builder logo

IMPERIA STRUCTURES LIMITED

  • No of Complaints: 53
  • States (Active in): Haryana, Uttar Pradesh
CIN U45400DL2010PLC198791
Year Established 5-Feb-10
Address A - 25, MOHAN CO - OPERATIVE INDUSTRIAL ESTATE MATHURA ROAD NA NEW DELHI DL 110044 IN
Company Status Public

Overview of Imperia Structures Limited

Imperia Structures Limited is a notable player in the real estate sector, primarily operating in the states of Haryana and Uttar Pradesh. With a considerable history in property development, the company faces scrutiny from current and potential buyers alike, especially regarding its legal history and complaint resolutions.

Legal Performance Analysis

In total, Imperia Structures Limited has received 53 complaints over time. Of these, the builder has won 7 cases while losing 46 cases. This indicates a somewhat concerning trend, as the majority of the legal outcomes have not favored the builder.

Patterns in Lost Cases

  1. Withdrawal or Dismissal of Complaints: Several of the cases lost by the builder were either dismissed due to the complainants’ failure to appear or were withdrawn by the complainants, often suggesting issues with prosecution or satisfaction outside the tribunal. For instance, there were complaints dismissed for want of prosecution or withdrawn due to settlements.
  2. Claims Relating to Delay and Possession: Common themes in the cases lost include allegations regarding delays in possession and construction. The builder was often found to have not delivered possessions as agreed, with complainants successfully claiming refunds or interest for delays.
  3. Legal Technicalities: In some lost cases, failures stemmed from procedural issues, such as the builder failing to include relevant parties in complaints or inadequately addressing claims.

Patterns in Won Cases

  1. Default Dismissals: The majority of cases won were dismissed due to the absence of complainants during hearings. This suggests that a considerable number of disputes may lack the necessary follow-through from buyers.
  2. Compensation and Refund Disputes: Successful outcomes for the builder typically stemmed from disputes where the complainants could not adequately prove their claims, especially relating to compensation sought for construction delays or non-deliveries.
  3. Compliance with Agreements: In won cases, the builder often defended claims by proving adherence to agreed-upon timelines or contractual obligations, showing that they were able to argue effectively wherever they could demonstrate compliance.

Conclusion

Based on the legal performance of Imperia Structures Limited, potential buyers should proceed with caution. With a high number of complaints and a significant rate of cases lost, this builder's track record indicates potential risks for customers seeking timely delivery and satisfaction. However, it’s noteworthy that some disputes stem from broader systemic issues within the industry, rather than solely from builder negligence.

Tips for Potential Buyers

  1. Thoroughly Research: Before engaging with Imperia Structures Limited or any builder, conduct detailed research on their history, financial standing, and legal history.
  2. Visit Projects: If possible, visit existing projects to gauge the quality of construction and talk to current residents about their experiences.
  3. Check for Documentation: Ensure all agreements are documented and clearly outline timelines, penalty clauses for delays, and payment terms.
  4. Seek Expert Opinion: Consider consulting with legal experts or real estate professionals to better understand your rights as a buyer and any potential ramifications of contracts.
  5. Be Proactive in Communication: Maintain constant communication with the builder throughout the procurement process to stay informed about project progress and any changes.

General Tips for Selecting Any Builder

  1. Check Reviews and Ratings: Explore online reviews and ratings from other homeowners and check complaint resolutions on consumer forums.
  2. Look for Accountability: Choose builders who are transparent about their processes and willing to take responsibility for any issues that arise.
  3. Review Their Portfolio: Look into their previous projects and success stories to affirm their competency in delivering what they promise.
  4. Legal Compliance: Ensure that the builder is compliant with local regulations and has the necessary approvals for development.
  5. Understand the Fine Print: Always read the fine print of the buyer's agreement, especially clauses relating to delays, possession, and refunds.

