Complaint Case No.1…Complaint Case No.187 of 2023 |
OdishaOdisha |
The complainant, Swarupa Sahu, filed a complaint …The complainant, Swarupa Sahu, filed a complaint against M/s Arundhati Infratech Pvt. Ltd. and its directors for not completing the construction of a simplex house as per the agreement. The authority directed the respondents to complete the construction, provide all facilities, and hand over possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Non-provision of facilities"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house as per the agreement and did not provide all the facilities mentioned in the agreement.", "respondent_claim": "The respondents claimed that the complainant did not pay the balance consideration amount and that the construction was delayed due to the complainant's non-cooperation.", "final_verdict": "The authority directed the respondents to complete the construction of the simplex house, provide all the facilities mentioned in the agreement, and hand over possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Swarupa SahuSwarupa Sahu |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.186 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the simplex house as per the construction agreement and for not providing the necessary amenities. The authority directed the respondents to complete the house and provide the amenities within a period of three months. |
["Non-completion of…["Non-completion of simplex house", "Non-provision of amenities"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the simplex house as per the construction agreement and did not provide the necessary amenities.", "respondent_claim": "The respondents claimed that the complainant did not pay the full amount due to them and that the delay in completion was due to the complainant's non-payment.", "final_verdict": "The authority directed the respondents to complete the house and provide the amenities within a period of three months.", "in_favor_of_respondent": "no"} |
Gurucharan MohapatraGurucharan Mohapatra |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
185 of 2023185 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of the simplex house and not handing over the possession of the house despite receiving the full payment. The authority directed the respondents to complete the construction of the house, obtain the completion and occupancy certificate, and hand over the possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Non-handover of possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house and did not hand over the possession of the house despite receiving the full payment.", "respondent_claim": "The respondents claimed that the complainant did not pay the instalments on time and that the delay in completion of the construction was due to the complainant's fault.", "final_verdict": "The authority directed the respondents to complete the construction of the house, obtain the completion and occupancy certificate, and hand over the possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Manmohan SahuManmohan Sahu |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.184 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of a simplex house and not handing over possession of the house despite receiving payment. The authority directed the respondents to complete the construction, obtain completion and occupancy certificate, and hand over possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Non-handover of possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house and did not hand over possession of the house despite receiving payment.", "respondent_claim": "The respondents claimed that the complainant stopped payment and hindered the construction work.", "final_verdict": "The authority directed the respondents to complete the construction, obtain completion and occupancy certificate, and hand over possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Birabara PradhanBirabara Pradhan |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.192 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of a simplex house as per the agreement. The authority directed the respondents to complete the construction, obtain completion and occupancy certificate, and hand over possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Non-handover of possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house as per the agreement and did not hand over possession of the house to her.", "respondent_claim": "The respondents claimed that the complainant did not pay the instalments on time and that was the reason for the delay in completion of the construction.", "final_verdict": "The authority directed the respondents to complete the construction, obtain completion and occupancy certificate, and hand over possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Monita PaloMonita Palo |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.191 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of a simplex house and not handing over the possession of the house despite receiving the payment. The authority directed the respondents to complete the construction of the house, obtain completion and occupancy certificate, and hand over the possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Non-handover of possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house and did not hand over the possession of the house despite receiving the payment.", "respondent_claim": "The respondents claimed that they had completed the construction of the house and had handed over the possession of the house to the complainant.", "final_verdict": "The authority directed the respondents to complete the construction of the house, obtain completion and occupancy certificate, and hand over the possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Ajit Kumar PradhanAjit Kumar Pradhan |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.190 of 2023 |
