Sh-Ra)-7-0646
Sh-Ra)-7-0646
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Rajesh Bahl, filed a complain…
The applicant, Shri Rajesh Bahl, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work and not registering the plot. The Authority found that the non-applicant had not completed the development work and had not registered the plot, and the applicant was entitled to compensation.
|
["Non-completion of…
["Non-completion of development work", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant had not completed the development work and had not registered the plot, and sought compensation.", "respondent_claim": "The non-applicant claimed that they had done partial development work and that the applicant had not paid the full amount as per the contract.", "final_verdict": "The Authority found that the non-applicant had not completed the development work and had not registered the plot, and the applicant was entitled to compensation.", "in_favor_of_respondent": "no"}
|
Shri Rajesh Bahl
Shri Rajesh Bahl
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/572720712599.pdf
|
5-II 40-9-4504
5-II 40-9-4504
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Jairam Patidar, sought posses…
The applicant, Shri Jairam Patidar, sought possession of a plot in the 'Shiv Residency-2' project developed by Vatsalya Builders & Developers Pvt. Ltd. The Authority accepted the application after scrutiny and instructed the developer to complete the project within two months and hand over possession to the applicant.
|
["Possession of plo…
["Possession of plot", "Developer's obligations"]
|
{"appellant_claim": "The applicant sought possess…
{"appellant_claim": "The applicant sought possession of a plot in the 'Shiv Residency-2' project developed by Vatsalya Builders & Developers Pvt. Ltd.", "respondent_claim": "The developer claimed that the applicant had not entered into a contract with them and had not paid the full amount due.", "final_verdict": "The Authority accepted the application after scrutiny and instructed the developer to complete the project within two months and hand over possession to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Jairam Patidar
Shri Jairam Patidar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/779071910151.pdf
|
40-20-0908-00
40-20-0908-00
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of the amount paid fo…
The applicant sought refund of the amount paid for a plot in the Shiv Residency Phase-2 project, along with interest, due to non-development of the project and non-registration with the Authority. The Authority ordered the non-applicants to return the amount with interest.
|
["Refund of amount …
["Refund of amount paid for undelivered real estate project"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of the amount paid for the plot, along with interest, due to non-development of the project and non-registration with the Authority.", "respondent_claim": "The respondents did not appear before the Authority despite being served a notice.", "final_verdict": "The Authority ordered the respondents to return the amount paid by the applicant, along with interest at the rate of 46.75% per annum from the date of payment till the date of repayment.", "in_favor_of_respondent": "no"}
|
Shri Sudesh Gupta
Shri Sudesh Gupta
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/612522571155.pdf
|
7-60-21-0086
7-60-21-0086
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Ruparam Mukati, filed a compl…
The applicant, Shri Ruparam Mukati, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not handing over possession of a residential plot and not executing the sale deed despite receiving payment. The M.P. Real Estate Regulatory Authority ordered the non-applicant to pay the applicant Rs. 9,72,200/- with interest and also ordered the applicant to pay Rs. 5000/- to the non-applicant.
|
["Non-delivery of p…
["Non-delivery of possession", "Non-execution of sale deed"]
|
{"appellant_claim": "The applicant claimed that h…
{"appellant_claim": "The applicant claimed that he had paid Rs. 9,72,200/- to the non-applicant for a residential plot, but the non-applicant had not handed over possession of the plot and had not executed the sale deed.", "respondent_claim": "The non-applicant did not file any reply or affidavit, and did not present any arguments.", "final_verdict": "The M.P. Real Estate Regulatory Authority ordered the non-applicant to pay the applicant Rs. 9,72,200/- with interest, and also ordered the applicant to pay Rs. 5000/- to the non-applicant.", "in_favor_of_respondent": "no"}
|
Shri Ruparam Mukati
Shri Ruparam Mukati
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/635854638886.pdf
|
4-2 400-49-0747
4-2 400-49-0747
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not completing the development work and not granting possession of the plot despite receiving the full consideration amount. The Adjudicating Officer passed an order directing the non-applicant to pay the principal amount with interest and compensation to the applicant.
|
["Non-completion of…
["Non-completion of development work", "Non-grant of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not grant possession of the plot despite receiving the full consideration amount.", "respondent_claim": "The non-applicant did not file any response or appear before the Adjudicating Officer.", "final_verdict": "The Adjudicating Officer directed the non-applicant to pay the principal amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Prabhat Kumar
Shri Prabhat Kumar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/117212128003.pdf
|
5-Bhat74-49073
5-Bhat74-49073
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicants for not carrying out development work of the plot and not returning the amount paid. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicants to pay the amount with interest.
|
["Non-payment of de…
["Non-payment of development charges", "Non-return of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not carry out development work of the plot and did not return the amount paid.", "respondent_claim": "The non-applicants did not file any response or defense.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicants to pay the amount with interest.", "in_favor_of_respondent": "no"}
|
Smt. Poonam Chauhan
Smt. Poonam Chauhan
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/251958937138.pdf
|
4-.40-49-0462
4-.40-49-0462
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for delay in possession of a residential plot and non-return of the amount paid. The Adjudicating Officer ordered the non-applicant to pay the amount with interest and compensation.
|
["Delay in possessi…
["Delay in possession", "Non-return of amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed possession of the residential plot and did not return the amount paid.", "respondent_claim": "The non-applicant claimed that the delay was due to unforeseen circumstances and that the amount paid was not refundable.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Arvind Kulkarni
Shri Arvind Kulkarni
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/367933191933.pdf
|
4-.40-49-0447
4-.40-49-0447
|
Madhya Pradesh
Madhya Pradesh
|
The applicant complained about the non-applicant'…
The applicant complained about the non-applicant's failure to deliver possession of a residential plot and sought compensation for the delay. The adjudicating officer ordered the non-applicant to pay the principal amount with interest and compensation for mental distress and other expenses.
|
["Delay in possessi…
["Delay in possession", "Compensation for mental distress"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant failed to deliver possession of the residential plot within the stipulated period and sought compensation for the delay.", "respondent_claim": "The non-applicant did not respond to the complaint.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the principal amount with interest and compensation for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Shri Dinesh Chandra…
Shri Dinesh Chandra Pandey
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/104410000166.pdf
|
4-240-49-0460
4-240-49-0460
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not completing the development work and not handing over the possession of the plot. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount with interest and compensation.
|
["Non-delivery of p…
["Non-delivery of possession", "Non-completion of development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not hand over the possession of the plot despite receiving the full payment.", "respondent_claim": "The non-applicant did not file any response or defense.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Jiwan Singh Bh…
Shri Jiwan Singh Bhati
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/463626744004.pdf
|
H |4-240-49-0429
H |4-240-49-0429
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not completing the development work and not granting possession of the plot. The Adjudicating Officer ordered the non-applicant to pay the principal amount, interest, and compensation to the applicant.
|
["Non-completion of…
["Non-completion of development work", "Non-granting of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not grant possession of the plot despite receiving the full payment.", "respondent_claim": "The non-applicant claimed that the delay in completion of the development work was due to unforeseen circumstances.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the principal amount, interest, and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Ajay Kothari
Shri Ajay Kothari
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/081106126103.pdf
|
4-II 40-49-4254
4-II 40-49-4254
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a plot of land despite receiving the consideration amount. The Adjudicating Officer ordered the non-applicant to pay the consideration amount with interest and compensation to the applicant.
|
["Non-grant of poss…
["Non-grant of possession", "Interest and compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the plot of land despite receiving the consideration amount.", "respondent_claim": "The non-applicant did not file any response.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the consideration amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Rajendra Patid…
Shri Rajendra Patidar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/100618142681.pdf
|
H |4-.40-49-0428
H |4-.40-49-0428
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not completing the development work and not granting possession of the plot. The Adjudicating Officer ordered the non-applicant to pay the principal amount with interest and compensation to the applicant.
|
["Non-completion of…
["Non-completion of development work", "Non-granting of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not grant possession of the plot despite receiving the full payment.", "respondent_claim": "The non-applicant claimed that the delay in completion of development work was due to unforeseen circumstances.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the principal amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Jitendra Kotha…
Shri Jitendra Kothari
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/181889779389.pdf
|
4-240-49-4249
4-240-49-4249
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for delay in possession of a residential plot and non-execution of development work. The Adjudicating Officer ordered the non-applicant to pay the applicant Rs. 40,35,000 with interest at 7% p.a. and compensation for mental distress and other expenses.
|
["Delay in possessi…
["Delay in possession", "Non-execution of development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed possession of the residential plot and did not execute development work as per the contract.", "respondent_claim": "The non-applicant did not file any response or defense.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the applicant Rs. 40,35,000 with interest at 7% p.a. and compensation for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Shri Ajay Patidar
Shri Ajay Patidar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/163404663155.pdf
|
4-II 400-49-0850
4-II 400-49-0850
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for delay in possession of a residential plot and non-execution of development work. The Adjudicating Officer ordered the non-applicant to pay the applicant Rs. 6,24,200 with interest at the rate of 7% p.a. and compensation for mental distress and other expenses.
|
["Delay in possessi…
["Delay in possession", "Non-execution of development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed possession of the residential plot and did not execute development work as per the agreement.", "respondent_claim": "The non-applicant did not file any response or defense.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the applicant Rs. 6,24,200 with interest at the rate of 7% p.a. and compensation for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Shri Deepanshu Johri
Shri Deepanshu Johri
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/181353359999.pdf
|
4-240-49-0075
4-240-49-0075
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a residential plot within the stipulated period. The Adjudicating Officer passed an order directing the non-applicant to pay the applicant Rs. 43,33,700 and interest at the rate of 7% p.a.
|
["Non-grant of poss…
["Non-grant of possession", "Interest payment"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the residential plot within the stipulated period of 24 months and sought compensation and interest.", "respondent_claim": "The non-applicant claimed that the delay in granting possession was due to unforeseen circumstances and sought to be exempt from paying compensation and interest.", "final_verdict": "The Adjudicating Officer directed the non-applicant to pay the applicant Rs. 43,33,700 and interest at the rate of 7% p.a.", "in_favor_of_respondent": "no"}
|
Shri A.K. Sharma
Shri A.K. Sharma
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/494461610446.pdf
|
4-42 44-49--4432
4-42 44-49--4432
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a residential plot and seeking compensation. The authority ordered the non-applicant to pay the applicant Rs. 5,58,450 with interest at the rate of 7% p.a. and Rs. 20,000 as compensation for mental distress.
