When navigating the real estate landscape, selecting a builder with a solid reputation is vital. In this post, we will examine Saraf Project Private Limited, a builder operational in Haryana. With data reflecting their track record and legal challenges, we will provide insights to help potential buyers make informed decisions.
Saraf Project Private Limited has come under scrutiny with a total of 1 recorded complaint. The legal case details indicate that the project involved a dispute over a commercial unit payment and the promised delivery of the property.
Based on the provided data, Saraf Project Private Limited has faced setbacks in legal standing, notably losing a case where the authority ruled in favor of the buyer. The lack of won cases raises concerns about the builder's reliability and fulfillment of contractual obligations.
When choosing a builder, like Saraf Project Private Limited, it is crucial to remain vigilant. Armed with knowledge of the builder’s legal outcomes and practices, buyers can better safeguard their investments and make choices aligned with their interests.
Yearly Trend for these Cases
Analysis of the cases filed against Saraf Project Private Limited, where the builder lost, reveals several key themes and key issues in their legal disputes.
The cases against Saraf Project Private Limited primarily revolve around three critical themes: Delayed Possession Claims, Disputes over Project Completion, and Refund and Interest Claims.
The most prominent theme among these is the Delayed Possession Claims. In these cases, buyers claim that although they made substantial payments towards their respective units, the builder failed to complete the project and hand over possession as promised. An example of this is the claim made by a complainant who paid a total of Rs. 26,01,250/- for a commercial unit in an unregistered project. Despite the builder's contention that possession was delivered in 2008 and 2009, the Authority determined that the project was incomplete and that possession had not been granted, leading to a refund of the payment along with interest.
Disputes over Project Completion often overlap with delayed possession claims, as buyers frequently argue that the builder did not fulfill their commitments. In the case summarized, the builder's assertion that the complainant paid significantly less than what was claimed (Rs. 7,68,750/- versus Rs. 26,01,250/-) indicates a substantial communication gap or potential mismanagement of payments and expectations.
Refund and Interest Claims naturally arise from the first two themes, as buyers seek recoupment for amounts paid when projects are not completed or possession is not granted. The Authority's decision to grant refunds along with interest in the case highlights the legal expectation that builders must meet their obligations and that non-compliance can result in significant financial repercussions.
Common reasons for the litigation in these cases include:
The builder lost these cases primarily due to:
In conclusion, the cases against Saraf Project Private Limited underline the importance of transparency, effective communication, and adherence to legal standards in real estate transactions. Buyers should remain vigilant and informed about their rights and the statuses of their investments.