Overall Case Outcomes
When it comes to selecting a builder for your next home, it's crucial to thoroughly research their track record. In this post, we delve into the case of Shri Krishna Empowerment, a builder operating in Madhya Pradesh. With a concerning number of complaints and a lack of favorable outcomes in legal disputes, potential buyers should take caution when considering this builder.
Shri Krishna Empowerment has faced a total of 4 complaints from customers, with no victories in any related legal cases. Each of the cases resulted in losses for the builder, painting a picture of a troubling pattern. Given the legal landscape surrounding this builder, it is vital for prospective customers to be well-informed before proceeding with any agreements.
While there are no cases where the builder has won, it is important to present the details leading to their losses, as these cases imply a consistent trend of unfavorable outcomes. In every case, the decision favored the applicant due to failures attributed to the builder.
Based on the provided data, Shri Krishna Empowerment appears to be a potentially risky choice for homebuyers in Madhya Pradesh. With no wins against 4 lost cases, there is a clear indication of dissatisfaction among clients and failures within the company concerning project completion and customer service.
In conclusion, it is essential for prospective homebuyers to approach Shri Krishna Empowerment with caution and to consider the outlined risks associated with this builder.
Yearly Trend for these Cases
Analysis of the cases filed against Shri Krishna Empowerment, where the builder lost, reveals several key themes across the complaints raised by the applicants. The primary disputes can be categorized into three main topics: Delayed Possession Claims, Disputes over Payment and Completion, and Compensation for Mental Distress and Delays.
The cases often revolved around the builder's failure to initiate or complete construction work on flats after receiving payments from the applicants. This led to multiple claims primarily classified as Delayed Possession Claims. Applicants sought compensation and interest for the delays, arguing that they had made substantial payments for flats that were supposed to be completed within a reasonable timeframe. For instance, in one case, the applicant paid Rs. 84,000, and in another, Rs. 3,42,000, yet the builder did not fulfill their commitments.
Disputes over Payment and Completion emerged as another significant theme. In these cases, the builder contested the claims by stating that applicants had not paid the full amount due. However, the adjudicating officer consistently ruled in favor of the applicants, indicating a failure on the builder's part to provide credible evidence of incomplete payments or to justify the delays in construction.
The builders were also held accountable for causing mental distress to the applicants due to their inability to deliver properties on time. Compensation for Mental Distress and Delays was a common verdict, with courts recognizing the emotional and psychological ramifications that buyers face when contracts are not honored.
A pattern emerges from these summaries: the builder’s litigation often stemmed from a combination of factors, including insufficient evidence to support their claims, a lack of compliance with payment agreements, and a failure to meet project timelines. The consistent ruling against the builder suggests systemic issues within their operational practices, resulting in repeated failures to fulfill contractual obligations and meet buyer expectations.