WTC NOIDA DEVELOPMENT COMPANY LIMITED

  • No of Complaints: 21
  • States (Active in): Gujarat, Punjab, Uttar Pradesh
CIN Not Available
Year Established Not Available
Address Not Available
Company Status Not Available

Introduction

WTC Noida Development Company Limited has garnered attention within the real estate sector, particularly due to its engagement in various legal disputes. With a notable history of complaints and court cases, potential buyers may wonder what this means for their investment choices. This blog delves into the builder's legal performance, examining the patterns in cases lost and won, and offering insights for prospective buyers.

Overview of Complaints

WTC Noida Development Company Limited has faced a total of 21 complaints, of which they lost 6 cases and won 15. The complaints span multiple states, including Punjab, Gujarat, and Uttar Pradesh, highlighting a diverse geographical impact of their operations.

Analysis of Lost Cases

In the 6 cases where WTC Noida lost, the following patterns emerged:

  1. Claims for Recovery: Many cases involved complaints related to the recovery of amounts paid for units, specifically citing delay or failure to deliver possession. In one notable instance, the complainant alleged that possession was not provided, while the builder contended that the complaint was unripe due to possession not being due yet. This reflects a common issue regarding the timelines and expectations around possession of property.
  2. Dismissals due to Procedural Issues: Several cases were dismissed due to lack of prosecution or the non-appearance of the complainant. This indicates procedural deficiencies on the part of the complainants rather than substantive failures on the part of the builder.
  3. Settlements: One case was resolved as settled, suggesting that some disputes could be addressed outside the court process, but it may also point to a strategic decision by the builder to mitigate further litigation risks.

Analysis of Won Cases

When examining the 15 cases won by WTC Noida, certain patterns can be identified:

  1. Favorable Evidence Submission: In many instances, the builder defended claims by demonstrating that construction was progressing according to schedule or that all required information was being provided to the complainants. This points to a reflective adherence to project timelines and ongoing communication with stakeholders.
  2. Regulatory Compliance: Several defenses revolved around compliance with existing regulations and the successful registration of projects. The builder’s ability to demonstrate this compliance likely played a significant role in their legal victories.
  3. Settlement Resolutions: Similar to lost cases, several won cases were resolved through settlements, indicating the builder's preference for negotiated agreements over prolonged litigation, which can be beneficial for both parties.

Conclusion

Based on the provided data, WTC Noida Development Company Limited presents a mixed portfolio concerning legal disputes. While the builder has faced a considerable number of complaints, they have also been successful in winning a majority of the cases brought against them. This suggests that while there are areas for concern, particularly regarding delivery timelines, the company has systems in place to manage and respond to these disputes effectively.

Tips for Potential Buyers

  1. Do Thorough Research: Before investing, prospective buyers should research the builder’s past projects, complaint histories, and the outcomes of any legal issues. Understanding the context can provide better insights into their reliability as a developer.
  2. Inquire About Timelines and Ownership: Ensure clarity on timelines for possession and ownership rights during the purchase process. Clear communication with the builder on these points is crucial.
  3. Look for Settlements: Investigating whether past complaints ended in settlements can reveal how the builder engages with clients post-sale, especially in resolving grievances amicably.

General Tips for Selecting Any Builder

  • Check Credentials: Verify the credentials of the builder, including their registration with relevant authorities and any industry certifications.
  • Read Reviews and Testimonials: Customer feedback can provide insights into the builder's reputation and service quality. Look for online reviews and word-of-mouth referrals.
  • Understand Your Rights: Familiarize yourself with your rights as a buyer under local real estate laws to ensure protection in case of disputes.

In summary, while WTC Noida Development Company Limited has experienced challenges, their response patterns in legal matters suggest a degree of resilience and a commitment to regulatory compliance that potential buyers can consider when making their purchasing decisions.

No builder reviews yet. Be the first to share your thoughts!

Project Progress and Transparency Claims Refund and Interest Disputes Compliance with Regulatory Directions Delayed Possession and Payment Assurances

Analysis of the cases filed against WTC Noida Development Company Limited, where the builder lost, reveals a spectrum of disputes primarily revolving around project delivery and compliance with regulatory requirements.

The cases can be grouped into several common themes. Firstly, there are recurring Project Progress and Transparency Claims, where appellants often expressed concerns where the builder failed to provide adequate information on the construction progress of projects like 'WTC Gift Tower A, B, and D'. This highlights an significant area of dissatisfaction among buyers who expected regular updates on their investments.