By employing these insights, potential buyers can make informed choices when deciding whether to trust Imperia Structures Limited with their real estate investments.

No builder reviews yet. Be the first to share your thoughts!

Delayed Possession Claims Refund and Compensation Disputes Interest Payment Delays Force Majeure and Unforeseen Circumstances Compliance with Agreements and Regulations
Error

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
APPEAL-466/2021 Uttar Pradesh The appellant filed an appeal with delay, and the… ["Condonation of de… {"appellant_claim(in detail)": "The appellant fil… BHAWANA 2 IMPERIA STRUCTURES … ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85NDg5OTI0NjYtMjAyMS5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy80OTA0N2E0NjYucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy81Mjc5NDVkIDQ2Ni0yMDIxLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yMTU1OTRhNDY2b2YyMDIxLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNDgxOTVkIDQ2Ni0yMDIxLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xODYyNzE0NjYtMjAyMS5wZGY=']
APPEAL-581/2020 Uttar Pradesh The appeal was filed on 02.11.2020, and the delay… ["Limitation", "Con… {"appellant_claim(in detail)": "The appellant cla… ASHOK KUMAR LAL IMPERIA STRUCTURES … ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MzM5MTM1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy80MjQ2MDk1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy84MTQ5MzY1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNzE1NDNhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNjU4NjE1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xOTM3YSA1ODEgMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8zNTgwMjFhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8zMzY2MzY1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8zODUyNTlhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82MzU2ODc1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy84Mjc0NzE1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yNjY1Njc1ODEtMjAyMC5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy84MTg1NDRhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82MDMxNDhhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xODA5NmEgNTgxIDIwMjAucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNzQ1NzJhIDU4MSAyMDIwLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8zMDg4MjhhNTgxLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MDEzMTFtYzU4MS5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82MTc3NTFtYzU4MS5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8zODEwNDA1ODEgb2YgMjAucGRm']
CR/250/2021 Haryana The case was settled between the parties amicably… ["Settlement"] {"appellant_claim(in detail)": "Not provided", "r… ANIL KUMAR IMPERIA STRUCTURES … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTUxMzEw
890/2018 Haryana Complainant Himanshu Giri filed a complaint again… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Himanshu Giri Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NjY0Ng==
2801 of 2019 Haryana The complainants filed a complaint against the re… ["Delay in possessi… {"appellant_claim": "The complainants claimed tha… Shri RK Handa Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NDg5MTE=
2110 of 2019 Haryana The complainants filed a complaint against the re… ["Delay in possessi… {"appellant_claim": "The complainants claimed tha… Smt. Pratibha Khan Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NDg5MTA=
3260 of 2020 Haryana The complainants filed a complaint against the re… ["Delay in possessi… {"appellant_claim": "The complainants claimed tha… Nishu Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NjU5ODk=
3259 of 2020 Haryana The complainants alleged that the respondent dela… ["Delayed Possessio… {"appellant_claim": "The complainants alleged tha… Jyoti Bajaj Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NjU5ODg=
3202 of 2020 Haryana The complainants filed a complaint against M/s Im… ["Violation of sect… {"appellant_claim": "The complainants claimed tha… Nirmala Singh Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NjU5ODc=
902/2018 Haryana Complainant sought refund of Rs.75,56,563 deposit… ["Refund for delaye… {"appellant_claim": "Seeking refund of Rs.75,56,5… Vipul Agarwal Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NTgxMTk=
487 of 2020 Haryana The complainant sought delay possession charges f… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Manu Maan Singh Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NzQ4ODE=
3954 of 2020 Haryana The complainants filed a complaint against the re… ["Delay in possessi… {"appellant_claim": "The complainants claimed tha… Ramola Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/ODY0MDg=
119 of 2020 Haryana The complainant sought delay possession charges f… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Shri Hemant Kumar D… Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/ODYzOTg=
