In the competitive world of real estate, selecting the right builder is crucial for ensuring a satisfactory home-buying experience. One such builder is Himanshu Infrastructure Pvt. Ltd., which has drawn attention due to its legal history and project footprints mainly located in Madhya Pradesh. In this blog post, we will analyze the performance of Himanshu Infrastructure based on the complaints filed against them and how they have handled legal challenges.
No builder reviews yet. Be the first to share your thoughts!
Here you’ll find cases where others sued the builder, and the builder lost. We’ve included a simple summary and key takeaways from each case.
Analysis of the cases filed against Himanshu Infrastructure Pvt. Ltd., which the builder lost, reveals several key themes and key pieces of information across the board.
The cases against the builder primarily revolve around three common themes: Delayed Possession Claims, Non-Completion of Construction Disputes, and the builder's frequent reliance on the Unforeseen Circumstances Defense.
The Delayed Possession Claims involve the builder failing to deliver completed flats to buyers within the stipulated timeline. In these cases, buyers sought compensation for the delay in possession, which reflects a growing concern among buyers about builders' ability to meet project timelines.
Non-Completion of Construction Disputes complement the delay claims, as they often intersect with issues of unfinished projects. Buyers in these cases expressed dissatisfaction not only with the delay in moving into their new homes but also with the incomplete state of the construction, which could lead to additional complications and costs down the line.
The builder consistently cited Unforeseen Circumstances as their defense in these cases. They attributed delays and non-completion of projects to events beyond their control, which they claimed exempted them from responsibility. However, the legal outcomes suggest that this defense did not resonate with the courts, indicating a level of disfavor towards builders who blame circumstance rather than taking responsibility for their projects.
A pattern emerges from these summaries: buyers commonly contest the builder’s timelines and project completion status. The primary trigger for litigation seems to be the builder’s inability to fulfill their contractual obligations, particularly concerning timely delivery and complete construction of flats.
The builder lost these cases likely due to insufficient evidence supporting their claims of unforeseen circumstances. It’s also possible that they failed to comply with legal or regulatory requirements governing construction timelines and project completion, which would have undermined their defense further.
Overall, these findings highlight the importance for potential buyers to be vigilant when engaging with builders, ensuring they assess thoroughly the builder's track record, understand the terms of their contracts, and are aware of their legal rights in the event of delays or disputes.
This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.
Case Number | State | Summary | Case Topic | Detailed Summary | Appellant Name | Respondent Name | Source |
---|---|---|---|---|---|---|---|
-छाग -.48--0409 | Madhya Pradesh | The appellant sought compensation for delay in po… | ["Delay in possessi… | {"appellant_claim": "The appellant claimed compen… | श्री रामबाबू रघुवंशी | Himanshu Infrastruc… | https://www.rera.mp.gov.in/upload/complaint_files/206215106218.pdf |