Another prominent theme involves Refund and Interest Disputes. In several instances, appellants sought refunds due to alleged violations of the RERA Act or delays in project completion. The builder's inability to meet the expectations of timely refunds and interest compensation was a key factor in these disputes.

Compliance with Regulatory Directions is a crucial theme that emerged from the cases. The builder faced challenges from the regulatory authority regarding adherence to approved plans and timelines. Failure to submit mandatory progress reports and comply with directions resulted in legal consequences, indicating a systemic issue within the builder's operations.

Lastly, Delayed Possession and Payment Assurances stand out as a theme that directly affects buyers' trust and financial stability. Cases where the builder was accused of delaying possession or failing to assure payments invited legal scrutiny, leading to verdicts that emphasized the need for accountability in meeting contractual obligations.

Common reasons for bringing cases to court include contesting penalties for delays, disputing project timelines, and seeking refunds or interest on deposits. People were driven to litigation primarily due to a lack of transparency, delays in communication from the builder, and financial grievances that were not addressed promptly.

The builder lost these cases largely due to insufficient evidence provided in their defense, failure to comply with regulatory requirements, and a pattern of neglecting to follow through on interim directions from authorities. The verdicts suggest a fundamental misunderstanding of the importance of clear communication and adherence to legal standards in real estate development, which negatively impacted their ability to fulfill commitments to buyers.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
CMP/Offline/Gandhin… Gujarat The complainant, Mr. Yagnesh Kumar Kanubhai Gohil… ["Delayed payment",… {"appellant_claim": "The complainant claimed that… Mr. Yagnesh Kumar K… WTC Noida Developme… https://drive.google.com/uc?id=1K1CkpKyp0ng1ODzbElSH7shed1gUgfhN
16/2023 Uttar Pradesh The appellants challenged the impugned order date… ["Refund of deposit… {"appellant_claim": "The appellants claimed that … Sarfaraz Hasnain Sh… WTC Noida Developme… ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MDYwMTExNi0yMDIzLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85OTU3MDQxNi0yMy5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy84OTU2NjQxNi0yMDIzLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy80ODA0NDYxNi0yMDIzLnBkZg==', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82NDgxMjAxNi0yMy5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85MjUxNzE2LTIwMjMucGRm']
GC No. 0433/2023 Punjab Complaint filed by Ranjit Singh Anand against WTC… ["Withdrawal of com… {"appellant_claim": "The complainant filed a comp… Ranjit Singh Anand WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgements\2024\M4219\/20240130FormM_OJbyAuth35917adf-3b28-47fc-b6fd-4a82c982f979.pdf
RERA/ AdCNo 0137 OF… Not provided The complainant and respondent entered into a wri… ["Settlement", "Dis… {"appellant_claim": "Not provided", "respondent_c… Nishant Mor WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgementsByAO\2022\N2320\/20220224FormN_OJbyAOe0248913-8f46-4286-8ea8-20fa57a702a1.pdf
RERA/ AdCNo 0135 OF… Not provided The complaint was dismissed as settled between th… ["Settlement", "Pay… {"appellant_claim": "Not provided", "respondent_c… Shelly Singh WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgementsByAO\2022\N2318\/20220224FormN_OJbyAOe1f97c09-8d7a-4ba3-9be7-051c499cef6d.pdf
RERA/AdCNo 0008 OF … Not provided Complaint filed for refund and interest, but with… ["Withdrawn complai… {"appellant_claim": "Seeking refund of amount and… Anand Nandan WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgementsByAO\2022\N2815\/20220713FormN_OJbyAO72dc8da5-f3a7-4d4d-b171-d38b52b2a22d.pdf
CMP/Gandhinagar/221… Gujarat The case is related to the project 'WTC Gift Towe… ["Project Progress … {"appellant_claim": "The appellant claimed that t… Sunil Kumar Agrawal WTC Noida Developme… https://drive.google.com/uc?id=1LBLDNTQh--5h101i7HOjlBfk1JGD3fuh
CMP/Gandhinagar/220… Gujarat The complaint was disposed of in terms of a settl… ["Settlement Deed"] {"appellant_claim": "Not provided", "respondent_c… Comprom Services LLP WTC Noida Developme… https://drive.google.com/uc?id=1Ji5Mfb5IoN1WMTh8nUDhhhnxRqalmO0n
Delayed Possession Claims Dismissals for Non-Appearance Review Applications Settled Complaints Wants of Prosecution

An analysis of the cases filed against the builder, WTC Noida Development Company Limited, which the builder won, revealed the following information: The disputes primarily revolved around themes such as Delayed Possession Claims, dismissals due to non-appearance, settlement of complaints, and review applications.