6001 of 2019 Haryana The complainant sought delay possession charges f… ["Delay possession … {"appellant_claim": "The complainant sought delay… Shri Rajesh Mittal Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/ODY0MDc=
3738 of 2020 Haryana The complainant, Mr. Anurag Verma, filed a compla… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Mr. Anurag Verma Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/ODY0MDY=
3006 of 2020 Haryana Complainant sought refund for delayed possession … ["Delayed possessio… {"appellant_claim(in detail)": "Complainant booke… Shashank Kumar Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTAxMzE2
4832 of 2020 Haryana The complainant sought refund of Rs. 95,86,140/- … ["Refund for delaye… {"appellant_claim": "The complainant claimed refu… Jaspreet Singh Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTAxMzE3
2130 of 2018 Haryana The complainant sought refund of Rs. 3,07,725/- w… ["Refund for delay … {"appellant_claim(in detail)": "The complainant b… Sh. Pramod Kumar Ar… Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTEyMjIw
3175 of 2019 Haryana Complainant sought refund and compensation for no… ["Non-delivery of p… {"appellant_claim": "The complainant claimed that… Sudha Sharma Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTE0MTc3
4494 of 2021 Haryana The complainant sought relief for delay in posses… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Pankaj Kumar Verma Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTIwOTk5
6240 of 2019 Haryana The complainant sought refund of Rs. 73,37,269/- … ["Delayed possessio… {"appellant_claim": "The complainant claimed that… Harjeet Kaur Dhillon Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTIwOTk2
680 of 2022 Haryana The complainant sought delay possession charges a… ["Delay possession … {"appellant_claim": "The complainant claimed that… Chavi Priya Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTMxMTM2
4397 of 2021 Haryana Complainant sought refund and compensation for de… ["Delayed possessio… {"appellant_claim": "Complainant sought refund an… Gagandeep Singh Jos… Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTM1MTY5
7600 of 2022 Haryana The complainants sought relief for delayed posses… ["Delayed Possessio… {"appellant_claim": "The complainants claimed tha… Shailendra Kumar Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTQyNDE2
CR/2370/2022 Haryana The complainants sought refund of the amount paid… ["Refund", "Possess… {"appellant_claim": "The complainants claimed tha… Sarita Sikchi Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTUwMTk1
134 of 2023 Haryana The complainant sought delay possession charges a… ["Delay in possessi… {"appellant_claim": "The complainant claimed that… Manoj Gandhi Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTQ2NTA3
7936 of 2022 Haryana The complainant booked a virtual space in the pro… ["Assured Return", … {"appellant_claim": "The complainant claimed that… Sunil Chhabra Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTQ2NTA2
5788 of 2022 Haryana The complainants, Praful Rawat and Deepti Rawat, … ["Violation of sect… {"appellant_claim": "The complainants claimed tha… Deepti Rawat Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTU0MDIx
1461 of 2022 Haryana The complainants sought refund of the amount paid… ["Refund of amount … {"appellant_claim": "The complainants sought refu… Pomilla Agarwal Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTU0OTM3
CR/6058/2022 Haryana Anubhav and Supriya vs Imperia Structures Limited… ["Non-appearance of… {"appellant_claim(in detail)": "The complainants,… Supriya Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTgxMjgz
APPEAL-661/2022 Uttar Pradesh The appellant filed an appeal for condonation of … ["Condonation of de… {"appellant_claim": "The appellant claimed that h… SUSHIL KUMAR BAGGA IMPERIA STRUCTURES … ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy84MTE5MTM2NjEtMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MDE4MzI2NjEtMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yNzI0NTY2NjEtMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy80NzQ4ODY2MS0yMDIyLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82ODI3OTg2MjEtMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNDEwNzlhNjYxLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yODc1OTY2NjEtMjAyMi5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy80NDE1Nzc2NjEtMjAyMi5wZGY=']
CR/4785/2021 Haryana The complainants, Regina Ranjani Devi Gupta and S… ["Delay in possessi… {"appellant_claim": "The complainants claimed tha… Sunil Gupta Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTM3OTIx
Release of Deposited Amounts Disputes over Appeal Dismissals Claims for Payments by Respondents

An analysis of the cases filed by the builder Imperia Structures Limited, which it lost, reveals several insights into the nature of their disputes and the recurring themes surrounding them.