|
["Non-grant of poss…
["Non-grant of possession", "Compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the residential plot within the stipulated period and sought compensation for mental distress and litigation expenses.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the full amount due and sought clarification on the interest rate.", "final_verdict": "The authority ordered the non-applicant to pay the applicant Rs. 5,58,450 with interest at the rate of 7% p.a. and Rs. 20,000 as compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Argav Khare
Shri Argav Khare
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/286225883156.pdf
|
4--0#-49-4320
4--0#-49-4320
|
Madhya Pradesh
Madhya Pradesh
|
The applicants filed a complaint against the non-…
The applicants filed a complaint against the non-applicants for not granting possession of a residential plot within the stipulated period and for not doing development work within the stipulated period. The Adjudicating Officer passed an order in favor of the applicants, directing the non-applicants to pay the amount paid by the applicants with interest and compensation.
|
["Non-grant of poss…
["Non-grant of possession", "Non-development work"]
|
{"appellant_claim": "The applicants claimed that …
{"appellant_claim": "The applicants claimed that the non-applicants did not grant possession of the residential plot within the stipulated period and did not do development work within the stipulated period.", "respondent_claim": "The non-applicants claimed that the applicants had not paid the amount due to them and had not complied with the terms of the contract.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicants, directing the non-applicants to pay the amount paid by the applicants with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Bhupendra Shri…
Shri Bhupendra Shringi
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/263610132121.pdf
|
4-42 44-19-0647
4-42 44-19-0647
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for delay in possession of a residential plot and non-execution of the sale deed. The authority ordered the non-applicant to refund the amount paid by the applicant with interest and compensation.
|
["Delay in possessi…
["Delay in possession", "Non-execution of sale deed"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed possession of the residential plot and did not execute the sale deed despite receiving the full payment.", "respondent_claim": "The non-applicant did not file any response or defense.", "final_verdict": "The authority ordered the non-applicant to refund the amount paid by the applicant with interest at the rate of 7% per annum and compensation of Rs. 20,000 for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Shyam Kumar Me…
Shri Shyam Kumar Mehra
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/128616666624.pdf
|
4-.40-49-4287
4-.40-49-4287
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a plot and not refunding the amount paid. The authority ordered the non-applicant to pay the amount with interest and compensation.
|
["Non-grant of poss…
["Non-grant of possession", "Non-refund of amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the plot and did not refund the amount paid despite several requests.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the remaining amount due and that the possession of the plot was not granted due to unforeseen circumstances.", "final_verdict": "The authority ordered the non-applicant to pay the amount with interest at the rate of 7% per annum and compensation of Rs. 20,000 for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Shri Prakhar Jain
Shri Prakhar Jain
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/621722626227.pdf
|
44-19-0854
44-19-0854
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a residential plot and seeking compensation. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the amount with interest and compensation.
|
["Non-grant of poss…
["Non-grant of possession", "Compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the residential plot within the stipulated period and sought compensation for the same.", "respondent_claim": "The non-applicant did not file any response or defense to the applicant's claim.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Raoji Sukhdev …
Shri Raoji Sukhdev Shinde
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/378273317931.pdf
|
4-42 44-49-0833
4-42 44-49-0833
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought possession of a plot and com…
The applicant sought possession of a plot and compensation from the non-applicants for delay in development work. The Adjudicating Officer ordered the non-applicants to pay the applicant Rs. 5,00,000 with interest at 7% p.a. and Rs. 20,000 as compensation.
|
["Delay in developm…
["Delay in development work", "Compensation for mental distress"]
|
{"appellant_claim": "The applicant sought possess…
{"appellant_claim": "The applicant sought possession of a plot and compensation from the non-applicants for delay in development work.", "respondent_claim": "The non-applicants did not provide any response or explanation.", "final_verdict": "The Adjudicating Officer ordered the non-applicants to pay the applicant Rs. 5,00,000 with interest at 7% p.a. and Rs. 20,000 as compensation.", "in_favor_of_respondent": "no"}
|
Smt. Jayashree Devi
Smt. Jayashree Devi
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/761281423178.pdf
|
44-19-0648
44-19-0648
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 3,89,000 to the non-applic…
The applicant paid Rs. 3,89,000 to the non-applicant for a residential plot, but the non-applicant failed to deliver possession and the sale deed. The applicant sought refund of the amount with interest and compensation for mental harassment and litigation expenses.
|
["Refund of amount"…
["Refund of amount", "Interest", "Compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant failed to deliver possession and the sale deed for the residential plot, and sought refund of the amount with interest and compensation for mental harassment and litigation expenses.", "respondent_claim": "The non-applicant did not respond to the complaint and was absent in the proceedings.", "final_verdict": "The adjudicating officer ordered the non-applicant to refund the amount of Rs. 3,89,000 with interest at the rate of 7% per annum, and compensation of Rs. 20,000 for mental distress. The applicant was also awarded a refund of the application fee of Rs. 2,000.", "in_favor_of_respondent": "no"}
|
Shri Shyam Kumar Me…
Shri Shyam Kumar Mehra
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/616707636263.pdf
|
4-II 40-49--4484
4-II 40-49--4484
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 4,32,400 with …
The applicant sought refund of Rs. 4,32,400 with 44% interest and compensation for mental harassment and delay in possession. The authority ordered payment of Rs. 4,32,400 with 7% interest and compensation of Rs. 20,000 for mental distress.
|
["Refund", "Compens…
["Refund", "Compensation", "Possession"]
|
{"appellant_claim": "The applicant sought refund …
{"appellant_claim": "The applicant sought refund of Rs. 4,32,400 with 44% interest and compensation for mental harassment and delay in possession.", "respondent_claim": "The respondent did not provide any claim.", "final_verdict": "The authority ordered payment of Rs. 4,32,400 with 7% interest and compensation of Rs. 20,000 for mental distress.", "in_favor_of_respondent": "no"}
|
Smt. Nidhi Rajput
Smt. Nidhi Rajput
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/268282226667.pdf
|
44-4 44-19-0853
44-4 44-19-0853
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 9,72,000 to the non-applic…
The applicant paid Rs. 9,72,000 to the non-applicant for a plot in the Shiv Residency-II project. The non-applicant did not deliver the plot as per the agreement, and the applicant sought compensation and interest.
|
["Non-delivery of p…
["Non-delivery of plot", "Compensation and interest"]
|
{"appellant_claim": "The applicant paid Rs. 9,72,…
{"appellant_claim": "The applicant paid Rs. 9,72,000 to the non-applicant for a plot in the Shiv Residency-II project. The non-applicant did not deliver the plot as per the agreement, and the applicant sought compensation and interest.", "respondent_claim": "The non-applicant did not provide any response or explanation for the non-delivery of the plot.", "final_verdict": "The applicant is entitled to receive Rs. 9,72,000 with interest at the rate of 7% p.a. from the date of receipt of the amount. The applicant is also entitled to compensation of Rs. 20,000 for mental distress. The non-applicant is required to pay Rs. 2,000 as application fee paid by the applicants in RERA.", "in_favor_of_respondent": "no"}
|
Shri Mangesh Bidkar
Shri Mangesh Bidkar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/772766121971.pdf
|
4-42 44-19-0646
4-42 44-19-0646
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a plot and not returning the consideration amount. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the consideration amount with interest and compensation.
|
["Non-payment of co…
["Non-payment of consideration amount", "Delay in possession of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the plot and did not return the consideration amount despite receiving the full payment.", "respondent_claim": "The non-applicant did not file any response or defense.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the consideration amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Pradeep Bajolia
Shri Pradeep Bajolia
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/002667270770.pdf
|
4--0#-49-4298
4--0#-49-4298
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not granting possession of a plot and not refunding the amount paid. The authority ordered the non-applicant to pay the amount with interest and compensation.
|
["Non-grant of poss…
["Non-grant of possession", "Non-refund of amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not grant possession of the plot and did not refund the amount paid.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the balance amount and that the possession of the plot was not granted due to unforeseen circumstances.", "final_verdict": "The authority ordered the non-applicant to pay the amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Yogesh Gupta
Shri Yogesh Gupta
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/142722611621.pdf
|
4/-.40-49-4296
4/-.40-49-4296
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Smt. Sharmistha Dashore, filed a c…
The applicant, Smt. Sharmistha Dashore, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not granting possession of a residential plot despite receiving the full consideration amount. The Adjudicating Officer ordered the non-applicant to pay the applicant with interest at the rate of 7% p.a. and compensation for mental distress.
|
["Non-grant of poss…
["Non-grant of possession", "Interest payment"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she had paid the full consideration amount of Rs. 6,24,200/- to the non-applicant, but the non-applicant had not granted possession of the residential plot despite the completion of development work.", "respondent_claim": "The non-applicant did not file any response or appear in the proceedings.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the applicant with interest at the rate of 7% p.a. and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Smt. Sharmistha Das…
Smt. Sharmistha Dashore
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/752065332096.pdf
|
4--II 40-49--4433
4--II 40-49--4433
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for delay in completion of development work and non-provision of possession of the plot. The Authority ordered the non-applicant to pay interest at the rate of 6% per annum on the amount paid by the applicant and compensation for mental distress.
|
["Delay in completi…
["Delay in completion of development work", "Non-provision of possession of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed the completion of development work and did not provide possession of the plot, causing mental distress and financial loss.", "respondent_claim": "The non-applicant claimed that the delay was due to unforeseen circumstances and that the applicant had not paid the full amount due.", "final_verdict": "The Authority ordered the non-applicant to pay interest at the rate of 6% per annum on the amount paid by the applicant and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Argav Khare
Shri Argav Khare
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/242644489944.pdf
|
|-0॥॥ 4-23-0025
|-0॥॥ 4-23-0025
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of interest paid to t…
The applicant sought refund of interest paid to the non-applicant for a plot booked in Project Prestige. The non-applicant was directed to pay the amount with simple interest.
