The trend demonstrates that the builder was often victorious due to the insufficiency of evidence presented by the respondent, often coupled with failures on the part of these parties to meet the necessary compliance requirements. This highlights the builder's sharp legal acumen and its ability to leverage procedural nuances to its favor, reflecting positively on its response to potential litigation threats. Furthermore, instances of settlement indicate a willingness to resolve matters amicably, which can often be misconstrued as an admission of guilt, thus underscoring the need for deeper examination of the circumstances.
In essence, this analysis sheds light on the reputation of Ansal Housing within the broader real estate market. It presents a case where, despite many disputes, the builder remains a formidable entity, often defending itself against unreasonable claims. Such situations underline the reality that buyers may sometimes lodge claims that lack sufficient validity, prompting legitimate builders to engage in lengthy legal battles. This not only provides an insight into the legal landscape surrounding builders but also signals to potential buyers the importance of critical engagement with the information at hand.
Thus, for prospective buyers, it is essential to remain vigilant and informed. While it is crucial to acknowledge that not all builders operate without fault, this analysis of Ansal Housing's legal cases reinforces the understanding that unjust claims against builders can lead to a disproportionate legal toll. Buyers are encouraged to research thoroughly and form measured opinions about a builder's reputation rather than relying solely on anecdotes or unverified claims.
This table provides details of individual cases contributing to the summary above. Click rows to expand content. Use "Show More/Less" buttons below.
Case No. | State | Summary | Topic | Detailed Summary | Appellant | Respondent | Source |
---|---|---|---|---|---|---|---|
359 of 2019359 of 2019 | HaryanaHaryana | The appeal was dismissed as withdrawn after the p…The appeal was dismissed as withdrawn after the parties reached a settlement. The respondents agreed to pay additional charges and the appellant agreed to deliver possession of the plot. | ["Settlement", "Pos…["Settlement", "Possession of Plot"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the respondents had not paid additional charges.", "respondent_claim": "The respondents claimed that they had paid all necessary charges.", "final_verdict": "The appeal was dismissed as withdrawn after the parties reached a settlement.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Santosh KumariSantosh Kumari | Link |
203 of 2021203 of 2021 | HaryanaHaryana | M/s Ansal Housing Ltd. vs Mr. Col. Kulwant Singh.…M/s Ansal Housing Ltd. vs Mr. Col. Kulwant Singh. Appeal withdrawn by the appellant. | ["Withdrawal of App…["Withdrawal of Appeal"] | {"appellant_claim(in detail)": "The appellant wan…{"appellant_claim(in detail)": "The appellant wanted to withdraw the present appeal.", "respondent_claim(in detail)": "Not applicable as the respondent is not involved in the withdrawal process.", "final_verdict(in detail)": "The appeal was dismissed as withdrawn.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Col. Kulwant Si…Mr. Col. Kulwant Singh | Link |
Appeal No. 528 of 2…Appeal No. 528 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., sought rel…The appellant, M/s Ansal Housing Ltd., sought relief from the order striking off their defence in a complaint. The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs. | ["Real Estate", "Ap…["Real Estate", "Appellate Tribunal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that their defence was wrongly struck off, and they sought relief from the order.", "respondent_claim": "The respondent did not contest the appellant's claim.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Sumeet BhatiaMr. Sumeet Bhatia | Link |
Appeal No. 527 of 2…Appeal No. 527 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., sought rel…The appellant, M/s Ansal Housing Ltd., sought relief against the order striking off their defence. The tribunal granted one more opportunity to the appellant to produce documents and pay costs. | ["Real Estate", "Ap…["Real Estate", "Appellate Tribunal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that their defence was wrongly struck off and sought relief.", "respondent_claim": "The respondent did not contest the appellant's claim.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents and pay costs.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Vijay Singh Yad…Mr. Vijay Singh Yadav and Jyotisana Yadav | Link |
Appeal No. 525 of 2…Appeal No. 525 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., filed an a…The appellant, M/s Ansal Housing Ltd., filed an appeal against the order striking off their defence. The tribunal granted one more opportunity to the appellant to produce documents and pay costs. | ["Real Estate", "Ap…["Real Estate", "Appeal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that their defence was wrongly struck off and they were not given a fair opportunity to produce documents.", "respondent_claim": "The respondent claimed that the appellant had not complied with the orders of the learned authority and therefore their defence was struck off.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents and pay costs. If the appellant complies with the concession, the order striking off their defence will be deemed to have been set aside.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Varun Mittal & …Mr. Varun Mittal & Arpit Mittal | Link |
Appeal No. 524 of 2…Appeal No. 524 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., sought rel…The appellant, M/s Ansal Housing Ltd., sought relief from the order striking off their defence in a complaint. The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs. | ["Real Estate", "Ap…["Real Estate", "Appellate Tribunal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the order striking off their defence was wrong and sought relief.", "respondent_claim": "The respondent did not contest the appellant's claim.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mrs. Jyotsna Makan …Mrs. Jyotsna Makan & Sandeep Makan | Link |