The key themes identified in these cases include the release of deposited amounts and disputes arising from claims tied to the dismissal of appeals. In these instances, the respondents consistently claimed that the appeals initiated by the builder had been dismissed, which directly led to their request for the release of amounts deposited during litigation.

The common reasons for the builder bringing cases to court typically revolved around contesting unfavorable decisions, seeking reversal of judgments, and disputing the penalties or financial liabilities they faced as a result of the tribunal’s actions. However, in the cases we've examined, it appears that such appeals were often met with dismissals, indicating a pattern where the builder might struggle to substantiate its cases against the claims made by the respondents.

A closer look reveals that the reasons contributing to the builder's losses in these legal battles include insufficient evidence to support their claims, non-compliance with ongoing legal or regulatory orders, and possible misunderstandings related to the applicability of certain legal standards in their situations. The tribunal’s decisions reflected a need for stricter adherence to legal requirements, which the builder may not have met adequately.

Overall, these cases shed light on potential areas for improvement for Imperia Structures Limited. It becomes apparent that a more robust approach to documentation, compliance with legal norms, and thorough evaluations of claims prior to entering into legal disputes may significantly bolster their position in future litigation.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
TA-1539/2021 Uttar Pradesh The applicant/appellant deposited an amount towar… ["Release of deposi… {"appellant_claim": "Not provided", "respondent_c… IMPERIA STRUCTURES … ASHOK KUMAR GUPTA ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy81NjExNzJtIDYxMyAyMDE5LnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy83NTI2MjdpYSAxNTM5IDIwMjEucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xNjU4NzBtIDYxMyAyMDE5LnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yNTIyODFpYSAxNTM5LTIwMjEucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82Njc4MDNpYSAxNTM5LTIwMjEucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MjE4NTdpYSAxNTM5LTIwMjEucGRm']
Delayed Possession Claims Force Majeure Defenses Interest Payment Disputes Validity of Possession Offers

An analysis of the cases filed by the builder, IMPERIA STRUCTURES LIMITED, which it won, revealed the following insights.

Delayed Possession Claims:

A recurring theme in the disputes involves delays in handing over possession of flats to the buyers. Complainants have consistently claimed that the builder did not deliver their units by the agreed-upon date, often seeking significant interest payments for the delay.

Force Majeure Defenses:

In response to these claims, the builder frequently cited force majeure circumstances as justification for the delays. This defense revolves around unforeseen events that are beyond the builder's control, which they argued affected their ability to meet deadlines.

Interest Payment Disputes:

Another common issue is the disagreement over the percentage of interest applicable for delays. While complainants often seek high rates, the builder has been able to contest these demands and settle on significantly lower rates directed by the authority.

Validity of Possession Offers:

Some cases also involved disputes over the validity of possession offers made by the builder. The implications hinge on whether the builder had fully complied with the necessary preconditions, such as obtaining mandatory occupancy certificates before making possession offers.

The builder commonly brought these cases to court to contest penalties related to delays, disproving claims of negligence, and clarifying misunderstandings about the obligations under the sale agreements. A pattern emerges wherein the builder often found itself defending against exaggerated claims from buyers or competing parties, which shows how disputes in the real estate sector can sometimes arise from miscommunication or misunderstanding of legal requirements.

A closer examination of why the builder won these cases illustrates that defendants like IMPERIA STRUCTURES LIMITED often succeeded due to insufficient evidence presented by the complainants, legal non-compliance on the part of buyers, or a clear failure by the complainants to understand their contractual obligations. The builder's effective legal defenses highlight how misinterpretations of the law or contractual terms can lead to the unjust vilification of builders.