In the case of delayed possession, one complainant sought the recovery of amounts paid for a unit, alleging failure to deliver possession. However, the builder successfully argued that the possession date was not yet due when the complaint was filed, leading to a dismissal of that claim. This indicates a common concern among buyers regarding timely possession, yet the builder effectively responded by pointing to the legal timelines in place.

Several cases were dismissed for want of prosecution or due to the non-appearance of the complainants. This outcome suggests that some buyers did not pursue their claims actively or may have been unable to provide necessary evidence, which reflects on the nature of some disputes that may lack sufficient foundational claims. In some circumstances, cases were referenced as settled under specific conditions, illustrating negotiations that often take place outside of court.

Moreover, the review applications filed by appellants did not succeed, as it was identified that the review applicants failed to demonstrate any errors in the earlier judgments. This exemplifies how the builder stands firm against claims and underscores the necessity for opposing parties to have solid grounds for their arguments.

Through this analysis, it becomes evident that the builder has been successful in defending itself against claims often rooted in misunderstandings of legal timelines or internal issues within the complainants' cases. Not only does this reflect positively on WTC Noida Development Company Limited's operations and adherence to legal obligations, but it also casts a spotlight on the potential for buyers' claims to sometimes be influenced by emotional responses to project timelines.

The broader implications of this analysis indicate that while there are indeed legitimate grievances within the real estate market, WTC Noida Development Company Limited appears to have a strong foothold in responding to unwarranted claims. This reinforces the idea that buyers must approach claims with caution and draw conclusions based on thorough investigations rather than singular incidents.

In conclusion, potential buyers should prioritize making informed decisions when weighing builders and their reputations. The evidence suggests that despite the challenges inherent in real estate transactions, builders like WTC Noida Development Company Limited can often successfully defend their positions against unjust claims. Therefore, buyers are advised to seek reliable information and engage in independent research to form educated perspectives about builders they might consider.

This table provides an analysis of individual cases that contributed to the summary above. Click on any row to expand and view complete details, and use the "Show More" button to load additional rows as needed.

Case Number State Summary Case Topic Detailed Summary Appellant Name Respondent Name Source
RERA/AdCNo 0081 OF … Not provided The case was dismissed due to non-appearance of t… Non-appearance of c… {"appellant_claim": "Not provided", "respondent_c… Arvinder Singh WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgementsByAO\2023\N3005\/20230612FormN_OJbyAO4e18c332-3c66-4893-b620-b18fc86971a1.pdf
RERAYGC No.0085 of … Not provided The case was dismissed for want of prosecution as… Want of prosecution {"appellant_claim": "Not provided", "respondent_c… Ors WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgements\2022\M2324\/20221207FormM_OJbyAuth64bf5992-25bd-4aa8-9185-d3865157cca7.pdf
Review Application.… Uttar Pradesh The review application was rejected as the learne… ["Review applicatio… {"appellant_claim": "The review applicant sought … Priyadarshini Misra WTC Noida Developme… ['https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy82NDY1MjgxNTU2LTIwMjJyZXZpZXcucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8yODA3ODQxNTU2LTIwMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy85NzAwNHJhIDE1NTYgMjAyMi5wZGY=', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy83MDUzNTNyYSAxNTU2IDIwMjAucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy8xMTUyOTByYSBubyAxNTU2IDIwMjIucGRm', 'https://efilingreat.up.gov.in/upreat/order_view.php?path=L3VwcmVhdF9kb2N1bWVudHMvb3JkZXJzX2RvYy83OTQ5ODAxNTU2LTIwMjIucGRm']
RERA/ AdCNo 0136 OF… Not provided The complainant and respondent entered into a wri… ["Settlement"] {"appellant_claim": "Not provided", "respondent_c… Sandeep Chaudhary WTC Noida Developme… https://rera.punjab.gov.in/rera/rwdataOrdersJudgementsByAO\2022\N2319\/20220224FormN_OJbyAOd5b8a2f2-5657-4985-a280-293610c3bccc.pdf
CMP/Gandhinagar/190… Gujarat The complainant sought to recover the amount paid… ["Unripe complaint"… {"appellant_claim": "The complainant sought to re… Anju Shatrughan Sar… WTC Noida Developme… https://drive.google.com/uc?id=1Lx3xgjyUJxpg1QOIepA28HwjUupKIKOL