523 of 2021523 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., filed an a…The appellant, M/s Ansal Housing Ltd., filed an appeal against the order striking off their defence. The tribunal granted one more opportunity to the appellant to produce documents and pay additional costs. | ["Real Estate", "Ap…["Real Estate", "Appeal"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that their defence was wrongly struck off and they were not given sufficient opportunity to produce documents.", "respondent_claim": "The respondent claimed that the appellant had not complied with the orders of the learned authority and had not paid the costs imposed.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents and pay additional costs. If the appellant complies with the concession, the order striking the defence will be deemed to have been set aside.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Bhavya JainBhavya Jain | Link |
Appeal No. 522 of 2…Appeal No. 522 of 2021 | HaryanaHaryana | The appeal was allowed and the impugned order str…The appeal was allowed and the impugned order striking the defence of the appellant was set aside. The learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case. | ["Jurisdiction", "S…["Jurisdiction", "Striking off defence"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case.", "respondent_claim": "The respondent claimed that the learned Adjudicating Officer was justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019.", "final_verdict": "The appeal was allowed and the impugned order striking the defence of the appellant was set aside.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Kapil BanduniMr. Kapil Banduni | Link |
521 of 2021521 of 2021 | HaryanaHaryana | The appeal was allowed and the impugned order str…The appeal was allowed and the impugned order striking the defence of the appellant was set aside. The learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case. | ["Jurisdiction of A…["Jurisdiction of Adjudicating Officer", "Validity of order striking off defence"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case.", "respondent_claim": "The respondent claimed that the learned Adjudicating Officer was justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019.", "final_verdict": "The appeal was allowed and the impugned order striking the defence of the appellant was set aside.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Ruchi Singh and Sne…Ruchi Singh and Sneh Lata Singh | Link |
520 of 2021520 of 2021 | HaryanaHaryana | The appeal was allowed and the impugned order str…The appeal was allowed and the impugned order striking the defence of the appellant was set aside. The learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case. | ["Jurisdiction of A…["Jurisdiction of Adjudicating Officer", "Striking off defence of appellant"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the learned Adjudicating Officer was not justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019 which was in fact never passed in the present case.", "respondent_claim": "The respondent claimed that the learned Adjudicating Officer was justified to strike off the defence of the appellant due to non-compliance of the directions given vide order dated 19.11.2019.", "final_verdict": "The appeal was allowed and the impugned order striking the defence of the appellant was set aside.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Jaspal SinghJaspal Singh | Link |
Appeal No. 526 of 2…Appeal No. 526 of 2021 | HaryanaHaryana | The appellant, M/s Ansal Housing Ltd., sought rel…The appellant, M/s Ansal Housing Ltd., sought relief from the order striking off their defence in a complaint. The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs. | ["Real Estate", "RE…["Real Estate", "RERA"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the order striking off their defence was wrongful and sought relief.", "respondent_claim": "The respondent did not contest the appellant's claim.", "final_verdict": "The tribunal granted one more opportunity to the appellant to produce documents, subject to further costs.", "in_favor_of_respondent": "no"} | Ansal Housing Limit…Ansal Housing Limited | Mr. Jagan KumarMr. Jagan Kumar | Link |
Yearly Trend for these Cases
An analysis of the cases filed against the builder Ansal Housing, which the builder won, revealed the following information.
The disputes emerged around several key themes:
The reasons for bringing these cases to court mainly revolve around contesting penalties for perceived delivery delays, disputes over the interpretation of settlement agreements, or failure to comply with certain agreements made with buyers. It reflects a pattern where buyers may sometimes feel aggrieved and opt for legal remedies even in cases where the builder may argue that their actions were compliant or justified.
The builder’s success in these cases stemmed from various factors. There were several instances where the opposing parties did not meet their legal obligations or failed to provide sufficient evidence to substantiate their claims. Furthermore, many complaints were dismissed as withdrawn or settled amicably, suggesting that the builder maintained a strong position in negotiations or discussions.
This analysis provides valuable insights into Ansal Housing's reputation in the real estate market. It suggests that while some buyers may genuinely feel wronged, there is a possibility that not all claims are valid. Ansal Housing’s ability to effectively contest and win these legal battles indicates a strong legal backing and operational integrity.
To potential buyers, this analysis underscores the importance of making informed decisions in the real estate market. Buyers should critically evaluate the circumstances and information available before forming opinions about a builder's reputation. Legitimate disputes do exist within the industry, but builders like Ansal Housing have shown a propensity to defend themselves against unjust claims. It is crucial for buyers to seek reliable information before entering agreements and forming judgments about builders.