|
["Refund of interes…
["Refund of interest", "Plot booking"]
|
{"appellant_claim": "The applicant sought refund …
{"appellant_claim": "The applicant sought refund of interest paid to the non-applicant for a plot booked in Project Prestige.", "respondent_claim": "The non-applicant claimed that the development work was affected due to COVID-19 and sought time to complete the work.", "final_verdict": "The non-applicant was directed to pay the amount with simple interest at the rate of 46.75% per annum.", "in_favor_of_respondent": "no"}
|
Shri Bablu Kumar Gu…
Shri Bablu Kumar Gupta
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/211716117167.pdf
|
4-20-0426
4-20-0426
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 2,68,056 with …
The applicant sought refund of Rs. 2,68,056 with interest from the non-applicant for failure to develop the plot and hand over possession within the stipulated period.
|
["Refund of advance…
["Refund of advance payment", "Interest"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of Rs. 2,68,056 with interest for failure of the non-applicant to develop the plot and hand over possession within the stipulated period.", "respondent_claim": "The non-applicant claimed that the applicant had not deposited a large amount and that the development work was affected due to COVID-19.", "final_verdict": "The non-applicant was directed to pay the applicant Rs. 2,68,056 with interest at the rate of 16.50% per annum simple interest.", "in_favor_of_respondent": "no"}
|
Shri Birendra Kumar
Shri Birendra Kumar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/779661733311.pdf
|
20-0425
20-0425
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 6,72,000 with …
The applicant sought refund of Rs. 6,72,000 with interest from the non-applicant for failure to develop the plot and hand over possession. The adjudicating officer ordered the non-applicant to pay the amount with simple interest at 6.75% per annum.
|
["Refund of amount …
["Refund of amount with interest"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of Rs. 6,72,000 with interest for failure of the non-applicant to develop the plot and hand over possession within the stipulated period.", "respondent_claim": "The non-applicant claimed that the development work was affected due to COVID-19 and sought time to complete the work.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the amount of Rs. 6,72,000 with simple interest at 6.75% per annum.", "in_favor_of_respondent": "no"}
|
Shri Birendra Kumar
Shri Birendra Kumar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/915371755759.pdf
|
5-II 40-49-253
5-II 40-49-253
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 6,48,200/- wit…
The applicant sought refund of Rs. 6,48,200/- with interest and compensation for delay in possession of a plot. The non-applicant was directed to pay the amount with simple interest and compensation for mental distress and physical torture.
|
["Refund of amount"…
["Refund of amount", "Compensation for delay"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of Rs. 6,48,200/- with interest and compensation for delay in possession of a plot.", "respondent_claim": "The non-applicant claimed that the plot was not developed and possession was not given within the stipulated period.", "final_verdict": "The non-applicant was directed to pay the amount with simple interest and compensation for mental distress and physical torture.", "in_favor_of_respondent": "no"}
|
Smt. Lata Manoj Jos…
Smt. Lata Manoj Joshi
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/741799176414.pdf
|
4-II 30-22-0293
4-II 30-22-0293
|
Madhya Pradesh
Madhya Pradesh
|
The applicants sought refund of Rs. 3,35,000/- wi…
The applicants sought refund of Rs. 3,35,000/- with interest and compensation for delay in development of plot by non-applicants. The Adjudicating Officer ordered non-applicants to pay Rs. 3,35,000/- with 43.75% interest and Rs. 4,00,000/- as compensation for mental and physical distress.
|
["Refund of amount"…
["Refund of amount", "Compensation for delay"]
|
{"appellant_claim": "The applicants claimed refun…
{"appellant_claim": "The applicants claimed refund of Rs. 3,35,000/- with interest and compensation for delay in development of plot by non-applicants.", "respondent_claim": "The non-applicants claimed that the development work was delayed due to COVID-19 and other reasons.", "final_verdict": "The Adjudicating Officer ordered non-applicants to pay Rs. 3,35,000/- with 43.75% interest and Rs. 4,00,000/- as compensation for mental and physical distress.", "in_favor_of_respondent": "no"}
|
Tafe Mata Smt. Shub…
Tafe Mata Smt. Shubhangi Mahajan
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/588581881887.pdf
|
Case Co., N-O.TH.-4…
Case Co., N-O.TH.-47-0744
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Smt. Draupadi Mandloi, filed a com…
The applicant, Smt. Draupadi Mandloi, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not giving possession of a plot and not registering it despite receiving the full payment. The Adjudicating Officer passed an order in favor of the applicant, directing the respondent to pay the principal amount, interest, and compensation.
|
["Non-delivery of p…
["Non-delivery of possession", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she had paid the full amount for a plot, but the respondent had not given her possession of the plot and had not registered it despite receiving the payment.", "respondent_claim": "The respondent did not appear in the case and did not provide any defense.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the respondent to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Smt. Draupadi Mandl…
Smt. Draupadi Mandloi
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/876228532338.pdf
|
M.I&D-47-0647
M.I&D-47-0647
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not completing the development work and not giving possession of the plot. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the entire sale amount, damages, and interest.
|
["Non-completion of…
["Non-completion of development work", "Non-giving of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not give possession of the plot despite receiving the full payment.", "respondent_claim": "The non-applicant did not respond to the complaint.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the entire sale amount, damages, and interest.", "in_favor_of_respondent": "no"}
|
Smt. Draupadi Chouk…
Smt. Draupadi Chouksey
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/351613881063.pdf
|
4- [Sh)-47-0554
4- [Sh)-47-0554
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant/promoter of Mauza Umarikheda Tehsil & District Indore for not developing the plot within the stipulated period and not handing over possession. The Adjudicating Officer passed an order in favor of the applicant.
|
["Non-development o…
["Non-development of plot", "Non-handover of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not develop the plot within the stipulated period and did not hand over possession.", "respondent_claim": "The non-applicant claimed that they had refunded the entire amount to the applicant, but did not provide any proof.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the basic consideration amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Col. Anil Singh
Col. Anil Singh
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/332453374775.pdf
|
40-47-0634
40-47-0634
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a plot and not registering the sale deed. The authority ordered the non-applicant to pay the applicant the consideration amount with interest and compensation.
|
["Non-registration …
["Non-registration of sale deed", "Non-provision of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the plot and did not register the sale deed, despite receiving the consideration amount.", "respondent_claim": "The non-applicant did not provide any response or defense.", "final_verdict": "The authority ordered the non-applicant to pay the applicant the consideration amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Smt. Sneh Jain
Smt. Sneh Jain
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/225752019531.pdf
|
4-4 545--8--0072
4-4 545--8--0072
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 4,35,000 to the non-applic…
The applicant paid Rs. 4,35,000 to the non-applicant for a plot, but the non-applicant failed to develop the plot and return the possession. The applicant sought compensation and interest.
|
["Non-development o…
["Non-development of plot", "Non-return of possession"]
|
{"appellant_claim": "The applicant paid Rs. 4,35,…
{"appellant_claim": "The applicant paid Rs. 4,35,000 for a plot, but the non-applicant failed to develop the plot and return the possession. The applicant sought compensation and interest.", "respondent_claim": "The non-applicant claimed that the development work would be completed in 18 months and the remaining amount would be repaid.", "final_verdict": "The applicant is entitled to receive the principal amount of Rs. 4,35,000 and interest at the rate of 8% per annum from 04.05.2042 to the date of payment.", "in_favor_of_respondent": "no"}
|
Smt. Sunita Nigwal
Smt. Sunita Nigwal
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/035508283805.pdf
|
74-18-00060
74-18-00060
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of the amount paid to…
The applicant sought refund of the amount paid to the non-applicant for a plot, along with interest and compensation for mental agony. The adjudicating officer ordered the non-applicant to pay the principal amount, interest, and compensation.
|
["Refund of amount …
["Refund of amount paid for plot", "Interest and compensation"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of the amount paid to the non-applicant for a plot, along with interest and compensation for mental agony.", "respondent_claim": "The non-applicant claimed that the agreement was executed between the parties, but the applicants filed their application nowhere does it mention the fact that between him and the non-applicant The contract was executed.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Smt. Shweta Sharma
Smt. Shweta Sharma
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/598785395695.pdf
|
44/--8-0059
44/--8-0059
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 4,35,000 to the non-applic…
The applicant paid Rs. 4,35,000 to the non-applicant for a plot, but the non-applicant failed to develop the plot and return the amount. The adjudicating officer ordered the non-applicant to pay the principal amount with 8% interest and compensation for mental distress.
|
["Non-payment of pl…
["Non-payment of plot development amount", "Compensation for mental distress"]
|
{"appellant_claim": "The applicant paid Rs. 4,35,…
{"appellant_claim": "The applicant paid Rs. 4,35,000 to the non-applicant for a plot, but the non-applicant failed to develop the plot and return the amount.", "respondent_claim": "The non-applicant claimed that the agreement was executed between the parties, but the applicant had nowhere mentioned the fact that the middle contract was executed.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the principal amount with 8% interest and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Ram Kishore Sh…
Shri Ram Kishore Sharma
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/751183751555.pdf
|
4-II 40-17-0485
4-II 40-17-0485
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought compensation and interest fo…
The applicant sought compensation and interest for a plot of land not developed by the respondent. The adjudicating officer ordered the respondent to return the principal amount with 8% interest and compensation for mental distress.
|
["Non-development o…
["Non-development of plot", "Interest and compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the respondent did not develop the plot as per the agreement and sought compensation and interest.", "respondent_claim": "The respondent did not appear in the case and no claim was made.", "final_verdict": "The adjudicating officer ordered the respondent to return the principal amount with 8% interest and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Parmanandji Bh…
Shri Parmanandji Bhavsar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/551817595357.pdf
|
4-7. 44/-18-0074
4-7. 44/-18-0074
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 4,35,000 to the non-applic…
The applicant paid Rs. 4,35,000 to the non-applicant for a plot, but no development work was done. The authority ordered the non-applicant to return the amount with 8% interest.
