Overall Case Outcomes
Archana Construction And Land Developers is a builder operating in the state of Madhya Pradesh. While the builder has undertaken projects in this region, it is essential for potential buyers to consider their track record carefully.
The builder has faced one recorded complaint, which highlights concerns over the timely completion of projects. Understanding the nuances of this case can offer insights into the builder’s practices and how they handle legal disputes.
From the information provided, it is evident that the primary factor leading to the builder’s loss in the one legal case involved non-completion of the project and delays in possession handover. The case underlines the importance of adhering to timelines and fulfilling contractual obligations.
Notably, the builder has yet to win a case on the basis of merit, as the data indicates only a single legal case with the verdict being against them. This absence of successful defenses raises concerns regarding their ability to navigate disputes effectively.
Based on the available data, Archana Construction And Land Developers has encountered issues with project completion and has not successfully defended their interests in legal matters. The single complaint and subsequent ruling against them serve as a cautionary tale for potential purchasers.
By adhering to these practices, potential buyers can better protect themselves and make informed decisions when considering investments in real estate.
Yearly Trend for these Cases
Analysis of the cases filed against Archana Construction And Land Developers, where the builder lost, revealed several key themes and patterns. The cases primarily revolved around delayed possession claims, highlighting significant disputes between the builder and the applicants regarding timely completion and handover of properties.
One of the most notable reasons for these disputes was the builder's defense related to the COVID-19 pandemic. The builder frequently attributed delays in construction work to the pandemic and the ensuing lockdowns, which raised important considerations about the impact of external factors on contractual obligations in the construction sector. However, the legal verdicts did not accept this defense as sufficient to negate the builder's responsibility to deliver completed projects on time, leading to decisions mandating compensation payments to the applicants.
The common thread among the applicants' claims was the assertion that they had paid the full consideration amount for their flats yet faced prolonged waiting periods without possession. This raised questions about the builder's adherence to standard practices and regulatory requirements governing real estate transactions. The implications of these cases suggest that buyers found it necessary to resort to legal action primarily due to a lack of communication or accountability from the builder's side regarding project timelines and completion statuses.
The builder's losses in these cases can be attributed to several factors. Insufficient evidence to support their claims of pandemic-related delays was a critical shortcoming. Moreover, the builder's failure to adhere to timelines established by the courts for completing outstanding work resulted in further legal repercussions. These patterns indicate a broader issue with the builder's operational practices, potentially involving inadequate project management and a lack of compliance with regulatory frameworks that safeguard consumer rights in the real estate market.