In today’s fast-paced real estate market, choosing the right builder is paramount. One such builder, Trehan Apna Ghar Private Limited, primarily operates in Rajasthan. However, with a number of complaints and legal cases reported against them, it is crucial to examine their track record of performance in light of these complaints. This blog post analyzes the builder’s legal case history and provides insights to potential buyers considering investing in properties by this builder.
Trehan Apna Ghar has faced a total of 13 complaints, resulting in 5 cases won and 8 cases lost. This situation suggests a significant degree of contention surrounding their business practices, particularly concerning property possession and compliance issues.
The 8 cases that the builder lost reveal several notable patterns:
In contrast, the 5 cases that the builder won showcased their ability to defend against several claims:
Overall, the data suggests that Trehan Apna Ghar Private Limited has faced a challenging legal landscape but has also demonstrated a capacity to defend against several claims effectively. While buyers should be wary of the builder’s history of complaints and losses, successful defenses indicate that they do maintain a degree of legal compliance within the industry norms.
In summary, potential buyers should weigh the builder's strengths and weaknesses carefully, armed with the insight from their legal history prior to making a purchase decision.
No builder reviews yet. Be the first to share your thoughts!
Here you’ll find cases where others sued the builder, and the builder lost. We’ve included a simple summary and key takeaways from each case.
Analysis of the cases filed against Trehan Apna Ghar Private Limited, where the builder lost, reveals several key themes and patterns. The cases primarily revolve around delayed possession claims, with multiple complainants seeking compensation for the late delivery of flats.
The most common theme among the cases is the claim for compensation due to delays attributed to various reasons, such as the need for completion certificates and the impact of the COVID-19 pandemic. The builder consistently cited unforeseen circumstances as a defense; however, this did not stand in court as sufficient justification for the delays. Consequently, the adjudicating officers directed the builder to pay compensation, which typically included amounts for the delay itself, mental agony, and litigation costs.
Another significant theme is the claim for interest on the delayed delivery of possession. Complainants often sought interest at specific rates, and the authority usually ruled in their favor, indicating a legal obligation on the builder to compensate for the prolonged duration in which buyers were unable to receive their properties.
The reasons people brought cases to court primarily revolved around contesting delays and seeking rightful compensation for their emotional distress and financial burdens, such as interest on loans while waiting to receive their flats. A pattern emerges where the builder’s reliance on claims of unforeseen circumstances was not sufficient to alleviate their responsibility for timely delivery and adequate communication with buyers.
The common reasons for the builder’s losses in these cases were rooted in their inability to meet project timelines and fulfill their commitments. The consistent failure to provide possession on time, despite buyer expectations and contractual agreements, led to the legal obligations to compensate buyers for delays and emotional distress. The builder's defense of unforeseen circumstances suggests a lack of proper planning or risk management, which is critical in the construction industry.
This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.
Case Number | State | Summary | Case Topic | Detailed Summary | Appellant Name | Respondent Name | Source |
---|---|---|---|---|---|---|---|
RAJ-RERA-C-N-2022-5… | Rajasthan | Complainant sought refund for delayed delivery of… | ["Delayed delivery"… | {"appellant_claim": "Refund for delayed delivery … | Devendra Kumar | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/22302022-5159.pdf |
RAJRERA-C-2022-5271 | Rajasthan | The complainants, Pramod Kumar Tanwar and Neetu T… | ["Delay in possessi… | {"appellant_claim": "The complainants claimed tha… | Neetu Tanwar | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/52912022-5271.pdf |
RAJ RERA-C-2022-5281 | Rajasthan | Complainant sought compensation for delay in poss… | ["Delay in possessi… | {"appellant_claim": "Complainant claimed compensa… | Munish Ranjan Sahay | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/20652022-5281.pdf |
RAJRERA-C-N-2023-60… | Rajasthan | Complainants sought interest for delayed delivery… | ["Delayed Possessio… | {"appellant_claim": "Complainants claimed interes… | Others | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/68182023-6023.pdf |
RAJ-RERA-C-2023-6028 | Rajasthan | The complainant, Narain Singh, filed a complaint … | ["Delayed possessio… | {"appellant_claim": "The complainant claimed comp… | Narain Singh | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/17762023-6028 Narain Singh Vs. Trehan Apna Ghar Pvt. Ltd..pdf |
Here you’ll find cases where others sued the builder, but the builder won. We’ve included a summary and key insights from each case.
An analysis of the cases filed against the builder, Trehan Apna Ghar Private Limited, which the builder won, revealed the following information. The cases can be grouped under four primary themes: Delayed Possession Claims, Withdrawal of Complaints, Insufficient Deposits and Non-binding Agreements, and Case Dismissals for Lack of Prosecution. Each theme highlights different aspects of disputes arising between buyers and the builder.
Common reasons for bringing these cases to court include accusations of undue delays, disputes over contractual obligations, and requests for refunds. Patterns observed in these summaries point to misunderstandings of agreements and contractual commitments by buyers and highlight that the builder maintained consistent legal defenses focused on addressing these deficiencies.
In summary, Trehan Apna Ghar Private Limited showcased strong defense strategies that often underlined the failures of the complainants to provide adequate evidence or establish solid grounds for their claims. The builder's ability to navigate these disputes successfully indicates a level of diligence, as they largely pivoted on regulatory compliance and contractual adherence among buyers.
This analysis reflects an overarching insight about the builder’s reputation within the broader real estate market. It suggests that while legitimate disputes exist, wishful thinking or misunderstandings can lead to accusations that lack foundation. Trehan Apna Ghar Private Limited demonstrated resilience and competence in defending against exaggerated claims, reinforcing a notion that buyers must be cautious and well-informed.
To potential buyers: it’s crucial to approach claims and allegations carefully. Ensure to gather reliable information before making decisions or forming opinions about a builder’s credibility. While disputes are an inherent part of real estate transactions, discerning fact from overreaction can assist in safeguarding your investments.
This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.
Case Number | State | Summary | Case Topic | Detailed Summary | Appellant Name | Respondent Name | Source |
---|---|---|---|---|---|---|---|
RAJRERA-C-2020-3600 | Rajasthan | Complaint withdrawn by the complainant. Case dism… | ["Complaint withdra… | {"appellant_claim(in detail)": "The complainant f… | Ritu Sharma | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/5202Order 2020-3600.pdf |
F. 3(277)RJIRERAIPI… | Rajasthan | The real estate project registered with the Autho… | ["Real estate proje… | {"appellant_claim": "", "respondent_claim": "The … | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/9064F.3(277).pdf | |
RAJ-RERA-C-N-2022-4… | Rajasthan | Complainant claimed refund for not executing agre… | ["Refund for not ex… | {"appellant_claim(in detail)": "Complainant claim… | Manish Khurana | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/47062022-4894.pdf |
RAJ RERA-C-2020-4008 | Rajasthan | The complaint was dismissed for want of prosecuti… | ["Want of prosecuti… | {"appellant_claim": "Not provided", "respondent_c… | Satya Dey Sharma | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/61972020-4008.pdf |
RAJ RERA-C-2020-4006 | Rajasthan | Complainant sought refund for delayed possession … | ["Delayed Possessio… | {"appellant_claim": "Complainant claimed that res… | Satya Dev Sharma | Trehan Apna Ghar Pr… | https://rera.rajasthan.gov.in/Content/pdf/12162020-4006.pdf |