|
["Non-development o…
["Non-development of plot", "Non-return of amount"]
|
{"appellant_claim": "The applicant paid Rs. 4,35,…
{"appellant_claim": "The applicant paid Rs. 4,35,000 for a plot, but no development work was done. The applicant seeks a refund of the amount with interest.", "respondent_claim": "The non-applicant claims that the contract was executed between the parties, but the applicant had not referred to the fact that the middle contract was executed.", "final_verdict": "The authority ordered the non-applicant to return the amount of Rs. 4,35,000 with 8% interest from 27.02.2042 till the date of payment.", "in_favor_of_respondent": "no"}
|
SHRIMATI KSHAMA SONI
SHRIMATI KSHAMA SONI
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/177499919877.pdf
|
4-2 400-47-0439
4-2 400-47-0439
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not executing the sale deed and development work despite receiving the full consideration amount. The adjudicating officer ordered the non-applicant to pay the principal amount, interest, and compensation to the applicant.
|
["Non-execution of …
["Non-execution of sale deed and development work", "Non-payment of interest and compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not execute the sale deed and development work despite receiving the full consideration amount.", "respondent_claim": "The non-applicant claimed that the applicant did not pay the installments as per the agreement.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the principal amount, interest, and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Keshav Singh S…
Shri Keshav Singh Sisodia
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/431648356869.pdf
|
4-Na57/--17-060
4-Na57/--17-060
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of consideration amou…
The applicant sought refund of consideration amount along with interest and compensation for delayed development work. The adjudicating officer ordered the non-applicant to pay compensation for delayed development work and completion of development work within a specified timeframe.
|
["Delayed developme…
["Delayed development work", "Compensation"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of consideration amount along with interest and compensation for delayed development work.", "respondent_claim": "The non-applicant claimed that the development work was not completed due to unforeseen circumstances.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay compensation for delayed development work and completion of development work within a specified timeframe.", "in_favor_of_respondent": "no"}
|
Shri Ravi Gurjar
Shri Ravi Gurjar
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/151155316935.pdf
|
4 -॥ 49-48-0032
4 -॥ 49-48-0032
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant/promoter for not completing the development work and not registering the plot. The authority ordered the non-applicant to pay the principal amount, interest, and compensation to the applicant.
|
["Non-completion of…
["Non-completion of development work", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not register the plot despite receiving the full consideration amount.", "respondent_claim": "The non-applicant did not respond to the complaint and did not provide any justification for not completing the development work and not registering the plot.", "final_verdict": "The authority ordered the non-applicant to pay the principal amount of Rs. 4,78,000, interest at the rate of 8% per annum, and compensation of Rs. 5,000 for mental agony and other expenses.", "in_favor_of_respondent": "no"}
|
Smt. Shobha Saklecha
Smt. Shobha Saklecha
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/936522963352.pdf
|
4-8/.-47-0522
4-8/.-47-0522
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Mrs. Sheena Thomas, filed a compla…
The applicant, Mrs. Sheena Thomas, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work and not registering the plot despite receiving payment. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.
|
["Non-completion of…
["Non-completion of development work", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not register the plot despite receiving payment.", "respondent_claim": "The non-applicant did not appear in the proceedings and did not file any response.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Mrs. Sheena Thomas
Mrs. Sheena Thomas
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/378381080313.pdf
|
4-II 90)-47-0639
4-II 90)-47-0639
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of amount paid to the…
The applicant sought refund of amount paid to the non-applicant for non-execution of sale deeds and development work. The Adjudicating Officer ordered the non-applicant to pay the principal amount with interest and compensation for mental distress.
|
["Non-execution of …
["Non-execution of sale deeds", "Development work"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of amount paid to the non-applicant for non-execution of sale deeds and development work.", "respondent_claim": "The non-applicant claimed that the applicant had not completed the development work within the stipulated time period.", "final_verdict": "The Adjudicating Officer ordered the non-applicant to pay the principal amount with interest and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Rajiv Kumar Ja…
Shri Rajiv Kumar Jain
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/003110101893.pdf
|
44-II )-48-0434
44-II )-48-0434
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a plot despite receiving the full payment. The authority ordered the non-applicant to pay the principal amount with 8% interest and compensation for mental distress.
|
["Non-possession of…
["Non-possession of plot", "Delay in development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that they had paid the full amount for the plot, but the non-applicant had not provided possession despite completing the development work.", "respondent_claim": "The non-applicant claimed that they had not received the full payment and that the development work was still ongoing.", "final_verdict": "The authority ordered the non-applicant to pay the principal amount with 8% interest and compensation for mental distress.", "in_favor_of_respondent": "no"}
|
Smt. Rashmi Sureka …
Smt. Rashmi Sureka Jadd
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/633463571362.pdf
|
4-2 5/-18-0432
4-2 5/-18-0432
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Gopal Agarwal, filed a compla…
The applicant, Shri Gopal Agarwal, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for not providing possession of a plot and not developing the project as per the agreement. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.
|
["Non-payment of po…
["Non-payment of possession", "Delay in development"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the plot and did not develop the project as per the agreement.", "respondent_claim": "The non-applicant did not file any response or reply to the applicant's claims.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Shri Gopal Agarwal
Shri Gopal Agarwal
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/512283723566.pdf
|
04-II 470-48-0830
04-II 470-48-0830
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Mrs. Ruby Bahl, filed a complaint …
The applicant, Mrs. Ruby Bahl, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work on time and not granting possession of the plot. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.
|
["Non-completion of…
["Non-completion of development work", "Non-granting of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work on time and did not grant possession of the plot despite receiving the full payment.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the full amount and that the development work was delayed due to unforeseen circumstances.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Mrs. Ruby Bahl
Mrs. Ruby Bahl
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/519159233370.pdf
|
DhPCP1757Chhodthaga…
DhPCP1757Chhodthagatra
|
Madhya Pradesh
Madhya Pradesh
|
The applicant paid Rs. 5,50,800 to the non-applic…
The applicant paid Rs. 5,50,800 to the non-applicant for a residential plot, but the non-applicant failed to complete the development work within the stipulated period. The adjudicating officer ordered the non-applicant to pay the original amount with interest and compensation to the applicant.
|
["Non-performance o…
["Non-performance of development work", "Non-payment of interest and compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant failed to complete the development work within the stipulated period and did not pay the interest and compensation as per the agreement.", "respondent_claim": "The non-applicant did not respond to the complaint and did not provide any justification for the non-performance of the development work.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the original amount of Rs. 5,50,800 with interest at the rate of 8% per annum from the date of payment and a compensation of Rs. 40,000 for the mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Shri T.C.
Shri T.C.
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/252797217555.pdf
|
5-II 40-18-0502
5-II 40-18-0502
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of booking amount and…
The applicant sought refund of booking amount and compensation for delay in possession of a plot. The authority ordered the non-applicant to pay the principal amount with interest and compensation.
|
["Refund of booking…
["Refund of booking amount", "Compensation for delay"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of booking amount and compensation for delay in possession of a plot.", "respondent_claim": "The respondent claimed that the applicant was not entitled to refund and compensation.", "final_verdict": "The authority ordered the respondent to pay the principal amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Sachin Trivedi
Shri Sachin Trivedi
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/318176185562.pdf
|
4-2 400--48--0689
4-2 400--48--0689
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Kantilal Neema, filed a compl…
The applicant, Shri Kantilal Neema, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not developing the plot and not giving possession despite receiving the consideration amount. The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the amount with interest and compensation.
|
["Non-development o…
["Non-development of plot", "Non-payment of interest and compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not develop the plot and did not give possession despite receiving the consideration amount. The applicant sought compensation for the mental distress and other expenses incurred.", "respondent_claim": "The non-applicant did not appear in the hearing and did not file any response.", "final_verdict": "The Adjudicating Officer passed an order in favor of the applicant, directing the non-applicant to pay the amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Kantilal Neema
Shri Kantilal Neema
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/165711657757.pdf
|
4-2] 7॥ )--8--0049
4-2] 7॥ )--8--0049
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a developed plot and not refunding the amount paid. The authority ordered the non-applicant to pay the principal amount with interest and compensation for mental distress.
|
["Non-payment of po…
["Non-payment of possession", "Non-refund of amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the developed plot and did not refund the amount paid despite repeated requests.", "respondent_claim": "The non-applicant claimed that the applicant did not pay the full amount due and that the delay in possession was due to unforeseen circumstances.", "final_verdict": "The authority ordered the non-applicant to pay the principal amount of Rs. 2,00,000 with interest at the rate of 8% per annum from the date of payment of each installment to the date of payment. The authority also awarded compensation of Rs. 40,000 for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Mr. Vikas Singh Fat…
Mr. Vikas Singh Father Mr. Suresh Singh
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/581667175011.pdf
|
4-॥ 44--48--4253
4-॥ 44--48--4253
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a developed plot and not executing the sale deed. The adjudicating officer passed an order in favor of the applicant, directing the non-applicant to pay the amount with interest and compensation.
|
["Non-provision of …
["Non-provision of possession", "Non-execution of sale deed"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the developed plot and did not execute the sale deed despite receiving the full consideration amount.", "respondent_claim": "The non-applicant did not respond to the complaint and did not provide any defense.", "final_verdict": "The adjudicating officer directed the non-applicant to pay the amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Smt. Shashi Sahu
Smt. Shashi Sahu
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/395319691944.pdf
|
4-07 --48-4269
4-07 --48-4269
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant promoters for not granting possession of a plot of land and not completing the development work. The Adjudicating Officer ordered the non-applicants to pay the applicant the principal amount with interest at the rate of 8% p.a. and compensation for mental distress and other expenses.
|
["Non-grant of poss…
["Non-grant of possession", "Non-completion of development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not grant possession of the plot of land and did not complete the development work despite receiving the consideration amount.", "respondent_claim": "The non-applicants claimed that they had completed the development work and granted possession of the plot of land, but the applicant had not paid the remaining amount.", "final_verdict": "The Adjudicating Officer ordered the non-applicants to pay the applicant the principal amount with interest at the rate of 8% p.a. and compensation for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Smt. Smita Medhe
Smt. Smita Medhe
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/787878676657.pdf
|
4-48--4267
4-48--4267
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicants for not providing possession of a developed plot and not refunding the consideration amount. The authority ordered the non-applicants to pay the applicant interest and compensation.
