builder logo

NBCC INDIA LIMITED

  • No of Complaints: 8
  • States (Active in): Haryana, Kerala, Odisha
CIN Not Available
Year Established Not Available
Address Not Available
Company Status Not Available

Introduction

In the rapidly evolving landscape of real estate, potential buyers often seek not just the best locations but also reliable builders. NBCC INDIA Limited is a prominent builder with a project presence across states like Haryana, Odisha, and Kerala. This blog provides detailed insights into the builder's legal standings, cases filed against it, and essential tips for prospective buyers.

Legal Case Summary

NBCC INDIA Limited has faced a total of 8 complaints, resulting in 3 cases won and 5 cases lost. A closer look at these cases reveals trends that can be beneficial for potential buyers.

Cases Lost

Out of the 5 cases against NBCC that were lost:

  • Common Themes: Most of the cases that the builder lost involved the withdrawal of complaints either due to amicable settlements or a lack of detailed claims from the complainants. For instance:
    • Case Withdrawals: In three instances, complaints were either dismissed or withdrawn, highlighting a pattern of settlements reached outside of court. The lack of substantial contest from NBCC suggests that when matters escalate to legal conflicts, they may often be resolved through mutual agreement rather than a court's final say.
    • This indicates that while complaints can arise, the resolution often leans towards negotiated settlements.

Cases Won

In contrast, NBCC won 3 cases against the complaints filed:

  • Common Themes: The cases that were won typically revolved around the authority favoring NBCC, especially in rectification claims and disputes regarding financial returns. For example:
    • Successful Rectifications: Numerous cases involved the authority's agreement to correct financial discrepancies, showcasing that when the builder's packaged offers or pricing are contested, they have documented evidence supporting their claims.
    • Maintenance Compliance: In one instance, despite the initial allegations regarding maintenance and structural compliance, the final judgment favored NBCC, indicating their adherence to regulatory standards and plans approved by relevant authorities.
    • Refund Cases: Outcomes favorable to NBCC also appeared in cases where the complainants sought refunds, with judgments often enforcing returns with interest, thereby reflecting positive financial practices by NBCC.

Conclusion

Assessing the performance of NBCC INDIA Limited reveals a foundation of generally favorable dispute resolutions, although the occurrence of complaints signifies areas requiring attention. The builder's pattern suggests amicable resolutions are a pivotal process, while formal litigations often tilt favorably due to established regulatory compliance.

Tips for Potential Buyers

  1. Research Past Projects: Investigate completed projects and gather feedback from previous buyers about their experiences with NBCC.
  2. Understand Complaint Histories: Examine legal case histories available through public records to determine the nature and resolution of complaints.
  3. Seek Comprehensive Documentation: When considering purchasing, request full disclosures of legal standings, including their approach to resolving practical issues.
  4. Legal Support: If there are significant concerns, engage legal counsel to assess contracts before committing.

General Tips for Selecting Any Builder

  • Reputation Matters: View feedback on platforms dedicated to real estate reviews.
  • Project Viability: Ensure that the project under consideration is compliant with local regulations and sufficiently funded.
  • Engagement: Stay proactive in communication with the builder, and address concerns or requests for clarifications transparently.
  • Work with Professionals: Leverage real estate professionals for guidance through the buying process, ensuring legalities are handled efficiently.

Closing Thoughts

Choosing a builder like NBCC INDIA Limited involves careful consideration of past legal encounters and customer experiences. By being informed and diligent, prospective buyers can secure not just properties, but also peace of mind.

No builder reviews yet. Be the first to share your thoughts!

Rectification Claims Failure to Rectify Structural Defects Refund Claims with Interest Compliance with Approved Plans

Analysis of the cases filed against NBCC India Limited, where the builder lost, revealed several key themes across the complaints raised by the plaintiffs. The cases can be broadly categorized into rectification claims, failure to rectify structural defects, refund claims with interest, and compliance with approved plans.

The rectification claims primarily revolved around the builder's failure to accurately document the payments made by the complainants. In two significant cases, the builder had incorrectly noted the payment amount, leading the complainants to seek rectifications to reflect their actual payments. Since the builder did not contest these applications, the authority ruled in favor of the complainants, highlighting the importance of accurate record-keeping in real estate transactions.

Several cases also focused on the builder's alleged failure to rectify structural defects in the properties developed by them. Complainants claimed that besides not addressing these issues, the builder had also neglected to provide requisite maintenance services, which is critical for the longevity and safety of the construction. The builder's defense was to assert that they had indeed provided maintenance and rectified any flaws, yet the ruling went against them, indicating a shortfall in their assurances and actions taken.