The analysis sheds light on the builder’s reputation within the broader real estate market. It reveals a reality where buyers, in some instances, may make unfounded accusations or fail to grasp the complexities involved in real estate transactions. This scenario underscores that builders like IMPERIA STRUCTURES LIMITED are not only capable of defending their positions but also in a strong position against unwarranted claims.

In conclusion, potential buyers should tread carefully and conduct thorough due diligence when engaging in real estate transactions. While legitimate disputes do arise, this analysis demonstrates that builders often have strong legal grounds to defend against unjust claims. Thus, it is vital for buyers to seek out reliable information and weigh the facts before forming opinions about a builder's reputation, ensuring informed decisions in their investment endeavors.

Withdrawal of Claims Complaints of Non-Registration Trial Dismissals Procedural Non-compliance

An analysis of the cases filed against the builder, IMPERIA STRUCTURES LIMITED, which the builder won, revealed the following information.

The cases can be broadly grouped into several themes, showcasing different kinds of disputes brought to court.

One prevalent theme is the frequent withdrawal of claims, where complainants chose to dismiss their complaints for various reasons, often indicating that the matters had been settled amicably between the parties.

Another common theme is related to complaints regarding non-registration of projects, which highlights issues of regulatory compliance that buyers often raise.

Finally, there are instances where procedural non-compliance and failures to follow legal processes led to dismissals of cases, as seen when parties neglected to properly include relevant parties in their claims.

These cases demonstrate that complaints against the builder typically stem from issues like project registration, delays in delivery, or disagreements on procedural matters.

A noteworthy pattern is the withdrawal of multiple cases, suggesting that some claims may have lacked sufficient grounding or that misunderstandings led to disputes that could be resolved without litigation.

Many of these complaints seem to arise from buyers’ frustrations or misconceptions rather than factual inaccuracies in the builder’s operations.

The reasons why IMPERIA STRUCTURES LIMITED successfully defended itself against these claims are significant.

Primarily, a recurring motif is the insufficiency of evidence submitted by opposing parties. In many instances, the buyers or complainants did not follow through with clear or documented claims, leading to dismissals primarily on procedural grounds.

Additionally, regulatory failures by the complainants themselves—like neglecting to include necessary parties in their filings—rendered their cases weaker.

This underscores the importance of adhering to legal processes and the consequences of failing to comply with proper legal standards.

The analysis further emphasizes the builder's reputation in the real estate market. It’s clear that while there are valid issues in real estate, buyers sometimes launch baseless accusations that can escalate into legal disputes.

IMPERIA STRUCTURES LIMITED has demonstrated a strong capacity to effectively challenge unjust claims, reflecting a robust operational integrity within the competitive landscape of the industry.

To potential buyers, this analysis serves as a critical reminder to approach claims against builders with caution and discernment.

While it is essential to be vigilant and informed about builder practices, understanding the broader context of legal disputes can prevent misguided perceptions and reinforce the importance of thorough investigation.

Ultimately, responsibly scrutinizing claims and seeking reliable information can help buyers make sound decisions in what can often be a complex and challenging real estate market.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
CR/3882/2021 Haryana Complaint received on 27.09.2021, settled between… ["Real Estate Dispu… {"appellant_claim(in detail)": "The complainant, … POONAM SHARMA IMPERIA STRUCTURES … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTgxMjg5
CR/1486/2019 Haryana Complaint dismissed for want of prosecution as th… Want of prosecution {"appellant_claim": "Not provided", "respondent_c… Sunil Kumar Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/Mjg1MTU=
1158/2018 Haryana Complaint filed by Poddar Infratech Pvt. Ltd. aga… ["Unregistered Proj… {"appellant_claim": "Booking of two units", "resp… Poddar Infratech Pr… Imperia Structures … https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/NjU3OQ==

Interested to buy from this builder?

Assured Callback in 5 mins