|
["Non-provision of …
["Non-provision of possession", "Non-refund of consideration"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not provide possession of the developed plot and did not refund the consideration amount.", "respondent_claim": "The non-applicants claimed that they had paid the applicant Rs. 3,36,427/- and that the applicant had not paid the remaining amount.", "final_verdict": "The authority ordered the non-applicants to pay the applicant interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Uday Medhe
Shri Uday Medhe
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/655556557606.pdf
|
2 4-2 4॥ 0-18-4096
2 4-2 4॥ 0-18-4096
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Smt. Sangeeta Upadhyay, filed a co…
The applicant, Smt. Sangeeta Upadhyay, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for delay in possession of a residential plot and non-refund of the amount paid. The Adjudicating Officer passed an order directing the non-applicant to pay the amount with interest and compensation.
|
["Delay in possessi…
["Delay in possession", "Non-refund of amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed possession of the residential plot and did not refund the amount paid despite repeated requests.", "respondent_claim": "The non-applicant claimed that the delay was due to unforeseen circumstances and that the applicant had not paid the full amount due.", "final_verdict": "The Adjudicating Officer directed the non-applicant to pay the amount with interest at the rate of 8% per annum and compensation of Rs. 40,000/- for mental distress and harassment.", "in_favor_of_respondent": "no"}
|
Smt. Sangeeta Upadh…
Smt. Sangeeta Upadhyay
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/718501863776.pdf
|
Krimankar: |4-2 547…
Krimankar: |4-2 547-18-4502
|
Madhya Pradesh
Madhya Pradesh
|
The applicant complained about non-payment of pos…
The applicant complained about non-payment of possession and refund of consideration amount by the non-applicant. The adjudicating officer ordered the non-applicant to pay the applicant with interest and compensation.
|
["Non-payment of po…
["Non-payment of possession", "Refund of consideration amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not pay possession and refund of consideration amount despite receiving payment.", "respondent_claim": "The non-applicant claimed that the applicant did not provide evidence of the prevailing interest rate at the time of booking.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the applicant with interest and compensation.", "in_favor_of_respondent": "no"}
|
Dr. Gopal Krishna M…
Dr. Gopal Krishna Maheshwari
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/957996575176.pdf
|
7-II 540--18-1499
7-II 540--18-1499
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of the plot and not refunding the consideration amount with interest. The adjudicating officer passed an order in favor of the applicant, directing the non-applicant to pay the consideration amount with interest and compensation.
|
["Non-provision of …
["Non-provision of possession", "Non-refund of consideration amount"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the plot and did not refund the consideration amount with interest.", "respondent_claim": "The respondent did not file any claim.", "final_verdict": "The adjudicating officer directed the non-applicant to pay the consideration amount with interest and compensation to the applicant.", "in_favor_of_respondent": "no"}
|
Dr. Gopal Krishna M…
Dr. Gopal Krishna Maheshwari
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/336367665356.pdf
|
4-0]c_-48-4268
4-0]c_-48-4268
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicants for not developing the plot within the stipulated period and not granting possession. The adjudicating officer passed an order in favor of the applicant, directing the non-applicants to pay the principal amount, interest, and compensation.
|
["Non-development o…
["Non-development of plot", "Non-grant of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not develop the plot within the stipulated period and did not grant possession.", "respondent_claim": "The non-applicants claimed that they had not received any payment from the applicant and therefore did not develop the plot.", "final_verdict": "The adjudicating officer passed an order in favor of the applicant, directing the non-applicants to pay the principal amount, interest, and compensation.", "in_favor_of_respondent": "no"}
|
Smt. Rama Medhe
Smt. Rama Medhe
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/874561716674.pdf
|
4-0-18-4266
4-0-18-4266
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicants for not completing the development work and not granting possession of the plot. The adjudicating officer ordered the non-applicants to pay the applicant the amount with interest and compensation.
|
["Non-completion of…
["Non-completion of development work", "Non-grant of possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not complete the development work and did not grant possession of the plot despite receiving the consideration amount.", "respondent_claim": "The non-applicants claimed that they had not received the full consideration amount from the applicant and that the applicant had not paid the interest as per the agreement.", "final_verdict": "The adjudicating officer ordered the non-applicants to pay the applicant the amount with interest and compensation.", "in_favor_of_respondent": "no"}
|
Shri Shubh Vyas
Shri Shubh Vyas
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/155127355737.pdf
|
SHA-A20-208-00230
SHA-A20-208-00230
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Baljinder Kaur, filed a compl…
The applicant, Smt. Baljinder Kaur, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for not completing the real estate project 'Vatsalya Gaurav-2' within the stipulated time and not handing over possession of the plot. The Authority ordered the non-applicant to pay the amount deposited by the applicant along with interest.
|
["Delay in Real Est…
["Delay in Real Estate Project", "Non-Handover of Possession"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the project within the stipulated time and did not hand over possession of the plot. The applicant sought return of the deposited amount with 5% interest and compensation for mental damage.", "respondent_claim": "The non-applicant claimed that the delay was due to a dispute with the original landowner and that the project was not completed within the stipulated time due to various reasons.", "final_verdict": "The Authority ordered the non-applicant to pay the amount deposited by the applicant along with interest.", "in_favor_of_respondent": "no"}
|
Smt. Baljinder Kaur
Smt. Baljinder Kaur
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2018-00230/FILE_FINAL_ORDER_68e7ff2c-a0c4-4d9f-8b79-b56bd777dcaa.pdf
|
P4-20-209-00274
P4-20-209-00274
|
Chhattisgarh
Chhattisgarh
|
The applicant, Shabana Parveen, filed a complaint…
The applicant, Shabana Parveen, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for delay in delivery of a residential plot. The Authority ordered the respondent to pay the applicant Rs. 3,36,466/-, including the original payment and interest for the delayed period.
|
["Delay in delivery…
["Delay in delivery of residential plot", "Interest for delayed period"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the respondent delayed delivery of the residential plot and sought return of the original payment with interest.", "respondent_claim": "The respondent claimed that the delay was due to a dispute with the original landowner and sought time to resolve the issue.", "final_verdict": "The Authority ordered the respondent to pay the applicant Rs. 3,36,466/-, including the original payment and interest for the delayed period.", "in_favor_of_respondent": "no"}
|
Shabana Parveen
Shabana Parveen
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00271/FILE_FINAL_ORDER_9041ddc6-dde3-487c-bb41-a52aa2270fc8.pdf
|
S20-208-00273
S20-208-00273
|
Chhattisgarh
Chhattisgarh
|
The applicant, Mrs. Shaida Khan, filed a complain…
The applicant, Mrs. Shaida Khan, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for not developing a plot in their project and not returning her money. The authority ordered the company to pay her the amount she paid and interest for the delay.
|
["Real Estate", "De…
["Real Estate", "Delayed Development", "Unreturned Money"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she paid Rs. 8,60,000 to the respondent for a plot in their project, but the respondent did not develop the plot and did not return her money.", "respondent_claim": "The respondent claimed that they received the money from the applicant, but they were unable to develop the plot due to a dispute with the original landowner.", "final_verdict": "The authority ordered the respondent to pay the applicant Rs. 8,60,000 and interest of Rs. 4,57,950 for the delay.", "in_favor_of_respondent": "no"}
|
Jamil Akhtar Khan
Jamil Akhtar Khan
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00273/FILE_FINAL_ORDER_b895730c-b832-4d4f-bc53-82cc422f9d10.pdf
|
P4-Shri-209-00695
P4-Shri-209-00695
|
Chhattisgarh
Chhattisgarh
|
The applicant, M.R. Siddiqui, filed a complaint a…
The applicant, M.R. Siddiqui, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not developing the plot and not registering it in his name. The authority ordered the non-applicant to pay the applicant Rs. 9,78,528/-
|
["Non-development o…
["Non-development of plot", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not develop the plot and did not register it in his name despite receiving Rs. 6,20,000/-", "respondent_claim": "The non-applicant claimed that the development work could not be done due to a land dispute with the original landowner and that the applicant had prior knowledge of the dispute", "final_verdict": "The authority ordered the non-applicant to pay the applicant Rs. 9,78,528/-", "in_favor_of_respondent": "no"}
|
M.R. Siddiqui
M.R. Siddiqui
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00695/FILE_FINAL_ORDER_92d9d1dd-ced7-4f8f-837d-9a0dc8149d23.pdf
|
4-686-209-00827
4-686-209-00827
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Baljinder Kaur, filed a compl…
The applicant, Smt. Baljinder Kaur, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for delay in handing over possession of a plot and non-payment of dues. The Authority passed an order directing the non-applicant to pay Rs. 9,46,654 to the applicant within 45 days and imposed a penalty of Rs. 500 per day for violation of the order.
|
["Delay in possessi…
["Delay in possession", "Non-payment of dues"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant had delayed handing over possession of a plot and had not paid the dues amounting to Rs. 9,46,654.", "respondent_claim": "The non-applicant claimed that a contract was executed between them and the original land owner, and that the dispute with the original land owner was pending before the Honorable Arbitration Court.", "final_verdict": "The Authority passed an order directing the non-applicant to pay Rs. 9,46,654 to the applicant within 45 days and imposed a penalty of Rs. 500 per day for violation of the order.", "in_favor_of_respondent": "no"}
|
Smt. Baljinder Kaur
Smt. Baljinder Kaur
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-EXE-2019-00827/FILE_FINAL_ORDER_cb68be54-8b82-49c6-b610-2e84dd4e934d.pdf
|
4-6)06-209-00866
4-6)06-209-00866
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Shabana Parveen, filed a comp…
The applicant, Smt. Shabana Parveen, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not complying with the earlier order passed by the Authority. The Authority passed an order directing the non-applicant to pay the amount due to the applicant and imposed a penalty for violating the order.
|
["Non-compliance wi…
["Non-compliance with earlier order", "Penalty for violation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant had not complied with the earlier order passed by the Authority and sought direction to implement the order and take action against the non-applicant for violating the order.", "respondent_claim": "The non-applicant claimed that a contract was executed between him and the original land owner, and the dispute was pending before the Honorable Arbitration Court. He stated that the registry deed would be executed in favor of all potential buyers after the resolution of the dispute.", "final_verdict": "The Authority directed the non-applicant to pay Rs. 3,36,466 to the applicant within 45 days and imposed a penalty of Rs. 500 per day for violating the order.", "in_favor_of_respondent": "no"}
|
Smt. Shabana Parveen
Smt. Shabana Parveen
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-EXE-2019-00866/FILE_FINAL_ORDER_53629cf1-ddf4-4737-aeaf-74492238a3d6.pdf
|
4-Shri-209-00903
4-Shri-209-00903
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Vijaya Jain, filed a complain…
The applicant, Smt. Vijaya Jain, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not registering the plot and developing the project as per the approved layout. The authority ordered the non-applicant to pay the applicant the amount of Rs. 8,00,000/- along with interest of Rs. 4,83,469/-.