Refund claims emerged as another significant theme, with various complainants seeking substantial refunds based on the builder’s inability to deliver promised services or rectify issues on their properties. These refunds were often coupled with claims for interest on the amounts paid, showcasing a degree of distrust in the builder's financial dealings and project timelines. The builder's responses in these cases typically involved offering refunds with interest, but the authorities often adjusted the interest rates upward, signaling a legal expectation for more equitable compensation.

Finally, the compliance with approved plans stands as a critical theme, with builders having a legal obligation to adhere to the plans that have received regulatory approval. Failure to do so can result in legal ramifications, as seen in these cases. The common thread among the complaints was the builders' inability to meet the standards and requirements set forth in the approved plans, which reflects a broader issue of regulatory compliance within the construction sector.

The patterns emerging from these summaries indicate that common triggers for litigation against NBCC India Limited include disputes over payment documentation, failure to address structural flaws, inadequate maintenance, and issues related to refunds and interest compensation. The builder's losses in these cases often stem from insufficient evidence to support their claims of adequate service delivery and compliance, highlighting the need for transparency and robust record-keeping practices.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
263 of 2022 Odisha The complainant, NBC Imperia Residents' Welfare A… ["Structural defect… {"appellant_claim": "The complainant alleged that… NBCC India Limited https://rera.odisha.gov.in/wp-content/uploads/2023/06/26-22.pdf
MA NO. 37/2024 in C… Haryana The complainant sought rectification of an earlie… ["Rectification of … {"appellant_claim(in detail)": "The complainant s… Jayprakash Mehta NBCC Limited https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTgwMTAw
Complaint Withdrawals Amicable Settlements Withdrawal of Claims

An analysis of the cases filed against the builder, NBCC India Limited, which the builder won, revealed the following information.

The cases can be grouped into a few common themes, with prominent examples including Complaint Withdrawals, where opposing parties decided to withdraw their complaints, often leading to dismissals.

Many instances reflected amicable settlements between parties, highlighting a tendency for disputes to be resolved outside the legal framework.

One specific case emphasized the withdrawal of a complaint after a resolution was reached between the parties involved.


Common reasons for these cases being brought to court appear to include disagreements where buyers and other parties raised complaints against the builder.

These complaints often involved claims regarding delays in project delivery or issues that may have stemmed from misunderstandings.

However, it is evident from the summaries that many cases were ultimately dismissed or withdrawn, indicating that disputes may not have been as substantial as initially perceived.


The builder, NBCC India Limited, was notably successful in defending itself in these instances, setting a precedent for its ability to counter claims effectively.

Many of these cases were dismissed due to insufficient evidence presented by the opposing parties, or they simply failed to adhere to legal or regulatory requirements, leading to a withdrawal of claims.

In some instances, the plaintiffs did not have a solid grounding for their accusations, resulting in the complaints being withdrawn voluntarily once a clearer picture emerged.


This analysis sheds light on the builder’s reputation amidst the broader real estate market, wherein it's not uncommon for buyers to make claims that may stem from misunderstandings or lack of information.

Typically, buyers can sometimes feel wronged, leading to accusations that may not hold up under legal scrutiny.

In the cases against NBCC India Limited, the builder's consistent ability to withstand claims showcases a strong defense mechanism against potentially unjust accusations.


For potential buyers, the clear takeaway is the immense importance of making informed decisions when navigating the real estate market.

While genuine disputes do exist, the experiences drawn from these cases suggest that reputable builders, like NBCC India Limited, can often rise to the occasion and defend their reputation against unwarranted claims.

Buyers are encouraged to approach such allegations cautiously, seeking comprehensive and reliable information before forming any opinions about a builder's credibility.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
CR/679/2023 Haryana Complaint withdrawn by the complainant as the mat… ["Withdrawal of com… {"appellant_claim(in detail)": "The complainant h… Rajender NBCC India Limited https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTczMjU3
CR/675/2023 Haryana Abhay Kumar Jain vs NBCC India Limited: Complaint… ["Real Estate Dispu… {"appellant_claim(in detail)": "Not provided", "r… Abhay Kumar Jain NBCC India Limited https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTczMjU2
CR/6860/2022 Haryana Sumita Gandhi vs NBCC Limited: Complaint withdraw… ["Complaint withdra… {"appellant_claim(in detail)": "Not provided", "r… Sumita Gandhi NBCC Limited https://haryanarera.gov.in/assistancecontrol/viewOrderPdf/MTc5OTk4

Interested to buy from this builder?