CIN | U70200MH2007PTC175594 |
---|---|
Year Established | Not Available |
Address | 127 SHRIKANT CHAMBERS 1 ST FLOOR, V N PURAV MARG, NEAR R K STUDIO CHEMBUR MUMBAI-400071 MUMBAI Mumbai City MH 400071 IN |
Company Status | Private |
Overall Case Outcomes
In the complex world of real estate, buyers often seek out reputable builders to invest their hard-earned money into properties that promise to deliver value and satisfaction. One such builder, Samira Realty Projects Private Limited, has left a notable footprint in the state of Maharashtra. However, a closer examination of their legal performance reveals some concerning trends.
Samira Realty Projects Private Limited has faced six complaints in total, and troublingly, they have not won any of these cases. Instead, the builder has lost all six, hinting at a pattern that potential buyers should consider.
Interestingly, while the builder lost all cases, there were instances whereby appeals were allowed with conditions focused on procedural aspects rather than substantive victories. This suggests that while technically, they have seen decisions in their favor concerning case procedures, it does not reflect positively on their overall capability to deliver projects as promised.
Given the disconcerting track record of Samira Realty Projects Private Limited, potential buyers might find it challenging to develop trust in this builder. The absence of successful resolutions in prior disputes raises alarms about their operational integrity and customer service.
In summary, while Samira Realty Projects Private Limited displays operational capabilities in a specific sector, potential buyers are encouraged to tread cautiously and take appropriate measures to safeguard their investments.
Yearly Trend for these Cases
Analysis of the cases filed against Samira Realty Projects Private Limited, where the builder lost, revealed several key themes and patterns. The cases primarily revolved around three common topics: delayed possession claims, condonation of delay in filing appeals, and refund and interest disputes.
The majority of the cases involved claims of delayed possession, where the appellants asserted that the builder had failed to deliver properties within the agreed timelines. For instance, in one case, the appellant sought a refund of ₹60,00,000 along with interest due to the builder's inability to complete the project on schedule. The builder's defense often revolved around their contention that they had completed significant portions of the projects, leaving only interior work pending. However, the tribunal did not accept this defense and partly allowed the appeal, indicating a degree of disfavor towards the builder's justifications.
Another recurring theme was the issue of condonation of delay in filing appeals. In multiple cases, the appellants cited the Supreme Court's order in Sou Motu Writ Petition (Civil) No.3 of 2020 as grounds for extending the limitation period for their appeals. The builder, on the other hand, argued that the appellants had failed to provide adequate reasons for the delay. The tribunal consistently ruled in favor of the appellants, condoning the delays based on the Supreme Court's order. This highlights a pattern where the builder's attempts to discredit the timeliness of the appeals were unsuccessful.
The common triggers for litigation in these cases primarily revolved around the builder's failure to meet project timelines and fulfill their contractual obligations. The appellants often sought refunds and interest on their investments due to the delays. The builder's losses in these cases underline the importance of adhering to timelines and clear communication in real estate transactions.
The builder's losses can be attributed to several factors, including insufficient evidence to support their claims of timely project completion and a lack of compliance with the expectations set during the purchase agreements. The consistent failure to convince the tribunal of their positions indicates a systemic issue within their operational practices, possibly related to project management or customer service. It also highlights the need for buyers to be vigilant and informed about their rights when engaging with builders.
No reviews for this builder yet. Be the first one to share your thoughts!