|
["Non-registration …
["Non-registration of plot", "Delay in development"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not register the plot and develop the project as per the approved layout, despite receiving the payment of Rs. 8,00,000/-.", "respondent_claim": "The non-applicant claimed that the development work could not be done due to a dispute with the original landowner, and that the applicant was aware of this dispute.", "final_verdict": "The authority ordered the non-applicant to pay the applicant the amount of Rs. 8,00,000/- along with interest of Rs. 4,83,469/-.", "in_favor_of_respondent": "no"}
|
Shri Sanjeev Jain
Shri Sanjeev Jain
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00903/FILE_FINAL_ORDER_3f702a6e-5f00-4d87-980e-011ee3130c5a.pdf
|
4-686-209-00826
4-686-209-00826
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Shaida Khan, filed a complain…
The applicant, Smt. Shaida Khan, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not complying with the earlier order passed by the Authority. The Authority passed an order directing the non-applicant to pay the amount due to the applicant and imposed a penalty for the violation.
|
["Non-compliance of…
["Non-compliance of earlier order", "Penalty for violation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant had not complied with the earlier order passed by the Authority and sought direction to the non-applicant to pay the amount due to the applicant.", "respondent_claim": "The non-applicant claimed that the dispute with the original land owner was pending before the Honorable Arbitration Court and sought time to resolve the issue.", "final_verdict": "The Authority passed an order directing the non-applicant to pay the amount due to the applicant and imposed a penalty for the violation.", "in_favor_of_respondent": "no"}
|
Smt. Shaida Khan
Smt. Shaida Khan
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-EXE-2019-00826/FILE_FINAL_ORDER_b11f62af-3e61-4da2-910c-10d14f232a84.pdf
|
4-Shri-209-00908
4-Shri-209-00908
|
Chhattisgarh
Chhattisgarh
|
The applicant sought refund of the amount paid fo…
The applicant sought refund of the amount paid for a plot in a project developed by the respondent. The authority held that the respondent was responsible for the delay in the project and ordered the respondent to pay the amount paid by the applicant along with interest.
|
["Delay in project"…
["Delay in project", "Refund of amount"]
|
{"appellant_claim": "The applicant sought refund …
{"appellant_claim": "The applicant sought refund of the amount paid for a plot in a project developed by the respondent.", "respondent_claim": "The respondent claimed that the applicant was not entitled to refund as the applicant had prior knowledge of the dispute between the respondent and the original landowner.", "final_verdict": "The authority held that the respondent was responsible for the delay in the project and ordered the respondent to pay the amount paid by the applicant along with interest.", "in_favor_of_respondent": "no"}
|
Shri Kshitij Mriddha
Shri Kshitij Mriddha
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00908/FILE_FINAL_ORDER_4ef4f274-6d31-417d-bcb9-3b49fc34daf7.pdf
|
4-209-00683
4-209-00683
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Saraswati Verma, filed a comp…
The applicant, Smt. Saraswati Verma, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not registering the plot and not completing the development work. The authority ordered the respondent to pay the applicant the amount paid with interest for the delayed period.
|
["Delay in developm…
["Delay in development work", "Non-registration of plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the respondent did not register the plot and did not complete the development work despite receiving the payment.", "respondent_claim": "The respondent claimed that the development work was delayed due to a dispute with the original landowner and that the applicant was aware of the situation.", "final_verdict": "The authority ordered the respondent to pay the applicant the amount paid with interest for the delayed period.", "in_favor_of_respondent": "no"}
|
Shri Chaitanya Kuma…
Shri Chaitanya Kumar Verma
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00683/FILE_FINAL_ORDER_d96adac2-ffaa-4b94-8838-f27f7b413edb.pdf
|
4-4-2020-00959
4-4-2020-00959
|
Chhattisgarh
Chhattisgarh
|
The applicant sought refund of amount paid for a …
The applicant sought refund of amount paid for a plot in a real estate project due to delay in completion. The authority ordered the non-applicants to pay the amount with interest for the delayed period.
|
["Real estate proje…
["Real estate project delay", "Refund of amount"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of amount paid for a plot in a real estate project due to delay in completion.", "respondent_claim": "The non-applicants claimed that the delay was due to a dispute with the original landowner and that the applicant was not entitled to refund.", "final_verdict": "The authority ordered the non-applicants to pay the amount with interest for the delayed period.", "in_favor_of_respondent": "no"}
|
Shri Rajesh Kumar Y…
Shri Rajesh Kumar Yadav
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-00959/FILE_FINAL_ORDER_1db9d1cd-7a40-4a17-a4b7-19c4d101f833.pdf
|
4-Share00-2020-0073
4-Share00-2020-0073
|
Chhattisgarh
Chhattisgarh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicants for not completing the development work and not refunding the amount paid. The authority accepted the application and ordered the non-applicants to pay the amount with interest.
|
["Non-completion of…
["Non-completion of development work", "Non-refund of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not complete the development work and did not refund the amount paid despite repeated demands.", "respondent_claim": "The non-applicants claimed that the development work was delayed due to a land dispute with the original landowner and that the applicant was not entitled to a refund.", "final_verdict": "The authority accepted the application and ordered the non-applicants to pay the amount with interest.", "in_favor_of_respondent": "no"}
|
Ms. Sunita Pahuja
Ms. Sunita Pahuja
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01073/FILE_FINAL_ORDER_7558e5c1-3f31-4bc1-abd5-a9de18e8d179.pdf
|
4-4-2020-0087
4-4-2020-0087
|
Chhattisgarh
Chhattisgarh
|
The applicant paid Rs. 8,92,000 to the non-applic…
The applicant paid Rs. 8,92,000 to the non-applicants for a plot, but no development work was done. The Authority ordered the non-applicants to pay the amount back with interest.
|
["Real Estate", "De…
["Real Estate", "Delayed Payment"]
|
{"appellant_claim": "The applicant paid Rs. 8,92,…
{"appellant_claim": "The applicant paid Rs. 8,92,000 to the non-applicants for a plot, but no development work was done. The applicant demanded a refund with interest.", "respondent_claim": "The non-applicants claimed that they did not receive any payment from the applicant and that the project was delayed due to a land dispute with the original land-owner.", "final_verdict": "The Authority ordered the non-applicants to pay the amount of Rs. 8,92,000 back to the applicant with interest of Rs. 5,80,692 for the delayed period of 7 years.", "in_favor_of_respondent": "no"}
|
Mehar Singh Hunjal
Mehar Singh Hunjal
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01087/FILE_FINAL_ORDER_7c92fe71-82ae-4d2f-ae09-57e8fd3d367f.pdf
|
A4-2020-0077
A4-2020-0077
|
Chhattisgarh
Chhattisgarh
|
The applicant paid Rs. 3,96,000/- to the non-appl…
The applicant paid Rs. 3,96,000/- to the non-applicants for the disputed deal. The non-applicants are fully responsible for the loss caused to the allottee / applicant due to the delay in the project in question.
|
["Delay in project"…
["Delay in project", "Non-refund of amount"]
|
{"appellant_claim": "The applicant paid Rs. 3,96,…
{"appellant_claim": "The applicant paid Rs. 3,96,000/- to the non-applicants for the disputed deal. The non-applicants are fully responsible for the loss caused to the allottee / applicant due to the delay in the project in question.", "respondent_claim": "The non-applicants claimed that they have not received any amount from the applicant for the disputed deal.", "final_verdict": "The amount paid by the applicant to the non-applicants Rs. 3,96,000/- only and the interest amount calculated thereon Rs. 2,24,037/- i.e. total amount Rs. 6,20,037/- (verbatim amount- six lakh twenty thousand thirty seven only), should be paid by non-applicant No. 2 to the applicant within two months.", "in_favor_of_respondent": "no"}
|
Asif Abu, Mohammad,…
Asif Abu, Mohammad, father- Mohammad Abu Jamshed
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01071/FILE_FINAL_ORDER_c9f6ee6a-ad03-455e-9c58-4b6139d7129e.pdf
|
4-Shri-209-00623
4-Shri-209-00623
|
Chhattisgarh
Chhattisgarh
|
The applicant, Shri Sandeep Singh Chauhan, filed …
The applicant, Shri Sandeep Singh Chauhan, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work of the project 'Vatsalya Gaurav-4' and not returning the amount paid. The Authority passed an order directing the non-applicant to execute the registry deed and hand over possession of the plot.
|
["Development work"…
["Development work", "Return of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work of the project and did not return the amount paid despite several requests.", "respondent_claim": "The non-applicant claimed that the project was registered in the name of M/s Silver Developers and that they were not responsible for the development work.", "final_verdict": "The Authority directed the non-applicant to execute the registry deed and hand over possession of the plot to the applicant.", "in_favor_of_respondent": "no"}
|
Shri Sandeep Singh …
Shri Sandeep Singh Chauhan
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00623/FILE_FINAL_ORDER_3f8f2771-2626-44cb-8415-e1663668fdc5.pdf
|
4-Shri-209-00855
4-Shri-209-00855
|
Chhattisgarh
Chhattisgarh
|
The applicant, Vishal Singh, filed a complaint ag…
The applicant, Vishal Singh, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not executing the registry deed of a plot and not completing the development work of the project. The Authority passed an order directing the non-applicant to execute the registry deed and complete the development work.