OdishaOdisha |
The complainants filed a case against the respond…The complainants filed a case against the respondents for not completing the construction of a simplex house and not providing the necessary amenities. The authority directed the respondents to complete the construction, provide the amenities, and pay interest for the delay. |
["Non-completion of…["Non-completion of construction", "Non-provision of amenities"] |
{"appellant_claim": "The complainants claimed tha…{"appellant_claim": "The complainants claimed that the respondents did not complete the construction of the simplex house and did not provide the necessary amenities as per the agreement.", "respondent_claim": "The respondents claimed that the complainants did not pay the instalments on time and that the delay was due to the complainants' non-response.", "final_verdict": "The authority directed the respondents to complete the construction of the simplex house, provide the necessary amenities, and pay interest for the delay.", "in_favor_of_respondent": "no"} |
Bandana MishraBandana Mishra |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Complaint Case No.1…Complaint Case No.189 of 2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of a simplex house as per the agreement and for not providing the necessary amenities. The authority directed the respondents to complete the construction, provide the amenities, and hand over the possession of the house to the complainant. |
Non-completion of c…Non-completion of construction and non-provision of amenities |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house as per the agreement and did not provide the necessary amenities.", "respondent_claim": "The respondents claimed that the complainant did not pay the remaining amount of Rs.3,80,000/- and that the delay in completion of the work was due to the non-response of the complainant in paying the installments in time.", "final_verdict": "The authority directed the respondents to complete the construction of the simplex house, provide the necessary amenities, and hand over the possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Sudhir Kumar BeheraSudhir Kumar Behera |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
i188_of_2023i188_of_2023 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of the simplex house and not handing over the possession of the house despite receiving the full payment. The respondents were directed to complete the construction, obtain completion and occupancy certificate, hand over the possession of the house, and execute a conveyance deed in favor of the complainant. |
["Non-completion of…["Non-completion of construction", "Non-handover of possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the simplex house and did not hand over the possession of the house despite receiving the full payment of Rs. 17,00,000/-.", "respondent_claim": "The respondents claimed that the complainant did not pay the installments on time and that the project was not completed due to the complainant's fault.", "final_verdict": "The respondents were directed to complete the construction of the simplex house, obtain completion and occupancy certificate, hand over the possession of the house, and execute a conveyance deed in favor of the complainant.", "in_favor_of_respondent": "no"} |
|
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
Suo Motu Complaint …Suo Motu Complaint Case No.328 of 2022 |
OdishaOdisha |
The case was initiated against Arundhati Infratec…The case was initiated against Arundhati Infratech Pvt. Ltd. and its Managing Director for violating an order passed by the Odisha Real Estate Regulatory Authority. The Authority imposed a penalty of Rs. 2,58,000 for the default. |
["Non-compliance of…["Non-compliance of order", "Penalty for default"] |
{"appellant_claim": "The appellant claimed that t…{"appellant_claim": "The appellant claimed that the respondents had failed to comply with the order passed by the Authority on 21.05.2022.", "respondent_claim": "The respondents claimed that their account had been seized by the EOW and they cannot be held liable unless the agreement is cancelled.", "final_verdict": "The Authority imposed a penalty of Rs. 2,58,000 on the respondents for violating the order.", "in_favor_of_respondent": "no"} |
ORERAORERA |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |
277 of 2021277 of 2021 |
OdishaOdisha |
The complainant filed a case against the responde…The complainant filed a case against the respondents for not completing the construction of a duplex house and not giving possession of the house despite receiving the full payment. The authority directed the respondents to complete the construction and give possession of the house to the complainant. |
["Non-completion of…["Non-completion of construction", "Delay in possession"] |
{"appellant_claim": "The complainant claimed that…{"appellant_claim": "The complainant claimed that the respondents did not complete the construction of the duplex house and did not give possession of the house despite receiving the full payment.", "respondent_claim": "The respondents claimed that the complainant did not pay the balance consideration amount and that was the reason for the delay in completion of the construction.", "final_verdict": "The authority directed the respondents to complete the construction and give possession of the house to the complainant.", "in_favor_of_respondent": "no"} |
Subhankar MishraSubhankar Mishra |
Arundhati Infratech…Arundhati Infratech Private Limited |
Link |