Overall Case Outcomes
Samyak Infrastrastra Private Limited is a builder operating in Madhya Pradesh (MP), with a recent history marked by legal challenges. In this post, we explore the legal cases associated with the company, analyze patterns in their disputes, and provide guidance for prospective buyers looking to invest in their projects.
Samyak Infrastrastra Private Limited has faced a total of 2 complaints, both of which resulted in losses for the builder. Each case centered around demands for refunds and compensation due to delays in possession of flats. Interestingly, these cases demonstrate a common theme and outcome, which we will discuss in detail later.
Based on the provided data, Samyak Infrastrastra Private Limited exhibits a troubling pattern concerning project delivery and customer satisfaction, as highlighted by the two lost cases. The builder has faced complaints about significant delays and ultimately has not successfully defended against claims for compensation.
In summary, while Samyak Infrastrastra Private Limited has active projects, potential buyers should exercise caution based on their track record with complaints and legal challenges surrounding project delays.
Yearly Trend for these Cases
Analysis of the cases filed against Samyak Infrastrastra Private Limited, where the builder lost, revealed several key themes and patterns. The cases primarily revolved around two main topics: delayed possession claims and refund/compensation disputes.
The delayed possession claims involved applicants seeking refunds due to significant delays in the delivery of their flats. In each case, the builder denied the allegations, claiming that the entire amount had been refunded to the applicants. However, the authority ruled in favor of the applicants, directing the builder to give 50% of the profit to the applicants when the property is sold. This highlights a consistent issue with transparency and adequate communication regarding project timelines and financial settlements.
The common trigger for these legal disputes appears to be the builder's inability to meet project deadlines, which led applicants to contest the delays and seek refunds and compensation. The builder's repeated denial of allegations suggests a defensive posture that may indicate a lack of accountability for project delays.
The reasons for the builder's losses in these cases seem to stem from a combination of factors. The builder's claims of having refunded the amounts in full were not validated, leading to the authority's decision to award profits to the applicants. This may suggest insufficient evidence on the part of the builder to support their claims or potential non-compliance with regulatory requirements governing real estate transactions.
Overall, these cases underline the importance of vigilant oversight and clear communication in real estate projects. Buyers should be wary of builders with a history of such disputes and conduct thorough research before committing to a purchase.