This table provides details of individual cases contributing to the summary above. Click rows to expand content. Use "Show More/Less" buttons below.
Case No. | State | Summary | Topic | Detailed Summary | Appellant | Respondent | Source |
---|---|---|---|---|---|---|---|
CR/4484/2021CR/4484/2021 | HaryanaHaryana | The complainant sought modification of an order d…The complainant sought modification of an order dated 21.10.2022, but the authority declined the application as it is not empowered to review its orders. | ["Modification of o…["Modification of order", "Authority's powers"] | {"appellant_claim": "The complainant sought modif…{"appellant_claim": "The complainant sought modification of the order dated 21.10.2022, claiming that the terms of the settlement agreement had not been complied with.", "respondent_claim": "The respondent argued that the authority is not empowered to review its orders.", "final_verdict": "The authority declined the application, stating that it is not empowered to review its orders.", "in_favor_of_respondent": "yes"} | Shimpy GuptaShimpy Gupta | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/4472/2021CR/4472/2021 | HaryanaHaryana | The complainant sought modification of an order d…The complainant sought modification of an order dated 21.10.2022, but the authority declined the application as it is not empowered to review its orders. | ["Modification of O…["Modification of Order", "Review of Decision"] | {"appellant_claim": "The complainant sought modif…{"appellant_claim": "The complainant sought modification of an order dated 21.10.2022, stating that the present complaint was disposed of merely on the basis of the copy of the settlement agreement produced by the respondent and without appreciating the stipulations in the agreement.", "respondent_claim": "The respondent claimed that the authority is not empowered to review its orders and that the application for rectification is not maintainable.", "final_verdict": "The authority declined the application for modification of the order dated 21.10.2022, stating that it is not empowered to review its orders.", "in_favor_of_respondent": "yes"} | Partyasha RathPartyasha Rath | Ansal Housing Limit…Ansal Housing Limited | Link |
CR/4483/2021CR/4483/2021 | HaryanaHaryana | The complainant sought rectification of an order …The complainant sought rectification of an order dated 21.10.2022, but the authority declined the application as it was filed after the prescribed period and the authority is not empowered to review its orders. | ["Rectification of …["Rectification of Order", "Authority's Powers"] | {"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the terms of the settlement agreement dated 11.10.2022 have not been complied with and sought rectification of the order dated 21.10.2022.", "respondent_claim": "The respondent claimed that the authority is not empowered to review its orders and that the application for rectification is filed after the prescribed period.", "final_verdict": "The authority declined the application for rectification and held that it is not empowered to review its orders.", "in_favor_of_respondent": "yes"} | Anjali SinghAnjali Singh | Ansal Housing Limit…Ansal Housing Limited | Link |
2488 of 20192488 of 2019 | HaryanaHaryana | The case involves a penalty imposed on a real est…The case involves a penalty imposed on a real estate promoter for not submitting online A-H Proforma. The Authority waived off the penalty for a certain period and the remaining amount was paid. | ["Penalty waiver"]["Penalty waiver"] | {"appellant_claim": "", "respondent_claim": "", "…{"appellant_claim": "", "respondent_claim": "", "final_verdict": "The Authority decided to discharge the notice and waive off the penalty for a certain period.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Link | |
1680 of 20221680 of 2022 | HaryanaHaryana | Suo-motu complaint against Ansal Housing Ltd. for…Suo-motu complaint against Ansal Housing Ltd. for not uploading quarterly progress reports. Notice discharged as reports uploaded up to June 2022. | ["Non-uploaded prog…["Non-uploaded progress reports"] | {"appellant_claim": "Not provided", "respondent_c…{"appellant_claim": "Not provided", "respondent_claim": "Not provided", "final_verdict": "Notice discharged as quarterly progress reports uploaded up to June 2022.", "in_favor_of_respondent": "yes"} | Ansal Housing Limit…Ansal Housing Limited | Link | |
APPEAL-269/2021APPEAL-269/2021 | Uttar PradeshUttar Pradesh | The appeal was dismissed due to non-compliance wi…The appeal was dismissed due to non-compliance with the provisions of Section 43(5) of the Act. The builder-company failed to deposit the required amount. | ["Non-compliance wi…["Non-compliance with Section 43(5) of the Act"] | {"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that they were not in a position to deposit the amount required under Section 43(5) of the Act due to financial crises.", "respondent_claim": "The respondents claimed that the appellant failed to comply with the provisions of Section 43(5) of the Act.", "final_verdict": "The appeal was dismissed due to non-compliance with the provisions of Section 43(5) of the Act.", "in_favor_of_respondent": "yes"} | ANSAL HOUSING AND C…ANSAL HOUSING AND CONSTRUCTION Limited | ANKIT GOELANKIT GOEL | Link |
No reviews for this builder yet. Be the first one to share your thoughts!