|
["Development block…
["Development blocked project", "Registry deed", "Development work"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not execute the registry deed of the plot and did not complete the development work of the project despite receiving payment.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the remaining amount of sale consideration and that the development work was pending due to various reasons.", "final_verdict": "The Authority passed an order directing the non-applicant to execute the registry deed of the plot and complete the development work of the project within two months.", "in_favor_of_respondent": "no"}
|
Vishal Singh
Vishal Singh
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00855/FILE_FINAL_ORDER_13e1e005-dbed-464e-855a-e78dd34d559d.pdf
|
4-Shri-209-00867
4-Shri-209-00867
|
Chhattisgarh
Chhattisgarh
|
The applicant sought return of amount paid for a …
The applicant sought return of amount paid for a plot in a development project, compensation, and litigation expenses. The authority ordered the non-applicant to execute the registry deed and hand over possession of the plot, and directed the Collector to take action to complete the development work.
|
["Development block…
["Development blocked project", "Return of amount paid"]
|
{"appellant_claim": "The applicant claimed that h…
{"appellant_claim": "The applicant claimed that he had paid an amount of Rs. 2,99,500/- for a plot in the non-applicant's project, but the non-applicant had not completed the development work and had not returned the amount paid.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the remaining amount due, and that the development work was pending due to various reasons.", "final_verdict": "The authority ordered the non-applicant to execute the registry deed and hand over possession of the plot, and directed the Collector to take action to complete the development work.", "in_favor_of_respondent": "no"}
|
Shri Chhote Singh R…
Shri Chhote Singh Rajput
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00867/FILE_FINAL_ORDER_e6763073-5714-4be0-83c9-8eb80f16ad3c.pdf
|
4-Shri-209-00900
4-Shri-209-00900
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Tanuja Tiwari, filed a compla…
The applicant, Smt. Tanuja Tiwari, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work of the disputed project and not returning the amount paid. The Authority passed an order directing the non-applicant to execute the registry deed and hand over possession of the plot.
|
["Development work"…
["Development work", "Registry deed"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work of the disputed project and did not return the amount paid.", "respondent_claim": "The non-applicant claimed that the development work was pending due to various reasons and that the applicant had not paid the remaining amount.", "final_verdict": "The Authority directed the non-applicant to execute the registry deed and hand over possession of the plot within two months.", "in_favor_of_respondent": "no"}
|
Smt. Tanuja Tiwari
Smt. Tanuja Tiwari
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00900/FILE_FINAL_ORDER_fd13d324-4828-4d01-9f4f-1fd869d641cf.pdf
|
A4-Shri-209-0090
A4-Shri-209-0090
|
Chhattisgarh
Chhattisgarh
|
The applicant, Mrs. Meena Dhruv, filed a complain…
The applicant, Mrs. Meena Dhruv, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work of the project 'Vatsalya Gaurav' and not returning the amount paid by her husband. The Authority passed an order directing the non-applicant to pay the amount and execute the registry deed of the plot.
|
["Development work"…
["Development work", "Refund of amount"]
|
{"appellant_claim": "The applicant claimed that h…
{"appellant_claim": "The applicant claimed that her husband had paid an amount of Rs. 4,40,740/- to the non-applicant for a plot in the project 'Vatsalya Gaurav', but the non-applicant had not completed the development work and not returned the amount.", "respondent_claim": "The non-applicant claimed that the project was registered in the name of M/s Silver Developers and that the dispute was pending in the High Court.", "final_verdict": "The Authority directed the non-applicant to pay the amount of Rs. 2,255/- to the applicant, execute the registry deed of the plot, and complete the development work of the project within two months.", "in_favor_of_respondent": "no"}
|
Mrs. Meena Dhruv
Mrs. Meena Dhruv
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00901/FILE_FINAL_ORDER_cdcc4c93-930e-4fd6-a2d9-8f0d9ccf5a14.pdf
|
4-4-2020-0033
4-4-2020-0033
|
Chhattisgarh
Chhattisgarh
|
The applicants paid Rs. 3,70,000/- to the non-app…
The applicants paid Rs. 3,70,000/- to the non-applicant for the disputed deal, but the non-applicant did not complete the development work in the project. The applicants are entitled to get back the entire amount paid by them along with interest for the delayed period.
|
["Delay in developm…
["Delay in development work", "Non-refund of amount"]
|
{"appellant_claim": "The applicants claimed that …
{"appellant_claim": "The applicants claimed that they paid Rs. 3,70,000/- to the non-applicant for the disputed deal, but the non-applicant did not complete the development work in the project. The applicants demanded refund of the amount paid along with interest for the delayed period.", "respondent_claim": "The non-applicant claimed that they did not receive any amount from the applicants for the disputed deal. The non-applicant also claimed that the applicants filed the application after seven years for the alleged transaction that took place in the year 203, which is time barred.", "final_verdict": "The Authority accepted the application of the applicants and passed an order against the non-applicant to pay the amount of Rs. 3,70,000/- paid by the applicants and the interest amount of Rs. 2,06,460/- to the applicants within two months.", "in_favor_of_respondent": "no"}
|
Mangala Srivastava
Mangala Srivastava
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01033/FILE_FINAL_ORDER_8a7efcf7-6bb1-4013-b979-ab41a7659be9.pdf
|
4-Share-2020-0770
4-Share-2020-0770
|
Chhattisgarh
Chhattisgarh
|
The applicant, Mrs. Manju Jain, filed a complaint…
The applicant, Mrs. Manju Jain, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work of the project and not returning the amount paid. The Authority ordered the non-applicant to pay the amount paid by the applicant along with interest.
|
["Non-completion of…
["Non-completion of development work", "Non-return of amount paid"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she paid Rs. 9,48,600/- to the non-applicant for the disputed plot deal and the non-applicant did not complete the development work within the stipulated time period.", "respondent_claim": "The non-applicant claimed that the applicant did not pay any amount for the disputed plot deal and the application was time-barred.", "final_verdict": "The Authority ordered the non-applicant to pay the amount paid by the applicant along with interest.", "in_favor_of_respondent": "no"}
|
Mrs. Manju Jain
Mrs. Manju Jain
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01110/FILE_FINAL_ORDER_b30eee6b-ce46-4326-a579-22f072e16726.pdf
|
4-4-2020-036
4-4-2020-036
|
Chhattisgarh
Chhattisgarh
|
The applicant, Mrs. Kamaljit Kaur, filed a compla…
The applicant, Mrs. Kamaljit Kaur, filed a complaint against Vatsalya Builders & Developers Pvt. Ltd. for not completing the development work of the project and not returning the amount paid. The authority accepted the application and ordered the respondent to return the amount paid with interest.
|
["Non-completion of…
["Non-completion of development work", "Non-return of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the respondent did not complete the development work of the project and did not return the amount paid despite repeated requests.", "respondent_claim": "The respondent claimed that the applicant did not make any booking with them for the disputed plot and did not pay any amount for the disputed deal.", "final_verdict": "The authority accepted the application of the applicant and ordered the respondent to return the amount paid with interest.", "in_favor_of_respondent": "no"}
|
Shri Charanjit Singh
Shri Charanjit Singh
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-01136/FILE_FINAL_ORDER_ab72c3de-19c4-4b1a-a275-cdca7a8b50b0.pdf
|
4-?sh20-2022-0724
4-?sh20-2022-0724
|
Chhattisgarh
Chhattisgarh
|
The applicant, Shri Vipul Tembe, filed a complain…
The applicant, Shri Vipul Tembe, filed a complaint against M/s Vatsalya Builders & Developers Pvt. Ltd. for delay in development work and non-execution of registry deed. The Authority ordered the non-applicants to pay the amount paid by the applicant with interest.
|
["Delay in developm…
["Delay in development work", "Non-execution of registry deed"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants delayed the development work and did not execute the registry deed despite receiving the full payment.", "respondent_claim": "The non-applicants did not submit any reply during the hearing.", "final_verdict": "The Authority ordered the non-applicants to pay the amount paid by the applicant with interest.", "in_favor_of_respondent": "no"}
|
Shri Vipul Tembe
Shri Vipul Tembe
|
Vatsalya Builders &…
Vatsalya Builders & Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2022-01724/FILE_FINAL_ORDER_c1045a5b-12e1-43fe-bbe2-95cb8d0424a3.pdf
|
KMI ND,--47-0707
KMI ND,--47-0707
|
Madhya Pradesh
Madhya Pradesh
|
The applicant filed a complaint against the non-a…
The applicant filed a complaint against the non-applicant for not providing possession of a plot and not registering the sale deed. The adjudicating officer ordered the non-applicant to pay the principal amount with interest and compensation for mental distress and other expenses.
|
["Non-payment of po…
["Non-payment of possession", "Non-registration of sale deed"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not provide possession of the plot and did not register the sale deed despite receiving the full payment.", "respondent_claim": "The non-applicant claimed that the applicant did not pay the interest as per the agreement and did not provide the necessary documents.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the principal amount with interest at the rate of 8% per annum and compensation for mental distress and other expenses.", "in_favor_of_respondent": "no"}
|
Dr. Sunita Bhatnagar
Dr. Sunita Bhatnagar
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://www.rera.mp.gov.in/upload/complaint_files/231188625837.pdf
|
4-Shri-209-00795
4-Shri-209-00795
|
Chhattisgarh
Chhattisgarh
|
The applicant, Brahmadev Chaudhary, filed a compl…
The applicant, Brahmadev Chaudhary, filed a complaint against Vatsalya Builders and Developers Pvt. Ltd. for not completing the development work and not refunding the amount paid. The authority accepted the application and ordered the non-applicant to pay the amount with interest.
|
["Delay in developm…
["Delay in development work", "Non-refund of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant did not complete the development work and did not refund the amount paid despite repeated demands.", "respondent_claim": "The non-applicant claimed that the development work was delayed due to a dispute with the original landowner and that the applicant was not entitled to a refund.", "final_verdict": "The authority accepted the application and ordered the non-applicant to pay the amount with interest.", "in_favor_of_respondent": "no"}
|
Brahmadev Chaudhary
Brahmadev Chaudhary
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00795/FILE_FINAL_ORDER_96ad1685-adaa-46fc-8225-8ffc9eb9756d.pdf
|
4-Shri-209-00868
4-Shri-209-00868
|
Chhattisgarh
Chhattisgarh
|
The applicant paid Rs. 5,25,000 to the non-applic…
The applicant paid Rs. 5,25,000 to the non-applicant for a plot, but the non-applicant failed to develop the plot and return the amount. The authority ordered the non-applicant to pay the amount with interest.
|
["Non-development o…
["Non-development of plot", "Delay in refund"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant failed to develop the plot and return the amount paid.", "respondent_claim": "The non-applicant claimed that the development work was delayed due to a dispute with the original landowner.", "final_verdict": "The authority ordered the non-applicant to pay the amount with interest.", "in_favor_of_respondent": "no"}
|
Smt. Indravati Dwiv…
Smt. Indravati Dwivedi
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2019-00868/FILE_FINAL_ORDER_c71c8f9e-f7ff-4235-b5d4-c50c40746461.pdf
|
4-4-2020-00979
4-4-2020-00979
|
Chhattisgarh
Chhattisgarh
|
The applicant, Mrs. Biji Pillai, filed a complain…
The applicant, Mrs. Biji Pillai, filed a complaint against Vatsalya Builders and Developers Pvt. Ltd. for not completing the development work of the project and not refunding the amount paid. The authority ordered the non-applicants to pay the amount paid by the applicant with interest.
|
["Delay in developm…
["Delay in development work", "Non-refund of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicants did not complete the development work of the project and did not refund the amount paid despite several requests.", "respondent_claim": "The non-applicants claimed that the development work could not be done due to a land dispute with the original landowner and that the agreement with the applicant mentioned handing over the possession of the plot within 24 months.", "final_verdict": "The authority ordered the non-applicants to pay the amount paid by the applicant with interest.", "in_favor_of_respondent": "no"}
|
Mrs. Biji Pillai
Mrs. Biji Pillai
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2020-00979/FILE_FINAL_ORDER_0c4e6692-e78c-487d-aa59-fc6dd5a14874.pdf
|
S20-2024-0545
S20-2024-0545
|
Chhattisgarh
Chhattisgarh
|
The applicant, Deepmala Lakra, filed a complaint …
The applicant, Deepmala Lakra, filed a complaint against Vatsalya Builders and Developers Pvt. Ltd. for delay in development work and non-refund of amount paid. The Authority ordered the non-applicant to pay the amount paid by the applicant with interest.
|
["Delay in developm…
["Delay in development work", "Non-refund of amount paid"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she paid an amount of Rs. 40,78,000/- to the non-applicant for the disputed deal, but the non-applicant did not complete the development work and did not refund the amount.", "respondent_claim": "The non-applicant did not submit any reply during the hearing of the case.", "final_verdict": "The Authority ordered the non-applicant to pay the amount paid by the applicant with interest.", "in_favor_of_respondent": "no"}
|
Deepmala Lakra
Deepmala Lakra
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2021-01545/FILE_FINAL_ORDER_c0869d67-894a-4c3f-945c-0190e1b44eb1.pdf
|
S20-202-0546
S20-202-0546
|
Chhattisgarh
Chhattisgarh
|
The applicant, Smt. Teresa Lakra, filed a complai…
The applicant, Smt. Teresa Lakra, filed a complaint against Vatsalya Builders and Developers Pvt. Ltd. for delay in development work and non-refund of the amount paid. The authority ordered the non-applicant to pay the amount paid by the applicant along with interest.
|
["Delay in developm…
["Delay in development work", "Non-refund of amount paid"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant delayed the development work and did not refund the amount paid despite repeated requests.", "respondent_claim": "The non-applicant did not submit any reply during the hearing.", "final_verdict": "The authority ordered the non-applicant to pay the amount paid by the applicant along with interest.", "in_favor_of_respondent": "no"}
|
Smt. Teresa Lakra
Smt. Teresa Lakra
|
Vatsalya Builders a…
Vatsalya Builders and Developers Private Limited
|
https://rera.cgstate.gov.in/Content/ComplaintDocuments/Application_M-PRO-2021-01546/FILE_FINAL_ORDER_4f334060-18bf-44c4-9ff4-d0d31d0d6807.pdf
|
4-2 40-47-0062
4-2 40-47-0062
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Bulbul Goyal, withdrew her name fr…
The applicant, Bulbul Goyal, withdrew her name from the case, and there was no transaction balance. The proceedings were terminated, and the case was stored in the archives.
|
["Withdrawal of app…
["Withdrawal of applicant", "Termination of proceedings"]
|
{"appellant_claim": "The applicant claimed that s…
{"appellant_claim": "The applicant claimed that she had paid a cheque of Rs. 4,54,000/- and Rs. 4,54,000/- to the applicant, and suit expenses of Rs. 3000/-.", "respondent_claim": "The respondent claimed that the applicant had voluntarily accepted the cheque and suit expenses.", "final_verdict": "The case was terminated, and the proceedings were closed due to the withdrawal of the applicant's name and lack of transaction balance.", "in_favor_of_respondent": "no"}
|
Bulbul Goyal
Bulbul Goyal
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/500318663655.pdf
|
2 4-2 40-47-573
2 4-2 40-47-573
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Dr. Sunil Kumar Pandey, agreed wit…
The applicant, Dr. Sunil Kumar Pandey, agreed with the non-applicant, Vatsalya Builders & Developers, outside the authority, and the case was quashed.
|
["Agreement between…
["Agreement between parties"]
|
{"appellant_claim": "The applicant submitted a re…
{"appellant_claim": "The applicant submitted a request to withdraw the case as he had agreed with the non-applicant outside the authority.", "respondent_claim": "Not provided", "final_verdict": "The case was quashed as the applicant and non-applicant had reached an unconditional agreement.", "in_favor_of_respondent": "no"}
|
Dr. Sunil Kumar Pan…
Dr. Sunil Kumar Pandey
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/725921717012.pdf
|
D-Ba0-8-0595
D-Ba0-8-0595
|
Madhya Pradesh
Madhya Pradesh
|
The applicant, Shri Swapnil Marathe, filed a comp…
The applicant, Shri Swapnil Marathe, filed a complaint against Vatsalya Builders & Developers for not paying compensation. The authority passed an order in favor of the applicant, and the case was resolved.
|
["Non-payment of co…
["Non-payment of compensation"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the respondent did not pay compensation despite the authority's order.", "respondent_claim": "No response was submitted by the respondent.", "final_verdict": "The authority passed an order in favor of the applicant, and the case was resolved.", "in_favor_of_respondent": "no"}
|
Shri Swapnil Marathe
Shri Swapnil Marathe
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/516181165354.pdf
|
4-2 400-20-0770
4-2 400-20-0770
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought compensation and refund of t…
The applicant sought compensation and refund of the amount paid to the non-applicant for a plot booked in the Shiv Residency Phase-2 project. The adjudicating officer ordered the non-applicant to pay the refund with interest and compensation for the applicant's expenses.
|
["Refund of amount …
["Refund of amount paid", "Compensation for expenses"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that they had paid Rs. 3,33,000 to the non-applicant for a plot booked in the Shiv Residency Phase-2 project, but the non-applicant had failed to develop the plot and hand over possession. The applicant sought refund of the amount paid with interest and compensation for their expenses.", "respondent_claim": "The non-applicant claimed that the applicant had failed to pay the amount due to them and had also failed to comply with the terms of the agreement.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the refund of Rs. 3,33,000 with interest at the rate of 46.60% per annum from the date of payment to the date of repayment. The non-applicant was also ordered to pay compensation of Rs. 40,000 for the applicant's suit expenses and Rs. 25,000 for mental distress and physical torture.", "in_favor_of_respondent": "no"}
|
Shri Asif Khan
Shri Asif Khan
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/626616331686.pdf
|
4-2 400-22-0292
4-2 400-22-0292
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought compensation and litigation …
The applicant sought compensation and litigation expenses from the non-applicant for failing to develop a plot and return the amount paid. The adjudicating officer ordered the non-applicant to pay the amount with interest and compensation for mental and physical distress.
|
["Non-payment of am…
["Non-payment of amount", "Failure to develop plot"]
|
{"appellant_claim": "The applicant claimed that t…
{"appellant_claim": "The applicant claimed that the non-applicant failed to develop the plot and return the amount paid, causing mental and physical distress.", "respondent_claim": "The non-applicant claimed that the applicant failed to pay the amount on time and that the delay was due to the applicant's fault.", "final_verdict": "The adjudicating officer ordered the non-applicant to pay the amount with interest and compensation for mental and physical distress.", "in_favor_of_respondent": "no"}
|
Shri Asif Khan
Shri Asif Khan
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/645163216111.pdf
|
Case No./-II 400-24…
Case No./-II 400-24-0545
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 9,34,670/- wit…
The applicant sought refund of Rs. 9,34,670/- with interest and compensation for mental and physical torture. The Adjudicating Officer ordered refund of Rs. 9,34,870/- with interest and compensation of Rs. 75,000/- for mental distress.
|
["Refund of amount …
["Refund of amount with interest and compensation"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of Rs. 9,34,670/- with interest and compensation for mental and physical torture.", "respondent_claim": "The respondent claimed that the applicant was not entitled to refund and compensation.", "final_verdict": "The Adjudicating Officer ordered refund of Rs. 9,34,870/- with interest and compensation of Rs. 75,000/- for mental distress.", "in_favor_of_respondent": "no"}
|
Shri Krishna Kant Y…
Shri Krishna Kant Yadav
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/771171766161.pdf
|
2 500-20-0847
2 500-20-0847
|
Madhya Pradesh
Madhya Pradesh
|
The applicant sought refund of Rs. 6,50,000 paid …
The applicant sought refund of Rs. 6,50,000 paid to the non-applicant for a plot that was not developed and possession not given. The adjudicating officer ordered refund of the amount with simple interest and compensation for mental and physical distress.
|
["Refund of payment…
["Refund of payment", "Compensation for delay"]
|
{"appellant_claim": "The applicant claimed refund…
{"appellant_claim": "The applicant claimed refund of Rs. 6,50,000 paid to the non-applicant for a plot that was not developed and possession not given.", "respondent_claim": "The non-applicant claimed that the applicant had not paid the amount due to them.", "final_verdict": "The adjudicating officer ordered refund of the amount with simple interest and compensation for mental and physical distress.", "in_favor_of_respondent": "no"}
|
Shri Rajesh Kumar O…
Shri Rajesh Kumar Ojha
|
Vatsalya Builders &…
Vatsalya Builders & Developers
|
https://www.rera.mp.gov.in/upload/complaint_files/136329131339.pdf
|